An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Phase II-2 Capital Project Phasing Plan

  2. Phase II-2 Capital ProjectPhasing Schedule • Phase 1 – December 2010 to August 2011 • Phase 2 – September 2011 to August 2012 • Phase 3 – September 2012 to August 2013

  3. Phase II-2 Capital Project • Phase 1 • December 2010 to August 2011

  4. Middle School Phase I Middle School Auditorium Renovations Begin February 2011 Complete August 2011 Middle School Office Upgrades Begin July 2011 Complete August 2011 Central Office Renovations Begin July 2011 Complete August 2011 New Middle School Gym / Locker Room Renovations to begin December 2010 New 2-Classroom / Link Addition Begin December 2010 Complete August 2011

  5. High School Phase I New 2-Classrom/ Corridor Addition Begin December 2010 Complete August 2011 300 Wing Bathroom Renovations Begin December 2010 Complete April 2011 Auditorium / Gym B Demolition Begin July 2011 100 Wing Demolition Begin July 2011 Athletic Department Office Renovations Begin July 2011 Complete August 2011 New Science Room Renovation Begin April 2011 Complete August 2011 Classroom Renovations Begin July 2011 Complete August 2011 Science Classroom Renovations Begin July 2011 Complete August 2011 Classroom Renovations Begin July 2011 Complete August 2011 New Fitness Room Renovations Begin December 2010 Complete February 2011 Gym A Locker Room Renovations Begin April 2011 Complete August 2011 New AP Office Renovation Begin February 2011 Complete August 2011 New Bathroom Set Renovations Begin February 2011 Complete August 2011 New 2-Classroom / Team Room Renovation Begin February 2011 Complete April 2011

  6. Fairbanks Road Entrance Phase I Construct Addition Staging Areas Begin December 2010 Construct Storm Water Retention Area Begin December 2010 Construct New Central Office Parking Lot Begin March 2011 Complete August 2011 Construct Fairbanks Road Entrance Drive Begin March 2011 Complete August 2011 Re-construct Parking Lots and Bus Loop Begin July 2011 Complete August 2011

  7. Buffalo Road Entrance Phase I Re-Construct Entrance Drive and Staging Areas Begin July 2011 Complete August 2011 Construct Storm Water Retention Area Begin December 2010 Re-Construct Parking Lots and Entrance Drive Begin March 2011 Complete August 2011

  8. Phase II-2 Capital Project • Phase 2 • September 2011 to August 2012

  9. Renovate Pool Area and Pool Locker Rooms Begin April 2012 Complete August 2012 Renovate Classroom Begin July 2012 Complete August 2012 100 Wing Renovation/New Science Classrooms Complete August 2012 New Middle School Gym/Fitness Room Complete January 2012 Continue Auditorium Renovation Full Phase 2

  10. Restore Staging Area at MS Gym Complete December 2012 Continue Use for Staging Area Full Phase 2 Install Top Course of Asphalt Complete August 2012

  11. Phase II-2 Capital Project • Phase 3 • September 2012 to August 2013

  12. New Auditorium Complete August 2013

  13. New Auditorium Complete August 2013 New Auditorium Complete August 2013 Corridor Renovations Begin July 2013 Complete August 2013

  14. Reconstruct Parking Lot Complete August 2013

  15. Thank you!