Chisinau-Gurgiulesti Motorway, Construction of Comrat Bypass

Chisinau-Gurgiulesti Motorway, Construction of Comrat Bypass. Chisinau-Gurgiulesti Motorway, Comrat Bypass MLD3. Brussels, 12th October 2010. First TRACECA Investment Forum. 2. GEOGRAPHICAL DESCRIPTION.

zohar
Download Presentation

Chisinau-Gurgiulesti Motorway, Construction of Comrat Bypass

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chisinau-Gurgiulesti Motorway, Construction of Comrat Bypass

  2. Chisinau-Gurgiulesti Motorway, Comrat Bypass MLD3 Brussels, 12th October 2010 First TRACECA Investment Forum 2

  3. GEOGRAPHICAL DESCRIPTION South of Republic of Moldova, connecting the Capital city, Romanian and Ukrainian borders, and the Giurgiulesti International Free Port (GIFP). GIFP - the only country access to the fluvial and maritime navigable ways. Chisinau-Giurgiulesti Motorway Brussels, 12th October 2010 3 First TRACECA Investment Forum

  4. TECHNICAL DESCRIPTION Type of ImprovementNew alignmentLength of new road17.9 kmEstimated travel speed90 km/hTravel time in minutes18 minTraffic in 2011 in (000)3,400Improving AccessAccess provided to Comrat townCongestion2 lanes on 4 Lane Right-of WayLand ownershipland need to be acquired Brussels, 12th October 2010 4 First TRACECA Investment Forum

  5. SOCIO-ECONOMIC DESCRIPTION Construction of the road will facilitate: trade transport industry and tourism development and strengthen access to agricultural markets securing transportation connections between the country's centre and its southern regions; will also provide for the employment of significant number of population and stimulate the local economies. Brussels, 12th October 2010 First TRACECA Investment Forum 5

  6. INVESTMENT AMOUNT AND REPAYMENT Investment Amount Euro 16 million Repayment Period 7 years Source of Repayment State Budget Brussels, 12th October 2010 6

  7. OTHER SOCIO-ECONOMIC DESCRIPTIONS The Feasibility Study completed in June, 2009 Economic internal rate of return (30 years): 12.2% The benefits of the project implementation: Cost savings to transport operators 0.28 eur/vehicle Cost savings to passengers 0.22 eur/passenger Time savings 20% less Enhance environmental sustainability Reduce air pollution, noise, accident rates. The discount rate applied in the project is 12%. Final goal of the Project. To ensure regional economic development trough agricultural markets extension, enhancing access to social services, reducing transportation costs and travel time for international and national operators, and passengers; employment of a considerable number of population. Brussels, 12th October 2010 First TRACECA Investment Forum 7

  8. SUMMARY • The Comrat bypass alignment: • is shorter than the existing • will allow long-distance trips to bypass the urban section of Comrat. • residents of Comrat relieved off the traffic. Since the bypass alignment is partially build and • limited negative social and environmental effects of the construction (bypass alignment is partially build) • new opportunities for transport operators from the perspectives of Port development. Investment Amount million Euro 16 Brussels, 12th October 2010 First TRACECA Investment Forum