10 likes | 120 Views
U.S. ARMY PROJECT 2002-2003. In May 2002 RMR was the successful bidder for the U.S. Army to deliver two (2) completely refurbished GP-9 locomotives. Both locomotives had to be completely re-manufactured to Military Specifications.
E N D
U.S. ARMYPROJECT 2002-2003 • In May 2002 RMR was the successful bidder for the U.S. Army to deliver two (2) completely refurbished GP-9 locomotives. • Both locomotives had to be completely re-manufactured to Military Specifications. • The overhaul included new High and Low voltage cabling and wiring plus a state of the art wheel slip control system. The trucks and car body were remanufactured to original OEM specifications. • The first locomotive was to be delivered to the Army in January 2003, with the second locomotive to be delivered in May 2003. • Both locomotives were delivered ahead of schedule by three (3) months. • The contract included delivery of complete wiring and mechanical diagrams, one (1) year supply of consumables, various spare parts and scheduled maintenance documentation.