1 / 11

2X660 MW MAITREE SUPER THERMAL POWER PROJECT PROGRESS REPORT FOR THE MONTH OF APRIL’ 2014

Bangladesh-India Friendship Power Company (Pvt.) Limited (A Joint Venture of NTPC Ltd and BPDB ) Registered Office : Bidyut Bhaban (14th Floor), 1 Abdul Gani Road, Dhaka-1000, Bangladesh. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT PROGRESS REPORT FOR THE MONTH OF APRIL’ 2014.

hedia
Download Presentation

2X660 MW MAITREE SUPER THERMAL POWER PROJECT PROGRESS REPORT FOR THE MONTH OF APRIL’ 2014

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bangladesh-India Friendship Power Company (Pvt.) Limited(A Joint Venture of NTPC Ltd and BPDB)Registered Office : Bidyut Bhaban (14th Floor), 1 Abdul Gani Road, Dhaka-1000, Bangladesh 2X660 MW MAITREE SUPER THERMAL POWER PROJECT PROGRESS REPORT FOR THE MONTH OF APRIL’ 2014 Pontoon under high tide condition PROGRESS REPORT-APR'2014

  2. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT INDEX PROGRESS REPORT-APR'2014

  3. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT Management Summary • Appointment of Owner’s Engineer: Appointment of M/S Fichtner GmbH as Owner’s Engineer has been approved in 8th Board Meeting. Notification of Award issued on 24th April 2014. • Appointment of Coal Consultant : Pre-proposal meeting held on 10th April ‘14. • Environment Management: 1st Quarterly monitoring of Environment parameters done by M/S CEGIS. Report expected in 2nd week of May. • Boundary wall, Slope protection & Additional area filling: Negotiation held with M/S BDPL. Contract Finalized. Notification of Award issued. • Pre-fabricated Site Office : Technical specification Finalized. • Substation Package: Bid opening on 15th May’14. • Consultancy for Gate Complex: Contract is at finalizing stage. Highlights – Progress: Corporate Activities PROGRESS REPORT-APR'2014

  4. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT Highlights - Progress : Site Activities • Pontoon Jetty foundation protection wall made. Pontoon stair erected. • 33/11 KV Line 200 KVA both the transformers erected. Cable laying completed. • Site filling work completed. Micro-leveling & compaction in progress. • Earthen dyke preparation in progress, for slope protection. 1500 m/ 5400 m completed. • Main Plant Fencing work in progress. PROGRESS REPORT-APR'2014

  5. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT Financial Progress (FY-2013-14) PROGRESS REPORT-APR'2014

  6. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT Status of Critical Inputs PROGRESS REPORT-APR'2014

  7. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT Pending Critical Approvals PROGRESS REPORT-APR'2014

  8. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT Major Initiatives taken during this month • Owner’s Engineer : Negotiation held and Notification of Award issued. • Pre-Proposal meeting held for Coal Consultancy. • Meeting held with Chairman, Mongla Port Authority regarding the scope of service & preparation of DPP for Capital Dredging. • Tax consultant engaged. • Meeting held with HSBC Bank regarding appointment of Finance Consultant cum Arranger. • Notification of Award issued to BDPL for “Boundary wall, Slope protection, preparation of Earthen Dyke & Additional Land Filling. PROGRESS REPORT-APR'2014

  9. 2X660 MW MAITREE SUPER THERMAL POWER PROJECT Schedule of activities Planned for next six months PROGRESS REPORT-APR'2014

  10. Bangladesh-India Friendship Power Company (Pvt.) Limited(A Joint Venture of NTPC Ltd and BPDB)Registered Office : Bidyut Bhaban (14th Floor), 1 Abdul Gani Road, Dhaka-1000, Bangladesh Main Plant Fencing work in Progress PROGRESS REPORT-APR'2014

  11. BANGLADESH- INDIA FRIENDSHIP POWER COMPANY (PVT.) LTD. PARTNER IN PROGRESS PARTNER IN PROGRESS PARTNER IN PROGRESS PROGRESS REPORT-APR'2014

More Related