1 / 9

Center for Creativity & Innovation Progress Update

Center for Creativity & Innovation Progress Update. Construction Progress Update. Elevator installed Main entry stairway installed Moving in progress On target for final inspections early next week for Albemarle Tech

zeki
Download Presentation

Center for Creativity & Innovation Progress Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Center for Creativity & Innovation Progress Update

  2. Construction Progress Update • Elevator installed • Main entry stairway installed • Moving in progress • On target for final inspections early next week for Albemarle Tech • LEAD office side will be construction focus from late August through September

  3. Program Update • Open House: August 20th from 5:30 - 7:00 pm • 19 scheduled students • Student interests include robotics, architecture, environmental issues/policy, digital media, entrepreneurship, film making and art therapy • 8 students will be receiving credit to use for graduation requirements • Focus on arranging internships to match student interests

  4. Operations Update • Child Nutrition: Pilot for vending machine with school meal options connected to student ID number • Transportation: Working on details for students needing transportation to Albemarle Tech • Custodial: Procurement completed for a custodial contractor - on budget with current level of occupancy

  5. MAIN ENTRY - STAIRS AND ELEVATOR INSTALLATION ALMOST COMPLETE

  6. COMMONS AREA & ADDITIONAL SKYLIGHTS

  7. KITCHENETTE

  8. INDIVIDUAL RESTROOMS

  9. STUDIOS - REMAINING FLOORING COMPLETED TOMORROW

More Related