290 likes | 610 Views
2. Outline. CEBS ? role and tasksIndustry reaction and scope of the Guidelines on Validation (GL10)The approval and post-approval process 3.1. Application, assessment, decision (approval process)3.2. The cooperation and coordination process between supervisorsSelected items of the Assessment process4.1. Partial use and Roll-out4.2. Use test4.3. Rating assignment and risk quantification (PDs, LGDs, CFs)4.4. Back-testing and benchmarking (incl. Low default portfolios)4.5. Internal governanceSummary.
E N D
1. Validation and Approval of IRB Systems under the CRD – Guidelines on the implementation, validation and review of AMA and IRB approachesThomas Dietz, CEBS secretariat
PRMIA Workshop | 18 September 2006
2. 2 Outline CEBS – role and tasks
Industry reaction and scope of the Guidelines on Validation (GL10)
The approval and post-approval process
3.1. Application, assessment, decision (approval process)
3.2. The cooperation and coordination process between supervisors
Selected items of the Assessment process
4.1. Partial use and Roll-out
4.2. Use test
4.3. Rating assignment and risk quantification (PDs, LGDs, CFs)
4.4. Back-testing and benchmarking (incl. Low default portfolios)
4.5. Internal governance
Summary
3. 3 1. CEBS – role and tasks CEBS is not a single European regulator, but a coordination body comprised of high level representatives of the 25 EU supervisory authorities (observers from ROM, BG, LI, Iceland and NO) responsible for banking supervision
Guidelines are one of the CEBS tools to achieve convergence in supervisory practices
Convergence is one of the main tasks of CEBS according to the European Commission decision in November 2003
Convergence means that the national supervisory authorities implement and apply European banking legislation as homogenously as possible
4. 4 1. CEBS – role and tasks (2) Convergence is in the interest of both the supervisory authorities (avoiding regulatory arbitrage) and the industry (level-playing field, especially important for cross-border groups)
Guidelines are not legally binding, but national supervisors have a high interest to respect them
Guidelines affect the industry since CEBS sets out expectations towards the national supervisors concerning what they should expect from their institutions
5. 5 2. Industry reaction and scope of GL10 During the drafting process meeting with experts nominated by the CEBS Consultative Panel to get informal input (two meetings on AMA, one on CP10 as a whole)
Two rounds of public consultation (mid-July to end October 2005 and end January until end February 2006)
Positive Reactions (among others):
Framework proposed for cooperation between home and host well-reasoned
Flexibility introduced for institutions which have already completed preliminary applications (good faith clause)
Principle of proportionality
6. 6 2. GL10 - Industry reaction (2) Negative Reactions (among others):
Instead of principles based approach too many details (“not necessary to reach convergence”) and too prescriptive
indicative examples will lead to tick-box approach (N.B.: some associations asked for more details/examples)
Internal Governance rules too burdensome
Proposals are too conservative and superequivalent to the CRD
Strong disagreement with general concept of downturn LGDs
CEBS reaction
40% of the proposed changes in the first round of consultation taken on board in CP10 revised, 50% of the proposed changes in the second round in the final Guidelines
7. 2. Scope – Underlying CRD requirements
Under the IRB Approach use of own estimates of risk parameters for the calculation of the institution’s capital requirements
-> adequacy of the resulting capital requirements depends critically on the adequacy of the estimated risk parameters
No use of AMA or IRB approaches for regulatory purposes without prior approval
-> explicit application necessary
Approval only if the competent authority is satisfied that the institution's systems for managing and rating credit risk exposures are sound, are implemented with integrity, and meet the requirements listed in Article 84 and Annex VII, Part 4 of the CRD.
-> supervisory assessment necessary
Guidelines on validation supposed to support the national supervisors’ work when dealing with the application, decision and especially the assessment process
8. 8 3. Approval and post-approval process – Structure of GL10 Structure of GL10 – a typical approval process
9. 9 3. Approval process – Art. 129 (2)
Art 129 (2) of the CRD: decisive new element in the relations between consolidating and host supervisors, strengthening the responsibility of the consolidating supervisor:
“In the case of applications […] submitted by an EU parent credit institution and its subsidiaries, or jointly by the subsidiaries of an EU parent financial holding company, the competent authorities shall work together, in full consultation, to decide whether or not to grant the permission sought and to determine the terms and conditions, if any, to which such permission should be subject. […] The competent authorities shall do everything within their power to reach a joint decision on the application within six months. […] In the absence of a joint decision between the competent authorities within six months, the competent authority referred to in paragraph 1 shall make its own decision on the application.
