1 / 12

Efficient Design of Vehicle Bridge over Spring Creek, PA

This project aims to replace a vehicle bridge destroyed by a 100-year flood event to restore access for regional residents and first responders. The recommended solution is a Warren Truss bridge based on structural and economic efficiency analysis. The bridge should be built as soon as possible to resume normal traffic and benefit the local community.

jblanca
Download Presentation

Efficient Design of Vehicle Bridge over Spring Creek, PA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Design Project #1 Replacement of Vechicle Bridge over Spring Creek Centre County, PA Introduction to Engneering Design EDGSN 100 Section #001 Team “Four Horsemen” Design Team 2 Jinzhen Hu Zixuan Feng Zeynep Okul Praakriti Bhatnagar Presented to: Prof. Berezniak 2017

  2. Statement of the Problem A 100 year flood event destroyed the existing Bridge. The bridge is vital for providing access to the medical center for the regional residents. Two problems: Disruption of daily usage for the regional residents & Disruption of direct access of first-responder vehicles to the residents.

  3. Project Objective PennDOT Engineering District 2-0 has implemented a fast-track project to expedite the design and building of a new vehicle bridge over Spring Creek.

  4. Required Design Criteria • The bridge will be built on standard abutments, and have no pier. • It will have the ability to take the load of two AASHTO H20 - 44 trucks, one in each lane. • It will be 20 meters above the ground, and the deck will span 40 meters across one end to the other. • The deck will be 0.223 meters thick and be made of medium strength concrete as the preferred material.

  5. The Technical Approach Phase 1: Economic Efficiency We used Engineering Encounters Bridge Design 2016 (EEBD 2016) for the estimation design. 1.The software applied a load to the bridge to determine if the design could withstand the expected load upon the bridge. 2.The software was able to display the estimated cost report, the load test results and showed bridge member details. This data was used to analyze the results and help to determine which bridge was the most structurally efficient.

  6. The Technical Approach Phase 2: Structural Efficiency Prototype Warren and Howe truss bridges were constructed by each design team using a maximum of 60 Popsicle sticks, white elmer’s glue, and hot glue for the struts and floor beams. The constructed prototypes had the following dimensions: 13.5 inches in length, 4.5 inches in width, and 4 inches in height. Each prototype bridge was load tested using a suspended mass from the center of the prototype, and more mass was added until the stress was too great and the bridge failed.

  7. The Results Phase 1: Economic Efficiency Final Cost of the Howe Truss Bridge Design : $ 234,909.66 Final Cost of the Warren Truss Bridge Design : $ 195,327.93

  8. The Results Phase 2: Structural Efficiency Final Load Test of the Howe Bridge : 51 lb Actual Weight of the Howe Bridge : 0.181 lb Final Load Test of the Warren Bridge: 71 lb Actual Wight of the Wareen Bridge: 0.196 lb 281 361

  9. The Best Solution Due to the significant differences between the structural efficiency and the economic efficiency, Warren Truss bridge should be the best solution of our design group. $ 234,909.66 $ 195,327.93 281 361

  10. Our Conclusions PennDOT Engineering District 2-0 has implemented a fast-track project to expedite the design and building of a new vehicle bridge over Spring Creek. Designing and building this new bridge over Spring Creek was important for the local residents of the area to have a direct route to Nittany Medical Center. Based on the results of structural efficiency and economic efficiency, the Warren Truss Bridge is the better option compared to a Howe Truss Bridge.

  11. Our Recommendations The next step to complete the final bridge design is to put our design to action. The bridge should be built as soon as possible in order to benefit the local residents and resume usual traffic.

  12. In Closing We would like to thank PennDOT 2-0 for sponsoring this project. Thank you for giving us this opportunity to design this bridge. Not only do bridges connect places, they connect people.

More Related