410 likes | 635 Views
Cryogenic Current Comparator – Status at GSI/FAIR -. Outline. Overview and timeline of the FAIR project at GSI Cryogenic Current Comparators as German In-Kind to FAIR CCCs in HEBT section of FAIR CCC inside Collector Ring CR Testbed for CCC inside CRYRING@ESR
E N D
Outline Overviewandtimelineofthe FAIR project at GSI CryogenicCurrentComparatorsasGerman In-Kind to FAIR CCCs in HEBT sectionof FAIR CCC insideCollector Ring CR Testbedfor CCC inside CRYRING@ESR ResultsoftherecentCCC beam tests seeFebin‘spresentation
SIS100and SIS300 UNILAC: Length: 120 m Energy: 11 MeV/u HESR S-FRS CR SIS18:Circumference: 216 m Energyupto 2 GeV/u accelerationof all ionspecies(protonstouranium) HEBT RESR NESR 100 m GSI andthe FAIR Modularized Start Version Existing GSI facility:UNILAC & SIS18asinjectors p-LINAC: high current 70 mA, 70 MeV SIS100:Superconducting, 100 Tm, 1-29 GeV/u, high currentoperationp to Up: 2.51013, U28+: 51011 /pulse HEBT: fast & slowextraction, low& high currents S-FRS:productionof rare-isotope beams (RIB) CR:stochasticcoolingof RIB andpbar HESR: storageandaccelerationofpbarto 15 GeV/u Not included in Modularized Start Version: SIS300: 300 Tm, accelerationupto 30 GeV/u RESR: accumulationofpbar, decelerationof RIB NESR: versatile experimental ring forstableions, RIB, pbarcooling, gas-target, e-A collider
Facility for Antiproton & Ion Research Nuclear Structure & Astrophysics (Rare-isotope beams) Hadron Physics (Stored andcooled 14 GeV/c anti-protons) SIS18 p-Linac SIS100/300 UNILAC QCD-Phase Diagram (HI beams 2 to 45 GeV/u) HESR Rare-Isotope Production Target Fundamental Symmetries & Ultra-High EM Fields (Antiprotons & highly stripped ions) Anti-Proton Production Target Dense Bulk Plasmas (Ion-beam bunchcompression & petawatt-laser) CR &RESR Cryring NESR Materials Science & Radiation Biology (Ion & antiproton beams) 100 m Accelerator Physics
FAIR Experiments CBM APPA Super-FRS PANDA NuSTAR
Satellite’s View 2.5 km Google Earth for FAIR 7.12.2013
MSV Civil Construction Synchrotrons: 1.1 km HESR: 0.6 km With beamlines: 3.2 km Existing SIS 18 Total area > 200 000 m2 Area buildings ~ 98 000 m2 Usable area ~ 135 000 m2 Volume of buildings ~ 1 049 000 m3 Substructure:~ 1500 pillars, up to 65 m deep
...with complex interior Central Switchyard Building down to 18 m below ground
Timeline MSV 2011 2012 2013 2014 2015 2016 2017 2018 2019 12 9 11 6 7 8 10 Submission of construction application Start Site preparation First civil construction contracts Building of accelerator & detector components Civil construction partly finished Start installing & commissioning accelerator and detector components Start commissioning with beam 10 6 7 12 8 9 11
Project planning work package structure 6 Machine projects GSI & FZJ (HESR) 102 Work packages 262 MSP project plans 5 MSP plans for buildings 4 Experiments 51 Work packages 30 MSP experiment plans In addition: 72 MSP department plans (general dep. tasks without PSP Code)
German Inkinds CCC as German Inkindassignedto GSI as German shareholder ofthe FAIR project.
IKRB-Decision, 20 Feb 2013 On GSI contributionsto HEBT beam diagnostics:The IKRB recommends to the Council to assign the HEBT beam diagnostics components with the specified PSP codes (all from CB version 6.12) to the German Shareholder GSI as in-kind contribution:2.3.6.1.1.6, 2.3.6.2.1.1, 2.3.6.2.1.2, 2.3.6.2.1.3, 2.3.6.2.1.4, 2.3.6.2.1.5, 2.3.6.2.1.6, 2.3.6.3.1.1, 2.3.6.3.1.3.2, 2.3.6.3.1.4, 2.3.6.3.1.5.1, 2.3.6.3.1.5.3, 2.3.6.3.1.6, 2.3.6.5.2.6, 2.3.6.5.3.1, 2.3.6.5.3.3.0, 2.3.6.5.3.4, 2.3.6.5.3.5.0, 2.3.6.5.3.5.1, 2.3.6.5.3.5.4, 2.3.6.5.3.6, 2.3.6.5.4.6. For information: The corresponding in-kind contract is planned to be ready for signing during the 2nd quarter of 2015.
IKRB-Decision, 20 Feb 2013 On GSI contributionsto S-FRS and CR beam diagnostics:The IKRB recommends to the Council to assign the S-FRS and CRbeam diagnostics components with the specified PSP codes (all from CB version 6.13) to the German Shareholder GSI as in-kind contribution:2.4.6.3.1, 2.5.6.1.3.1, 2.5.6.1.3.2, 2.5.6.1.3.3, 2.5.6.1.3.4, 2.5.6.1.3.5, 2.5.6.1.3.6, 2.5.6.3.1.6, 2.5.6.4.1.1, 2.5.6.4.1.2, 2.5.6.4.1.3, 2.5.6.4.1.4, 2.5.6.4.1.5.0, 2.5.6.4.1.5.1, 2.5.6.6.1.6, 2.5.6.6.3.6, 2.5.6.7.1.6, 2.5.6.7.2.6.For information: The corresponding in-kind contract is planned to be ready for signing during the 4th quarter of 2015.