De facto non-agreement after six months is unlikely. Supervisors will do everything to come to a common decision after the six-months period and will establish adequate cooperation procedures, already in the pre-application phase
10. 10 3.1. Approval process – Application
Required minimum documentation for an application is divided into five parts:
Cover letter requesting approval
Documentation of used or planned rating systems
Control environment of the rating systems, implementation procedures and IT infrastructure
Implementation plan (including Roll-Out) and details on permanent partial use
Self-assessment
Cover letter and supporting material must enable the supervisor to make an initial supervisory assessment of the application, and to develop a risk-based plan for a more thorough assessment
The six months clock is started upon receipt of a complete application
11. 11 3.1. Approval process - items to be covered in the assessment
Assessment? -> the supervisor has to assess whether or not he is satisfied that the institution’s systems meet the standards listed in Article 84 in accordance with the requirements of Annex VII, Part 4 of the CRD.
IRB approach must have been “validated” by the institution (self-assessment), before supervisor starts its own assessment.
Issues to be assessed by supervisors:
Methodology and documentation: rating system methodology and the quality of internal documentation supporting the rating system
Data quality: quality of data and databases being used for the development of the rating systems, in the rating assignment process, and in the estimation of risk parameters, along with any other databases needed to calculate minimum regulatory capital
12. 12 3.1. Assessment process – items to be covered (2)
Issues to be assessed by supervisors (continued):
Quantitative procedures: quantitative information relating to performance, validation, and monitoring of rating systems.
Qualitative procedures: perform an overall assessment of the quality of the internal model and assess compliance with the qualitative minimum regulatory requirements (use test, internal governance, the role of senior management, the adequacy of internal controls).
Technological environment: reliability and integration of systems, the functionality of the model, and the quality of information provided by systems.
13. 13 3.1. Approval process and documentation – Decision
End of application process: decision/permission
Decision: final act in the approval process, as a result of the consultation between the competent authorities.
Permission: legal form by which the decision, determinative and legally binding on the competent authorities, comes into force in their respective legislation (transposition of the full content of the decision under the standing legal provisions of each country)
Decision document may contain certain terms and conditions or may also cover recommendations for the possible improvement of any imperfections revealed during the assessment process.
14. 14 3.2.Supervisory cooperation and coordination As much cooperation as possible between consolidating and host supervisors to avoid a duplication of work (which supervisors to be involved, respective roles and responsibilities, allocation of specific tasks)
Basic idea: Streamlining 129 (2) process by a common understanding with regard to an application, its assessment and the decision on it
Developing an overall supervisory plan of action (including time table, communication strategy and escalation process -> exchange of information necessary already at a very early stage)
15. 15 3.2.Supervisory cooperation and coordination (2) Consolidating supervisor as central point of contact (also for the group) and as central coordinator, e.g.:
Assessing whether application is complete
Coordinate the on-site inspection/off-site assessment of the group‘s application
Determining the contents of the decision document
Communication of the decision to the group
sharing of tasks and resources (e.g. host supervisor reviewing locally developed models)
Monitoring of the roll-out plan and of the terms and conditions in the post-approval phase as well as processing of possible preliminary applications in the transition period before the CRD has come into force will be conducted by the supervisors involved (in the spirit of Art. 129 (2))
16. 16 4. Selected items of the Assessment process 2. Cooperation procedures, approval and post-approval process
2.1.Co-operation between supervisory authorities under Art. 129 (2)
Cross-reference to CP09 (“Home/host”)
2.2.Approval and post-approval process
Application
Supervisor’s assessment
Decision and permission
Post approval process
Transition period
4. Supervisor’s assessment for Operational Risk
4.1. Partial Use combinations
4.2. Simpler Approaches (TSA, ASA, BIA)
4.3. AMA
4.3.1.Roll-out
4.3.2. Use test
4.3.3. Data
4.3.4. Guidelines for AMA Quantitative issues, internal validation, risk transfer mechanisms and allocation
AMA four elements
Consistency of risk measurement system
Expected loss, correlation, Insurance and other risk transfer mechanisms
Internal validation of risk measurement and management processes
Allocation methodology
4.3.5. Internal governance
17. 17 4.1 Partial use and Roll-out – permanent partial use Permanent partial use allowed for the ‘institutions’ and/or ‘central governments and central banks’ exposure classes (if number of material counterparties is limited and if unduly burdensome to implement a rating system for these counterparties).
