FIELD VERIFICATION REPORT OF SCHEME SPA, VALUE CHAIN (2010-11) IMPLEMENTED UNDER MSAM. DALU & BETASING C&RD BLOCK. Presented by: Shri Kennedy Lamare Programme Manager, FFDA. DALU BLOCK. Smt. Senggi Sangma.
E N D
FIELD VERIFICATION REPORT OF SCHEME SPA, VALUE CHAIN (2010-11) IMPLEMENTED UNDER MSAM DALU & BETASING C&RD BLOCK • Presented by: Shri Kennedy Lamare • Programme Manager, FFDA
DALU BLOCK Smt. SenggiSangma Remarks: The pond was well maintained. Stocking done with 5-6 kg IMC and EMC during july. Harvesting was also done once (30-40 kg)
DALU BLOCK Shri Blis M. Marak Remarks: The project was found to be very good. He was also given the information about about the optimum stocking density of fishes.
DALU BLOCK Shri Romanath A. Sangma Remarks: The project was found to be good where from it is known that the partners has already earn Rs.12000/- income by selling his produce in the local market which gives him an extra income support to his family.
DALU BLOCK Shri TuwelsonMarak Remarks: He was instructed to expand his pond which he will be able to complete by the next two months.
DALU BLOCK Shri Marthin R. Marak Remarks: The pond was well maintained and the production was also good.
DALU BLOCK Smt. Mihilda M. Marak Remarks: Construction works still going on and target completion time by the end of this month.
DALU BLOCK Smt. Sokuntala Koch Remarks: 2nd installment has not been released.
DALU BLOCK Shri Sabin D. Sangma Remarks: The partner seems to be very interested in fish farming and plan to construct one more pond next to the existing one.
DALU BLOCK Shri MolithMarak Remarks: Harvesting was done periodically for own consumption. The project was found to be quite good.
DALU BLOCK Shri BikasHajong Remarks: Recently finished and construct another pond next to the existing one.
BETASING BLOCK Smt. EnithryMarak Remarks: The pond get dried up completely during the last week of February so complete harvesting was done therefore could not get good fish production.
BETASING BLOCK Smt. BibianaSangma Remarks: Harvesting was done periodically with an estimated production of about 10-15 kg/netting. The pond is well maintained.
BETASING BLOCK Smt. Polina A. Sangma Remarks: The pond get dried up by the time he complete his project and so could not stock the fish seeds.
BETASING BLOCK Smt. Probilla A. Sangma Remarks: Well maintained but there is no more space for further expansion.
BETASING BLOCK Smt. Melidish Ch. Marak Remarks: The pond was not well maintained so the partner was told to do same and stock the fishes.
BETASING BLOCK Smt. Hilda A. Sangma Remarks: Harvest has not been done. The project was also found to be good.
BETASING BLOCK Shri Sanjay Hajong Remarks: Less water due to lesser depth of the pond so he was suggested to increased the depth of the pond.
BETASING BLOCK Shri Rajiv Hajong Remarks: Harvesting was done twice with an average catch of 20-30 kg per netting. This project was also found to be good.
BETASING BLOCK Shri Saburam Koch Remarks: Partial harvesting was done with a catch of 40-50 kg. This project was also found to be good.
BETASING BLOCK Smt. Rishimoni Koch Remarks: The project was found to be good and moreover the partner had already construct another pond adjacent to this pond.
BETASING BLOCK Shri Rajkumar Koch Remarks: Harvesting was done periodically for own consumption. Area available for further expansion of the existing pond for increasing production.