Oil Load Serving Study Update. August 18 th , 2011. OIL LOAD SERVING STUDY AREA. WILLISTON LOAD POCKET. ASSUMPTIONS. MCDC LIMITED TO 100MW E-W MDU PEAKERS OFF LEWIS & CLARK GEN ON WIND OFF CULBERSTON OFF BUT AVAILABLE FOR PRIOR OUTAGES FORT PECK GENERATION = 35MW, MAX ~135MW
E N D
Oil Load Serving Study Update August 18th, 2011
ASSUMPTIONS MCDC LIMITED TO 100MW E-W MDU PEAKERS OFF LEWIS & CLARK GEN ON WIND OFF CULBERSTON OFF BUT AVAILABLE FOR PRIOR OUTAGES FORT PECK GENERATION = 35MW, MAX ~135MW WINTER PEAK LOADS
CHALLENGES VOLTAGE STABILITY LOW VOLTAGE, POWER QUALITY, POOR “PROFILE” REGIONAL LOAD INCREASES 115KV LINE OVERLOADS MAINLY FEEDING WILLISTON POCKET
EXISTING SYSTEM Charlie Creek-Williston at 115kV Charlie Creek 345kV Line 230kV Line 115kV Line
BASELINE FORECAST Existing System Limit Until July 2012
July 2012 Charlie Creek-Williston at 230kV
Williston-CCR 230 & Cap Additions BASELINE FORECAST
2013 Networked 115kV Des Lacs
Williston SVC BASELINE FORECAST
RUN CULBERTSON PRE-CONTINGENT BASELINE FORECAST
ADD 345KV BASELINE FORECAST
BASELINE FORECAST Williston-CCR 230 & Cap Additions Networked 115kV
BASELINE FORECAST Networked 115kV Williston-CCR 230 & Cap Additions
BASELINE FORECAST Networked 115kV Williston-CCR 230 & Cap Additions