German In-Kind: CCC for HEBT, CR HEBT:4 CCC installationsforeseenformeasurementofslowlyextractedbeams CR:1 CCC for online intensitymeasurementofcirculating beam
Technical System Design – Tunnels and Buildings 06C G0 T112 T110 G017.1 G018 G004 T104 G004A T113 G050 T108N T101 T103 T106 G0 07 T108S with HEBT Beamline with HEBT Supply Courtesy: F. Hagenbuck
Overview - HEBT beamlines- CCC SIS 100 SIS 18 HEBT A HEBT B CBM HEBT C CCC SFRSTarg PP APPA HESR PbarTarg CR Courtesy: F. Hagenbuck
HEBT System Design SFRS SIS100/300 DUMP Transfergebäude SIS18 Courtesy: F. Hagenbuck
Technical System Design SIS18 SIS18 SIS100 SFRS SFRS SIS18 DUMP DUMP CBM CBM CBM SFRSTarg HESR PP/AP PbarTarg SIS100/300 SIS100/300 SIS100/300 SIS100/300 CR Courtesy: F. Hagenbuck
Technical System Design SIS18 CBM SIS100/300 SIS100/300 Courtesy: F. Hagenbuck
CCC CCC CCC CCC CCC CCC CCC Installations in HEBT For all 6 beam linesabove: minimal Intensity: 104pps maximal intensity: 1012pps
Example: Slow Extractionto CBM Experiment The Au beam is produced in the following steps: UNILAC • Au4+ is produced in the MEVVA source, • Au25+ is produced in the UNILAC gas stripper at 1.4 MeV/u, • Accelerated in UNILAC to 11.4 MeV/u , • Stripping of Au25+ ions to Au65+ ions in the TK Stripper, • 4 pulses are produced in ~1 s (2.7 Hz) . SIS18 • Accelerates each pulse to 1 GeV/u, • Needs ~1.6 s for 4 batches (including pre- and post- processing) as limited by ion source. HEBT • transfer and stripping of Au65+ ions to Au79+ ions. SIS100 • Injection of 4 batches from SIS18 needs ~1.1 s • Acceleration to 11 GeV/u • KO-Extraction, spill length 1 - 10 s • Repetition Time ~3 - 13 s
Progress on the Collector Ring • The Technical Design Report of the CR has been updated and approved in February 2014. • In-kind Review Board (IKRB) meeting (01.04.20014) assigns a major part of the CR components (63 %) to Budker Institute of Nuclear Physics (BINP) • Contract on transfer of the CR system responsibility to BINP is prepared. After Council decision it can be signed. • BINP and GSI make good progress in designand procurement of CR components
CR and beam parameters Courtesy: O. Chorniy
BD components in CR and electronic room Distribution ofthe DAQ fordifferent componentsamongavailableracks Location of beam diagnosticdevices in tunnel Courtesy: O. Chorniy
Official CR layoutsfrom TDR CR and RESR rings in common building with stochastic cooling lines of the CR Courtesy: O. Chorniy Schematic layout of the CR with major installations and its nomenclature.
CollectorRing (CR) RF – cavities Stochasticcooling Pick-Up Injection Kicker magnets Stochasticcooling Kickers Courtesy: A. Dolinskii
CCC in CR CR scheme and present location of CCC Particlesdistribution at thepresent locationof CCC. Pbaroptic 71. 150 mm diameter Courtesy: O. Chorniy
CRYRING @ ESR GSI SIS 400 MeV/u FRS 11 MeV/u ESR UNILAC 4 MeV/u Courtesy: F. Herfurth F. Herfurth "HITRAP and CRYRING - deceleration of HCI and p-bar"
Experiment section Timeline CRYRING @ ESR Start ofinstallations: Now Operation ofionsourceandinjector: End 2014 Complete ring installed: Mid 2015 First testrunswithpreliminaryvacuumconditions: Fall 2015 Machinecommissioning + vacuumimprovementuntil spring 2016 firstphysicsexperiments GSI SIS 400 MeV/u FRS 11 MeV/u ESR UNILAC 4 MeV/u Courtesy: F. Herfurth CRYRING @ ESR
~3,3m Schottky/diag Experiment CRYRING Characteristics Reconfiguredfrom MSL setup Increasedcircumference ESR/2 = 54 m New injectionandextractionschemes Magneticrigidity: 0.052 – 1.44 Tm Proton energyrange: 0.14 – 96 MeV Intensityrange (frominjector): <50 mA A/q max (from RFQ): 4 Vacuum: 10-9 (start) – 10-12 mbar (final) Beam pipediameters: 100 – 150 mm Injection Extraction HF gap ECOOL Courtesy: F. Herfurth 35
Summary & Outlook • FAIR projectprogressingwell (accinstallation >= 2017) • CCCs arepartof German in-kind deliveredby GSI • 4 CCCs inside HEBT, 1 CCC inside CR • CRYRING astestbedfor CCC development • Outlook: • CERN-GSI collaborationagreementtobesignedsoon • New partnersinsidefuture CCC collaboration (HIJ, IPHT, Supraconandothers, mainly in/near Jena) • Definition ofresponsibilies, workpackages etc. required • Proposalfor BMBF-Project (Meeting on „Verbundforschung“ on 8./9. September