Discussion on TE/CRG equipment at H4IRRAD Marco Pezzetti

Discussion on TE/CRG equipment at H4IRRAD Marco Pezzetti (A. Tovar – B. Ivens / Support CE for cryo LHC ) & TE-CRG-OA – TE-CRG-CI. Discussion on TE/CRG equipment at H4IRRAD: - SEU Summary 2011/2012 - AMB introduction - SEU signature protocol on AMB

zoltin
Download Presentation

Discussion on TE/CRG equipment at H4IRRAD Marco Pezzetti

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Discussion on TE/CRG equipment at H4IRRAD Marco Pezzetti (A. Tovar – B. Ivens / Support CE for cryo LHC) & TE-CRG-OA – TE-CRG-CI TECRGCE M.PEZZETTI

  2. Discussion on TE/CRG equipment at H4IRRAD: - SEU Summary2011/2012 - AMB introduction - SEU signature protocol on AMB - Discussion on possible November 2012 test at H4IRRAD TECRGCE M.PEZZETTI

  3. TECRGCE M.PEZZETTI

  4. SEU: summary 2011-2012 Actions @ Xmas, not bad! QURCB_P8: 3x QURA_P4: 1x QUI_P4 : 1x QURCB_P6: 1x Courtesy A. Suraci TE-CRG-OA

  5. Actions @ Xmas, not bad! • Relocation during Xmas 2011 • P8: QURCB electrical cabinets & CPU of QURA • P6: CPU’s of: QUI, QURA, QURCA & QURCB • P4: CPU’s of: QUI, QURA, QURCA, QURCB, QURCACC & QURCBCC

  6. TE/CRG equipment - AMB introduction TECRGCE M.PEZZETTI

  7. TE/CRG equipment - AMB introduction TECRGCE M.PEZZETTI

  8. LINDE IHI QURC Layout TECRGCE M.PEZZETTI

  9. (13/08/2011) P8 stop SEU signature..

  10. (27/08/2012) P4 SEU signature… Rebooting (20s)…

  11. SEU signature protocol… TE/CRG technicalprocedure for SEU signature identification: 1) Trend analyzing(20 s reboot) 2) AMB Test on TECRGCE test bench 3) Manufacture electronicstressingtest In accord with TE/MPE (F. Formenti). TECRGCE M.PEZZETTI

  12. QURCs- AMB UX45 localisation PLC Siemens & Profibus network TECRGCE M.PEZZETTI

  13. QURCs- AMB UX45 localisation PLC Siemens & Schneider TECRGCE M.PEZZETTI

  14. QURCs- AMB UX45 localisation AMB & VFD TECRGCE M.PEZZETTI

  15. Discussion on possible November 2012 test at H4IRRAD. No radiation for CCS cartouche. H4IRRADarea test TECRGCE M.PEZZETTI

  16. R2E strategy for P4? -Blindage -Delocalisation <20m -Delocalisation >20m

  17. SEU: Balance 2011-2012 END

  18. SEU: Balance 2011-2012 • Number of weekswith Stable Beam > 640 bunches: • 20112012 • ~23 weeks ~15 weeks 640 bunches TS TS TS TS TS TS TS Courtesy A. Suraci TE-CRG-OA

  19. SEU: Balance 2011-2012 • Actions taken to improverobustness: • CV891: automatic reset implemented into PLC (action: cut off 24 Vdc). • TT89x: modification of electronics card (capacitor removed), timer • PLC: moved into better protected zone (P4-P6-P8 caverns) • 24 Vdc: longer term, to be moved into a safer protected zone and better distribution of power consumption to be done. • AMB (Magnetic bearing controlers): relocation 2nd unit of P8 (Phase III), additional shielding required? Courtesy A. Suraci TE-CRG-OA

  20. R2E P8 Ph 3 Relocation, long and complex project well prepared a success!!

  21. QURCs- AMB UX45 localisation 20 m maximum… TECRGCE M.PEZZETTI

  22. R2E- P8 Ph3 P8 QURCB Transfert US85 to UL84 QURCB-EMC4 QURCB-EMC3 QURCB-EMC2 QURCB-EMC1 QURA-Existing Schneider Cab. +Turbines cab.-NewLocation Caverne UX85 1 Cables 24VDC I/O depuis rack 24VDC US851 22 specific Cables controle depuis Blocs Phoenix QURCB-EM01=US85 2 Cables NE48 vers PLCSiemens + 1 cable NE18 QURCB-EM02=UL84 QURCB-Schneider New Cabinet QURCA-EM02=UL84 3 Cables Profibus PA QURC_QUI-EM03=UL84 24 Cables NE8 2 Cables Ethernet depuis Start Point US851 UJ84 QUICC-EM02=UL84 8 NE48 Cables controle from QURC-EMC1 to EMC4 QURCA/B&QUICC Valves Positionners Racks CCS Cabinet QURCA QURCA-EMC4 QURCA-EMC3 QURCA-EMC2 QURCA-EMC1 Realisation new chassis Blocs Phoenix UL84 US851 QURCB-EM01=US85 12 Cables CCS 24VDC/230VAC UPS /400VAC Longueur cables US852 a US85 CCS: 20m Longueur cables de US852 vers UJ84: 70 a 75m Longueur cables Armoires CCS US85 vers UJ84: 40 a 45m US852 Cold Compressors 12 specific Cables Compr. Froids Partie elec Vannes CV + 8 EV CCS Cabinet QURCB US85 Existing cabinets from US852 new location 22

  23. P4/P6 PLC CPU relocation