No further guidance on this given in GL10 -> onus of the bank to justify its choice
Other possibility for permanent partial use: exposures in non-significant business units and exposure classes that are immaterial in terms of size and perceived risk profile
In CP10 no quantitative thresholds set for significance and immateriality, but both should be measured by either Exposure value (indicator of size) or risk-weighted exposure amounts (risk profile), measuring of significance and immateriality at least at the aggregated level
Institution needs to have systems and procedures for monitoring materiality issues in a timely and appropriate manner
18. 18 4.1. Partial use and Roll out - Roll out
General approach in the CRD (Art. 85 (1)): once an institution decides to apply the IRB approach, all exposures should be covered by this approach. Temporary or permanent partial use is possible, however (e.g. because extension of rating systems to some parts of their business may be unduly burdensome)
Article 85 of the CRD gives institutions the possibility of implementing the IRB Approach sequentially across different exposure classes (Roll-out).
Nevertheless, institutions should already be using the IRB approach for at least a portion of their business when they apply for approval (assessed by supervisors by either qualitative or quantitative rules – Risk Weighted Exposure Amounts or Exposure values)
Article 85(2) requires that IRB implementation “shall be carried out within a reasonable period of time”.
Application already contains a complete roll-out plan, so no further Article 129 application will be needed as each portfolio is rolled out, with the possible exception of a merger or acquisition. New decisions may be necessary, however.
19. 19 4.2. Use test
Use test (Art.84(2)) refers to the time after the initial approval: information used in or produced by its rating system to determine regulatory capital requirements has also to be used in the course of conducting its regular business, particularly in risk management
Experience test (Art.84(3) and (4)) sets out minimum requirements for rating systems in the time period prior to the institution’s qualification to use the IRB approach (one up to three years): Rating systems have to be broadly in line/broadly consistent with the minimum requirements for internal risk measurement and management purposes and the systems for risk parameter estimation
-> institutions need to show that they are familiar enough with the systems (The rating systems used prior to approval do not need to have been fully identical to the ones used before)
-> rating systems, ratings, and default and loss estimates designed and set up with the exclusive aim of qualifying for the IRB, and used only to produce the data necessary for the IRB approach, are not allowed.
Data inputs and system’s outputs (ratings and risk parameter estimates used in calculating capital requirements) must have a substantial influence on the institution’s decision-making and actions, but – in order not to hamper industry development – do not have to be completely identical for internal purposes such as pricing.
20. 20 4.3. Rating assignment and Risk quantification – PD
In practice a variety of different methodologies in use to assign obligor grades (statistical models, heuristic models, causal models, or other mechanical methods). Institutions can combine various methodologies for assigning obligor grades. (For example, they can combine statistical models with expert judgement systems.)
Similarly, institutions may use different estimation methods (and different data sources) to estimate PDs for obligor rating grades or pools, including
mapping internal rating grades to the scale used by an ECAI
statistical default prediction models
or other estimation methods or combinations of methods.
21. 21 4.3. Risk quantification - LGD
Realised LGDs are ex-post values that can be applied to a facility grade or pool. Estimated LGDs are based on realised LGDs predicting a long-run forward-looking recovery rate for the facility grade or pool, taking both current and future economic circumstances into account
Realised LGD might be zero or even positive (e.g. technical default or selling of a collateral to a price higher than the outstanding amount). Even if positive outcomes in the recovery processes have been observed and can be explained, the estimated LGD used to calculate capital requirements must not be less than zero.
In principle, supervisors do not require any specific technique for LGD estimation (or for estimating other IRB parameters). However, institutions will have to demonstrate that the methods they choose are appropriate to the institution’s activities and the portfolios to which they apply.
22. 22 4.3. Risk quantification – Downturn LGDs
Institutions should produce an LGD estimate appropriate for an economic downturn (‘Downturn LGD’) if this is more conservative than the long-run average.
Three-stage process:
Identify appropriate downturn conditions for each supervisory exposure class in each jurisdiction
Identify adverse dependencies, if any, between default rates and recovery rates
Generate LGDs being consistent with identified downturn conditions
Supervisors recognise Data problems! Therefore: While institutions are building better data sets and developing more experience in estimating downturn LGDs, supervisors may choose to direct them to focus their efforts on types of exposures for which they believe the downturn effect is of special concern.
23. 23 4.3. Risk quantification – Conversion factors
Conversion factors are part of the Exposure at Default calculation
Definition: “conversion factor” means the ratio of the currently undrawn amount of a commitment that will be drawn and outstanding at default to the currently undrawn amount of the commitment
Not much guidance, since industry practice in this area is still at an early stage. However, four indicative examples are given how to estimate CFs. One of them (momentum approach) can only be accepted for a transitional period of time
Controversial discussion: For what instruments is the estimation of own CFs allowed/obligatory? (No estimation for 100% risk factors as listed in Basel framework)
24. 24 4.4. Backtesting and benchmarking – High level principles of validation High Level Principles of the Basel Accord Implementation Group (AIG):
‘Validation’ encompasses a range of processes and activities that contribute to an assessment of whether ratings adequately differentiate risk and whether estimates of risk components (such as PD, LGD, or CF) appropriately characterise the relevant aspects of risk.
