100 likes | 197 Views
BMLD refurbishing. CERN, June 19, 2006 ATLAS Muon week. G. Iacobucci and G. Chiodini INFN Bologna and Lecce for the RPC group. Reason for this work:. Our RPC units have very small leakage currents (<<1 m A).
E N D
BMLD refurbishing CERN, June 19, 2006 ATLAS Muon week G. Iacobucci and G. Chiodini INFN Bologna and Lecce for the RPC group
Reason for this work: • Our RPC units have very small leakage currents (<<1 mA). • This was achieved by requiring General Tecnica to install a c-shaped p.e.t. profile around the gas gaps. However, the early gas volumes were produced without this implemenent. These are 107 units out of the 116 which were mounted in 30 BMLD stations (26 double-unit and 4 single-unit stations) BMLD refurbishing - G. Iacobucci, G. Chiodini
It was therefore decided to “refurbish” the 107 RPC units of the 30 BMLD stations by opening them and by: 1. installing the c-shaped p.e.t. profile around the gas gaps, to reduce almost to zero the leakage currents 2. installing a 14 mm wide aluminum tape on top of the c-shaped p.e.t. profile, to build an internal Faraday cage to further shield the strips against external noise (this implement was adopted for the BOL units and proved to be very effective) BMLD refurbishing - G. Iacobucci, G. Chiodini
Overview of the work: It required a lot of hard work which involved many people: • Bring the stations to BB5 (Stephanie, Joerg + Logistics group) • dis-assemble a station (Frascati team) • uncable the two planes, separate the units (BB5 assembly team) • refurbish the units (“Refurbishing team”) • make a full test of the units (A. Salomon) • re-cable the planes • assemble back the station • pretest + test with cosmic rays ... essentially all of BB5 ! The “refurbishing team”, Gabriele, Peppe, P. Giusti, Givi, Michele and R. Perrino thanks them all BMLD refurbishing - G. Iacobucci, G. Chiodini
Work done on each unit: Once the “naked” units were available (thanks to the heroic effort of the BB5 assembly team which added this work to the usual heavy load they have and to the Frascati technicians) we proceeded in the following way: • take a test-pulse run (we dropped this test after few weeks, as we realized we did not produce damage to the units) • open the unit (… how many rivets!) • apply c-shaped p.e.t. profile and aluminum tape • check strip panels for dead channels (RF test) • re-built the unit (put rivets in position) • take a test-pulse run to check for dead channels • if ok: “close/fix” the rivets • flush and test the unit at 9.6 kV to hunt for dead channels by single rates and to measure the gap and leak currents. BMLD refurbishing - G. Iacobucci, G. Chiodini
Criteria to accept an RPC unit We required: • in each strip panel: < 2 dead h strips and < 3 dead f strips • in each gas volume: gap current < 4 mA/m2 leakage current < 1 mA The RPC unit was re-opened if these requirements were not met After we found all the small trapdoors preventing us from doing a high-quality job (special thanks go to R. Cardarelli) , we managed to refurbish an average of two units/day with a team of 1-2 physicists and 2-3 technicians (top: 13/week) (although our Lecce + Bologna technicians rarely left BB5 before 8 p.m.) BMLD refurbishing - G. Iacobucci, G. Chiodini
Results: leakage currents Essentially consistent with zero, for most of the units, except for ~10 gaps with ~0.3 mA 4 gaps with 0.5 < ileak <1 mA acceptance limit of 1 mA BMLD refurbishing - G. Iacobucci, G. Chiodini
Comparison before/after: Well within 1/10 of the first bin ! BMLD refurbishing - G. Iacobucci, G. Chiodini
Dead strips: We checked ~40000 channels 3 times. • Number of dead strips below 1%, both h and f • Same level as before BMLD refurbishing - G. Iacobucci, G. Chiodini
Conclusions That’s all folks BMLD refurbishing - G. Iacobucci, G. Chiodini