Coolview. Project Kick Off Meeting July 24, 2007. What is Coolview ?. Project that needs a better name The replacementenhancement of two critical services OPAC (HIP no long primary customer presentation) Database searching – enabling a more robust federated search. Why Change.

yorick
Download Presentation

Coolview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Coolview Project Kick Off Meeting July 24, 2007

  2. What is Coolview? • Project that needs a better name • The replacement\enhancement of two critical services • OPAC (HIP no long primary customer presentation) • Database searching – enabling a more robust federated search

  3. Why Change • Existing deficiencies of significant impact • Unable to search multiple database resources • Unable to easily search and use the existing database resources and the catalog • Lack of basic customer friendly functionality • no spell check • no relevancy ranking • confusing and ineffective search mechanism (avoid the huh factor) ????????????

  4. Team Makeup

  5. Change to What? • Sirsi upgrade (when and what)? • Opensource? • Aquabrowser – emerged as clear direction, truly no other unless switch ILS

  6. Project Scope • Deliverables (when is this called complete) • Project measures of success • Project risks • Assumptions • Feedback?

  7. Aquabroswer • Let’s take a look

  8. Scope – Team Feedback • Feeback • Additions/edits/comments……

  9. Timeline • July/Early August • finalize contract • Push for mid/late Sept implementation • August • Setup infrastructure • Procure and install server • Sept • Initiate installation • October • Complete installation • Testing and refinement • November • Staff orientation • Nov/Dec • Go live for public

  10. Timeline – Team Feedback • Comments/changes needed to timeline?

  11. Meeting Deliverables Met? • confirmed project team members and how project impacts them • have an awareness of what the project is about • drafted the project scope • developed a rough project schedule

  12. Next Steps • Pull together • Final contract • Vendor references • Legal review? • Target • contract signed by end of July