The credit institution has primary responsibility for validation
Validation is an iterative process and there is no single validation method; Validation should be subject to independent review
Validation should encompass both qualitative and quantitative elements (A validation process needs to contain a mix of developmental evidence (assessing the logic of the approach, its conceptual soundness, statistical testing performed prior to use), benchmarking and process verification (comparisons to relevant alternatives, verification that the process is being applied as intended), and outcomes analysis (backtesting)
25. 25 4.4. Backtesting and benchmarking
The CRD explicitly requires institutions to use both Backtesting and Benchmarking tools in their validation process (Annex VII, Part 4, Paragraphs 110 and 111).
Backtesting: checking the performance of the risk rating systems estimates by comparing realised risk parameters with estimated risk parameters. When backtesting is hindered by lack of data or insufficient quantitative information, institutions will need to rely more heavily on additional qualitative elements such as quality control tests (qualitative validation)
Benchmarking: comparing the outputs of the reviewed risk rating systems with the outputs of other risk rating systems with external information (other institutions or ECAIs).
In cases where a lack of internal or external data prevents the proper use of these techniques, institutions should apply a higher margin of conservatism in their estimations.
26. 26 4.4. Backtesting and Benchmarking – Low default portfolios
Low-default portfolios are portfolios with few or no defaults observed. Low-default portfolios can arise under different circumstances (high-quality borrowers or small number of borrowers)
In the case of systemic Low default portfolios ((data unavailable for all institutions) Exposures in low-default Portfolios should not necessarily be excluded from the IRB approach simply because of the absence of sufficient data to validate PD, LGD and CF estimates on a statistical basis.
Such exposures may be included if institutions can demonstrate that the methods and techniques applied to estimate and validate PD, LGD and CF constitute a sound and effective risk-management process and are employed in a consistent way.
Institutions will be required to use appropriate conservatism in risk parameter estimation
27. 27 4.5. Internal Governance – some definitions ‘Management body’ as defined in the CRD. The use of the term ‘management body’ does not advocate any particular board structure; represents the top management level of an institution
Senior management should be understood to represent the level of management below the management body
GL10: National authority can define which function of the management body is responsible for the tasks and responsibilities listed in the internal governance section
Proportionality principle: Assessment of an institution’s organisational structure, internal governance, and internal control systems should take into account their size and the complexity and nature of their business (could include a “comply or explain” approach)
28. 28 4.5. Internal governance – CRCU
CRCU “shall be responsible for the design or selection, implementation, oversight and performance of the rating systems” (Annex VII, Part 4, Paragraph 127)
Credit Risk Control function (CRCF) should be independent from the business lines it monitors and controls.
in most cases organisational CRCU and CRC identical (consequently CRCU would encompass only people responsible for fulfilling the Credit Risk Control function), but CRCU could encompass both people responsible for the design of the model and for its independent review
Counterbalance in this case: any potential for lack of objectivity to be offset with rigorous controls, administered by Internal Audit
Basic idea of Internal audit: control of the control function. It must not be directly involved in model design/selection and not in day-to-day operations (e.g. reviewing each individual rating assignment)
29. 29 4.5 Internal governance – Role of management body and senior management
Management body may – where appropriate - delegate tasks to senior management and/or risk committees
However, no relief for both bodies from general awareness of the IRB framework used by the institution:
management body ultimate responsibility for the IRB framework
senior management ultimate responsibility for developing and implementing it
both management body and senior management should be responsible for approving all material aspects of the rating and estimation processes
Mangement body and senior management to have a general understanding of the institution’s rating systems and detailed comprehension of its associated management reports
30. 30 5. Summary and Outlook
GL 10 was heavily critizised by the industry (too much rules- and not enough principles-based). However, managing an IRB application is a new field for supervisors; rather detailed guidelines were therefore deemed helpful at this stage
Probably most helpful for the industry: common application and decision process, part on Low Default Portfolios
Evolving industry practices and the practical application of these guidelines will enlarge supervisors’ experience. It could turn out that certain elements of the guidelines may not stand the test of time (e.g. unexpected side effects). Supervisors may reflect such additional information for the interpretation of these guidelines.
GL10 will be subject to review following implementation of the CRD, when and where necessary ('maintenance').
Implementation seminars on (e.g.) Article 129(2) applications, Downturn LGD and CF estimations, etc. are scheduled/envisaged.