1 / 24

V.Kain, H. Burkhardt, B.Goddard, W. Hofle, V.Mertens, S. Redaelli, J.Uythoven, J.Wenninger

V.Kain, H. Burkhardt, B.Goddard, W. Hofle, V.Mertens, S. Redaelli, J.Uythoven, J.Wenninger. Injection and Associated Protection Devices. Scope - Contents. Scope: Stage A: limit 43 x 43, 156 x 156 with 9 x 10 10 p + per bunch Only commissioning steps which require set-up with beam

zaide
Download Presentation

V.Kain, H. Burkhardt, B.Goddard, W. Hofle, V.Mertens, S. Redaelli, J.Uythoven, J.Wenninger

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. V.Kain, H. Burkhardt, B.Goddard, W. Hofle, V.Mertens, S. Redaelli, J.Uythoven, J.Wenninger Injection and Associated Protection Devices

  2. Scope - Contents • Scope: • Stage A: limit 43 x 43, 156 x 156 with 9 x 1010 p+ per bunch • Only commissioning steps which require set-up with beam • Injection/SPS extraction interlocking not covered • Commissioning steps are described for one beam • other beam requires repetition of same steps • Time estimate per step in general: 1 – 2 shifts maximum • Not very specific yet about exact values of target parameters • Contents: • Injection commissioning during phase A.1 • Injection commissioning during phase A.2-A.3 • Injection commissioning during phase A.4 • Injection commissioning during phase A.5 *target parameters need to be properly defined

  3. Injection Region LEFT OF IP2 (H plane) Kicker MKI TCDD TCDI Septum MSI TDI MKI +90˚ RIGHT OF IP2 (H plane) TCLIM TCLIA TCLIB

  4. PHASE A.1 First turn

  5. Preparation Phase A.1, pilot intensity, OP/BT • Requirements: • Transfer line re-commissioned with beam • With TED in, then TED moved out • Orthogonal steering available for MSI and MKI • Settings generated for TDI (out, coarse, protect) • Shot-by-shot logging configured • Timing tables verified (BI capture events) • Remove extraction permit at SPS • All TCDIs/TCLIs out • TDI masked (completely IN) • TCDD in point 2 IN • MKI ON, kick disabled • Soft-start done • All screens in, downstream of TED and downstream of MSI • Cameras on BTVSS: first screen in the LHC

  6. First Injections – MKI NOT pulsing Phase A.1, pilot intensity, OP/BT • Enable extraction permit • Injection (MKI disabled): • Beam should arrive at TDI, off-center • Steer if required • orthogonal steering at MSI and MKI already implemented in YASP • Check signals at screens and BPMs (BLMs no losses) • BTVSS, BTVSI1, BTVSI2, BPTX, BPMW, BTVST (in front of TDI) • Steer to have correct offset at TDI on screen • ~ + 30 mm • Verify BLM readings on TDI: • Triggered acquisition of BLM readings • Calibrate parasitically (mGy vs. intensity lost) • Thresholds should not trigger Screen in front of TDI

  7. First Injections – MKI pulsing Phase A.1, pilot intensity, OP/BT • Remove extraction permit – enable MKI, pulse • Enable extraction permit • Inject • Adjust delay such that beam is in middle of waveform • Verify vertical position on BTVST in front of TDI • Steer MKI angle • Beware of BETS constraints • Move TDI to PROTECT position • +/- 7 mm • Remove BIC mask on TDI • Start threading around ring… • (Move out injection screens)

  8. PHASE A.2 - PHASE A.3 Circulating beam – 450 GeV initial commissioning (BI, beam dump,…)

  9. Injection re-steeringPhase A.2, pilot intensity, OP; Phase A.3, 3 x 1010, OP • Phase A.2: after establishing closed orbit: • Inject & circulate • Initial optimisation of injection oscillations: re-steer injections • Phase A.3: high precision orbit measurements: • Inject & circulate • Optimisation of injection oscillations: re-steer injections • Minimise to… De < 0.5 s (results in 12 % emittance growth without damping) *target parameters need to be properly defined

  10. PHASE A.4 450 GeV optics measurements

  11. Injection stability - reproducibility Phase A.4, 3 x 1010, OP • Injected beam: check stability of injection point • Transfer line and MKI effects • Inject & dump • 1000 shots • Use BPMs and BTVs in injection region + BPMs and BTVs before MSI in transfer line • Shot-by-shot, restarting after a couple of days (temperatures, MKI soft-start, …) • Circulating beam at injection • Orbit at injection point/TDI • Beam sizes at injection point/TDI • Looking at nominal cycle only… • Parasitically every time we fill

  12. Aperture in injection region (1) Phase A.4, pilot intensity – 3 x 1010, OP/BT • Aperture bottlenecks in the LHC injection regions: • MSI, Q5, MKI, D2 • → Q5 tilted • + 1 mm on IP side • - 2 mm on IP side • Q5 tight under nominal conditions – n1 = 6.2 • MKI and D2 tight for • Non-kicked injected beam • Kicked circulating beam → beam in the injection kicker rise time gap (~ 0.9 ms) J. Uythoven J. Uythoven: InjWG 07-05 Injected non-kicked beam

  13. Aperture in injection region (2) Phase A.4, 3 x 1010, OP/BT Aperture measurement: MSI and Q5 Use injected beam → inject & dump, TDI out BLMs triggered acquisition mode FBCTs in point 4/point 6 Transfer line knobs in sigma to measure aperture Limited by aperture of MSI Calibrate BLMs at MSI (on TCDIM and MSIs) Aperture measurement: MKI and D2 Use circulating beam → circulate & dump, TDI needs to be in PROTECT Kick circulating beam + scan bump at D2 or MKI BLMs triggered acquisition mode (Take out bumps at the end)

  14. Scan MKI waveform Phase A.4, 3 x 1010, BT/OP • Scan MKI waveform: • Inject & dump • Use screen at TDI (90º downstream) • Scan kicker delay Example: LHC extraction commissioning – SPS LSS6 – 2006 kick delay was changed, position measured with screen.

