FL4 Remodel Project. NETS Network Upgrade!. Engineers at Work. Installation Factoids:. 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. 255,000 Feet of CAT6A copper cable were installed, over 48 miles.

zeheb
Download Presentation

FL4 Remodel Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FL4 Remodel Project NETS Network Upgrade!

  2. Engineers at Work

  3. Installation Factoids: • 304 Telecommunication Outlets (TO's) each with 4-copper and 4-fiber connections were installed. • 255,000 Feet of CAT6A copper cable were installed, over 48 miles. • 60,000 Feet of Multi Mode OM4 fiber were installed, more than 11 miles • 2432 station fiber terminations + 336 trunk fiber terminations were completed.

  4. Project Goal: Install new, ground up, network in 3300 Mitchell Lane capable of supporting current and foreseeable networking needs in accordance with NETS, NCAB, UCAR/NCAR, BICSI, and federal, state, and local jurisdictions building codes.

  5. Design Build Theory • A method to deliver a project in which the design and construction services are contracted by a single entity. It relies on a single point of responsibility and is used to minimize risks for the project owner and reduce the delivery schedule.

  6. Design Build in FL4 • The design build can take the owner out of the loop by the contractor/designer making decisions that the owner should be involved in. In the more traditional Design-Bid-Build, Change Controls are more prevalent and keep the Owner more informed and there more involved in the project.

  7. Personnel: • Ed Snyder (Primary) • Fabian Guerrero (Second) • Mike Martinez (On Site Supervisor)

  8. Safety Equipment?

  9. NI Team • Bryan Anderson • Rick Mumford • Jerome Martinez • Carlos Rojas-Torres • Wes Wildcat • Armando Cisneros • Teresa Shibao • NETS Admin Team

  10. FIRST PULL!

  11. NETS FL4 Budget   • 3-year Bond (Equipment) $0 • 15-year Bond (Permanent Infrastructure) $300,000 • Conduit Installation $150,000

  12. FL4 Budget Summary:   • 3-year Bond -$0 - Existing equipment used. • 15-year Bond $298,188.2 • Conduit Installation $150,000

  13. NETS start-of-work preceded contractor work • Marking of facilities not to be demoed • Temp (construction) network installation • Relocation of Multi-use fiber to FLA • Relocation of FLR(B) to FLA • Preparing drawings for installation crew • Order all parts for installation

  14. Broken Conduit

  15. Construction (contractor) • NETS work during contractor work • Monitoring contractor progress to ensure that network specifications were being adhered to • Attending OAC Meeting to ensure that changes were not made that affected the NETS installation • Scheduling NETS installation with other trades

  16. Conduit Runs

  17. Construction (NETS) • Project installation followed construction progress • installation of distributor [room] infrastructure (tray, racks, and cable managers) • cable installation and termination • Testing and documentation • Coordination of people move information

  18. Comm Room Cable Routing

  19. 5 Gang Box

  20. Need for Another Core

  21. Post-Construction (NETS) • Equipment installation followed construction progress • installation of network equipment: • Switches, VG242’s (analog), UPS’s, AP’s, Monitoring (Geese), Patch Cables • Activation of network ports: Network, Analog, Special • Verification of networks

  22. Schedule Summary • The project schedule changed due to • HVAC Design and Installation problems • Installation of additional Ducting all floors • Room remodel required on all floors • Replace undersized fan on roof • NETS Schedule • Personnel then reassigned to other projects • NWSC • Marshall • Ongoing normal WR’s

  23. Budgetary Advantages • Previous occupants returning, few new phones needed • AP’s already in update schedule • Reusing the NETS Switches and UPS’s • Not due for regular replacement • Still under maintenance

  24. Budgetary Challenges • Keeping the installation up to UCAR/NETS Standards when the scope of work changed • Full remodel instead of partial • Addition of Comm Outlets after budget set • Multi-use fiber removal and replacement • All new comm conduits throughout the building

  25. What Went Right • Strong technical installation team • UCAR/NETS Specifications • All Product arrived on time • Same electrical contractor as FLA

  26. What Could Have Gone Better? • Construction timeline • Comm Rooms and Chases built first • Always Promised • Never Delivered • Move Template Information • The sooner the better • From NETS sooner • To NETS sooner

  27. Lessons Learned • Comm Room size, minimum of 130 sq ft, prefer 150 sq ft • Only straight sleeves in cores between floors • Increase the number of cores between floors • Increased size of cable • Daily morning meetings kept the whole team informed to the ever changing Design build Project. This is critical for keeping ahead of a project of this size.

  28. Other Cahllenges • BAS on NETS cabling • Building Automation Systems • Becoming Industry Standard to use IP • Space in our cores • Space in our Comm Rooms • This project was a design build • Design and Construction done together • Changes come fast and often • Harder for NETS to remain within budget

  29. Thanks! • Thanks to the NI Crew for all of the hard work and long hours that went into this project.