WisDOT use of FieldManager ® Suite

WisDOT use of FieldManager ® Suite. David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October 7, 2008. WisDOT and FieldManager ®. History Statistics WisDOT Process Beyond FieldManager ®. History.

yoshi
Download Presentation

WisDOT use of FieldManager ® Suite

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WisDOT use ofFieldManager® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October 7, 2008

  2. WisDOT and FieldManager® • History • Statistics • WisDOT Process • Beyond FieldManager®

  3. History • 1994 WisDOT evaluates Trns.port (BAMS) • Include look at Iowa FieldBook® • 1997 Implement Trns.port and FM/FB 1.97 • Required 20 diskettes for FM/FB install • First FieldNet® service managed byInfo Tech • 375 users (255 DOT, 120 consultants)

  4. WisDOT Contract Management System

  5. History • 1999 upgraded to FM/FB 3.0 (ITI/MDOT) • First state to “beta” test in production • 410 users • 2003 migrated from Mainframe to C/S • Discontinued ITI FieldNet® service • Implemented FieldNet® in-house • 440 users (215 DOT, 225 consultants) • 2008 upgraded to FM 4.4a, FN 3.0a • 490 users (240 DOT, 250 consultants)

  6. Statistics • 300+ LET contracts in 2007 • $750 mil program • 5 region offices • 40+ vouchers processed daily

  7. Product Users

  8. WisDOT Process

  9. Organization

  10. Contract Assignment • CO send awarded contracts to 5 regional office contacts:CAS>FN>FM • Regions transfer contract to project engineer:FM>FN>FM • Project engineer exports toFB and FP: FM>FB/FP

  11. Payment Estimates • Project engineer generates andsends estimate for approval: FM>FN • Supervisor or delegate approves estimate: FN>CAS • Voucher processes andrefresh sent toPE: CAS>FN>FM

  12. Contract Modifications • Project engineer generates and sends Cont. Mod. for approval: FM>FN • Supervisor or delegate approves Cont. Mod.: FN>CAS OR • PE generates and approvesCont. Mod.: FM>FN>CAS

  13. Other Processes Used • Stockpiles • IDR’s • Daily diaries • FieldBook® for inspectors(as necessary)

  14. Other Notes • PC specification for consultants • Hardware requirements • Region IT support installs/uninstalls software • DSL for FieldNet® connection • Some by phone • Regional IT and contract specialist

  15. Beyond FieldManager®

  16. Field Information Tracking • Merged with FM database • Additional contract information • Used by project engineer

  17. Field Information Tracking

  18. Project Tracking • Contract data from CAS, FM, FIT • View and update • DBE • Labor Compliance • Warranty • R/R

  19. Project Tracking

  20. Materials Information Tracking • Project data from CAS • 5 standard field reports • Used by materials technician

  21. Materials Information Tracking

  22. Materials Tracking System • Physical test results • Entry • Verification • Used by central and consultant labs

  23. Materials Tracking System

  24. Materials Reporting System • Contractor entry of test results • IRI ride • Structures • Pavement • Project engineer validation of test results

  25. Materials Reporting System