  15. Injection Matching (1) Phase A.4, 3 x 1010 • Mismatch possibilities – leads to emittance growth and tail repopulation • Emittance growth: • Betatron, dispersion mismatch – measurement of twiss parameters at injection point • Energy, steering mismatch – verify with BPMs around the ring → see Jorg’s talk • Geometry • Tail repopulation: verify with scraped beam from SPS and scrapers in the LHC → stage B Results from simulations: Dominant effect: betatron and dispersion mismatch Emittance growth predicition about 3% Tail repopulation after scraping in SPS

  16. Injection Matching (2)Phase A.4, 3 x 1010, OP/ABP • Oscillation of image on matching screen indicates mismatch • Matching screen in point 3 (will not be there for 2008) • LHC optics needs to be measured • To measure twiss parameters at injection point (dispersion, betas and alfas) • Matching screen turn-by-turn • Screens in injection region • Eventually (= stage B) need to control better than: • Betatron mismatch: l < 1.15 • Dispersion: maximum mismatch of 10 cm, 0.001 rad • Screen matching application: • used for TI 2: • 2 D fit for beam sizes • optics calculated at any point in the • line • same application can be used for • LHC *target parameters need to be properly defined

  17. PHASE A.5 Increasing intensity 4 bunches max injected for 43 x 43 16 bunches max injected for 156 x 156

  18. Operational States? • In this phase injection protection starts to play a role • The systems will be commissioned for a certain envelope • Optics • Emittance • Crossing-/separation angle, experimental magnet polarity • Maximum injected intensity • … • What/who makes sure that the systems are not used outside these “operational states” without re-commissioning or adjusting?

  19. Multi-bunch injectionPhase A.5, 4 x 3 x 1010 or 16 x 3 x 1010, OP/BT • Multi-bunch injection: • Adjust delay for MKI kick • For 16 x 3 x 1010: • Only after setting up the TDI • For 4 x 3 x 1010: TDI roughly set up • Optics knowledge from phase A.4 • Centered Example: LSS4/LSS6 extraction

  20. Setting-up of TDIPhase A.5, 3 x 1010 – 4 x 3 x 1010, BT/collimation team/OP The required setting of the moveable passive protection devices depends on the LHC aperture. Assume 7.5 s. • TDI: • ~ 4m long, ~ 10 m upstream of D1, additional mask in front of D1 (TCDD) • Protects machine against MKI failures • Required setting: 6.8 s • TDI – setting-up • At this stage independent of cleaning collimators • Setting-up like cleaning collimators: covered by Ralph’s talk • Centering, alignment, beam size measurement • Test of synchronized (automated) setting-up with the beam cleaning collimators • Verify fill-to-fill reproducibility, orbit feedback • Verify aperture for second beam • Verify protection against MKI failure (3 x 1010): • Trim the MKI angle (beware of BETS limits and critical settings) • Maximum escaping amplitudes must be < 7.5 s and primary loss should only occur at the TDI • TCLIs → Stage B • Unless phase advance between TDI and MKI compromised

  21. Setting-up of Transferline Collimators (TCDI)Phase A.5, 3 x 1010, BT/collimation team/OP • Requirement: • Transferline optics measured • Setting-up: each TCDI individually (the others need to be out) • Inject & dump • Centering, alignment, beam size cross-check, set to 4.5 s • Use BLMs (local, non-local), BCTs TL/point 4/point 6 • Calibrate BLMs on TCDIs and masks parasitically • Thresholds set to: maximum allowed loss: 1 x 1011 • Verify response on nearby superconducting magnets • Check phase space coverage: maximum amplitudes escaping system: < 6 s • Inject & dump, move out TDI • Use aperture scan knobs from transfer lines • Oscillations down the line, generated by combinations of corrector magnets 4.5 s setting with maximum tolerance *target parameters needs to be properly defined

  22. Setting-up transverse damperPhase A.5, 3 x 1010 – 4 x 3 x 1010, RF/OP • Details in Wolfgang’s talk • Commission transverse damper to damp injection oscillations: • Inject & circulate • Could be done in phase A.4: single bunch: mis-steer injection • Measure emittance in line and in ring after injection (with and without damping) • Multi-bunch: injection kicker waveform effect • Verify with emittance measurement • Commission transverse damper to clean MKI rise time gap → stage B / depending on re-population mechanism and aperture in D2 • Might need to clean abort gap at the same time

  23. Injection protection needs to be revisited for… • New LHC optics version • Emittance changes • Injection re-steering • Aperture verifications in the injection region • Transfer line collimator centering needs to be verified • Injection protection needs to be set up again • Poor reproducibility after re-cycling • Re-set up injection protection system • Rematching of transfer lines • Transfer line collimators need to be set up again • Crossing-, separation angle changes, polarity changes of experimental magnets • Injection re-steering

  24. Conclusions • A commissioning plan has been developed to prepare the LHC injections for up to 156 x 156 with 9 x 1010 particles per bunch • Injection quality and injection protection has been taken into consideration • Details of target parameters still need definition • A “procedure/formalism/check list…” must be put in place to guarantee that the systems are not operated outside the parameters they have been commissioned for.

More Related