Standing Committee on Appropriations (SCOA) ASIDI PROGRESS REPORT 18-02-2014 1
Contents • ASIDI TARGETS • ASIDI MTEF ALLOCATIONS • ASIDI Implementation Stages, Deliverables and Estimated time • ASIDI Plans and Actual Progress • ASIDI Overall Financial Report • Way forward 2
ASIDI Plans and Actual Progress (Inappropriate Schools) • On the implementation of new schools • 329 schools are at various stages of implementation. • Included in the 329 is 49 schools which are now occupied by learners and teachers • Commitments to date since inception of the programme are at approx. R7.7bil • Approximately 190 schools remain on ASIDI. • These schools are all in the EC and • Are affected by rationalisation and mergers processes • Progress on the 329 schools is reported in the following slides. 8
ASIDI Plans and Actual Progress DBSA • 44 schools have been handed over. • 5 remaining schools are at various stages of progress as follows: 9
ASIDI Plans and Actual Progress DBSA (cont) • Batch 2 schools are at stage3: contractor procurement. • The summary of the implementation plan is indicated below. 10
ASIDI Plans and Actual Progress IDTEC (Cont.) • On the 36 ACT schools, the following schedule was provided to DBE in July 2013: • The progress is running behind schedule, works should have started in November 2013 • PSPs appointed, ACT technologies identified and Appointment of contractors in progress. 12
ASIDI Plans and Actual Progress JET • Temporary Mobile Structures: • The tender for mobile structures to replace dilapidated schools in the Eastern Cape has been withdrawn. • Communities have made it clear to the DBE that they would prefer to wait for brick and mortar structures that are planned for in the ASIDI programme. • Issues regarding the 6 schools • The projects are almost ready to advertise a tender for contractors. 17
ASIDI Plans and Actual Progress DBSA FS • On the 11 schools, DBSA is at procurement of contractors stage. • Start dates below refers the beginning of stage 3:design. 18
ASIDI Plans and Actual Progress FSPED • On the 9 schools, FSED started with procurement of PSPs in September 2013 and no progress has been made since. • Letters of notice have been sent to FSED. 20
ASIDI Plans and Actual Progress AAS • Below is a typical plan for the building of the three schools in KZN 21
ASIDI Plans and Actual Progress DBSA (L) • On the 3 Limpopo schools, DBSA is at procurement of contractors stage. • Planned dates below refer the beginning of stage 3:design. 22
ASIDI Plans and Actual Progress DBSA (M) • On the 5 Mpumalanga schools, DBSA is at stage 5: construction of works. • Planned dates below refer the beginning of stage 5. 23
ASIDI Plans and Actual Progress DBSA (NW&NC) • DBSA is at procurement of contractors stage. • Starts dates below refer to the beginning of stage 3:design. 24
ASIDI Plans and Actual Progress WCED • WCED is currently at stage 4:Contractor procurement • Revised PC dates are based on approved extension time claims. • PC1 = Practical Completion of Building works • PC2 = Practical completion of External works (Sport fields, landscaping and irrigation) 26
ASIDI Plans and Actual Progress (Water, Sanitation and Electrification) • On the provision of sanitation to schools • All ASIDI sanitation projects have been allocated to Implementing Agents • 159 schools are at stage 5: construction of the works and • 290 schools are at stage 4: procurement of contractors. • To date 226 schools have been provided with sanitation. 27
ASIDI Plans and Actual Progress (Water, Sanitation and Electrification) • On the provision of water to schools • All ASIDI water projects have been allocated to Implementing Agents • 197 schools are at stage 5: construction of the works and • 488 schools are at stage 4: procurement of contractors. • To date 232 schools have been provided with water. 28
ASIDI Plans and Actual Progress (Water, Sanitation and Electrification) • On the provision of electricity to schools • All ASIDI electrification projects have been allocated to Implementing Agents • 367 schools are at stage 3 & 4: design and procurement of contractors. • To date 150 schools have been provided with electrification. 29
ASIDI Overall Financial Report Expenditure against NT Allocation: ASIDI Allocation 2013/14: R1 900 000 000 Actual Expenditure at 2013/12/31 (Incl. Accruals): R 907 497 685 (49%) Balance at 2014/01/31: R 992 502 315 (51%) Expenditure incl. WC DOE against NT Allocation: ASIDI Allocation 2013/14: R2 400 000 000 Actual Expenditure at 2013/12/31 (Incl. Accruals): R1 215 334 273 (51%) Balance at 2014/01/31: R1 184 655 727 (49%) 30