An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District July 20, 2009 EDUCATE ENGAGE EMPOWER

  2. Agenda • Completed Construction Projects • LAC P Faculty Restroom Upgrades • District Wide - Master Landscape Plan • District Wide - Energy Efficiency Project Phase 2A • Current & Upcoming Construction Projects • LAC South Quad Complex • LAC Building A, Student Services Retrofit • LAC Math Technology Building • LAC Parking Structure • LAC Building O Complex • LAC Infrastructure Improvements • LAC Q & R ADA/HVAC Upgrades • PCC Industrial Tech Phase 1 • PCC MDAB (Multi-Disciplinary Academic Building) • PCC Building CC Retrofit • District Wide – Electronic Signage Plan • District Wide - Energy Retrofits • Los Coyotes Property • Upcoming Projects • Planned Phasing of Future Projects • Q & A

  3. Current and UpcomingConstruction Projects Construction approx. 99% Complete Space includes Approx. 68,000 ASF 32 modern classrooms and labs 38 faculty offices Executive offices Multipurpose room State of the art Board Room Substantial completion anticipated Fall 2009 South Quad Complex – Measure E 2002

  4. Current and UpcomingConstruction Projects Construction Document phase in progress Adds 6,018 ASF to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. Estimated start of construction Fall 2010 LAC Building A – Student Services Retrofit Measure E 2008

  5. Current and UpcomingConstruction Projects Completed Schematic Design Will house Math and Culinary Arts instructional program as well as Reprographics Estimated start of construction Winter 2013 LAC Math Technology Building – Measure E 2008

  6. Current and UpcomingConstruction Projects LAC Parking Structure – Measure E 2008 • Spaces for 900 Vehicles • To be procured under “Design Build” method • Photovoltaic Electrical Generation Array on top level • To be located Southeast corner of Lot J adjacent to the Verizon building • Outfitted with single-axis tracking system • Minimum 450 KW+ output • Curriculum building opportunity • Exhibit classroom • Anticipated start of construction Spring 2010

  7. Current and UpcomingConstruction Projects LAC Building O Complex – Measure E 2008 • Property acquired December 2008 • Two structures totaling 87,000 square feet • Occupants shall be: IITS, BMT, Warehouse Facility (operational), ERD, and Foundation Office (Relocating July 6th) • Tenant improvements underway on: ERD offices, elevator installation for bldg. 1 • Potential rental spaces being assessed

  8. Current and UpcomingConstruction Projects LAC Infrastructure Improvement Projects Measure E 2008 • Completes 3.5 mile long chilled water line loop • Total annual estimated savings of 1.5 million Kwh • Provides system redundancy and mitigates operational impacts • Upgrades include; Reclaimed Water, Domestic Water, Data, etc. • Majority of existing building HVAC systems to be connected to new infrastructure • Landscaping upgrades to be implemented in conjunction with infrastructure project phasing

  9. Current and UpcomingConstruction Projects LAC Q & R ADA/HVAC - Measure E 2008 • Complete building ADA upgrade: includes restrooms, stair lift, etc. (Bldg. R) • All new infrastructure: new piping, fixtures, etc. (Bldg. R) • Minor renovations to offices (Bldg. R) • Total renovation of locker/training rooms (Bldg. R) • HVAC upgrade: includes new air handlers, ductwork, etc. (Bldg. Q & R) • Update fire alarm system (Bldg. Q & R) • Construction will be done in phases so as to minimize disruption of classes • Final construction documents to be submitted to DSA Fall 2009 • Estimated start of construction Summer 2010

  10. Current and UpcomingConstruction Projects PCC Industrial Technology Center Phase 1 Measure E 2002 • Modern facility houses Welding Department and other trade programs • Construction is 85% complete • Replaces existing antiquated structures • New Northern face of the campus • Completion anticipated late Fall 2009

  11. Current and UpcomingConstruction Projects PCC MDAB (Multi-Disciplinary Academic Building) - Measure E 2002 • 90% construction documents submitted for review • Install portables for swing space at PCC Fall 2009 • Anticipated start of MDAB construction December 2009 • Project to be completed in two phases

  12. Current and UpcomingConstruction Projects PCC Building CC Retrofit - Measure E 2008 • To be designed by Hill Partnership Architects • Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices • Swing space to be located on PCC Campus (Bldg. GG) • To be completed concurrently with MDAB project phase 2 • Anticipated start of construction Summer 2011

  13. Current and UpcomingConstruction Projects District Wide – Electronic Signage Plan Measure E 2008 • District Wide Signage Plan complete • Currently in City Permitting phase • Final site locations determined • Construction completion of Marquee Signs Spring 2010

  14. Current and UpcomingConstruction Projects District Wide Energy Retrofits - Measure E 2008 • Phase 1 – Construction of Central Plants • The chillers at the Central Plants were selected to achieve maximum efficiencies both at part load and full load conditions. The plant not only reduces the peak electrical demand at the campus but also offers lower emissions thus reducing the impact on the environment. Received rebates from Southern California Edison • LAC Central Plant • Designed to have (2) 600 ton centrifugal chillers and (1) 300 ton chiller with space for a future 600 ton chiller. The Central Plant is designed to serve most of the existing buildings and all the new buildings at the campus.   • PCC Central Plant • Designed to have (2) 300 ton centrifugal chillers and (1) 300 ton multi-stack chiller. The Central Plant is designed to serve most of the existing buildings and approximately three new buildings at the campus.

  15. Current and UpcomingConstruction Projects District Wide Energy Retrofits - Measure E 2008 • Phase 2A (Complete) • Lighting upgrades • HVAC upgrades • Controls upgrades • Pool upgrades • Water systems upgrades • Hot water system upgrades • Re-roofing • Phase 2B (Design Phase) • HVAC upgrades (Air Handlers, Zone upgrades, tie to Central plant, etc.) • Controls upgrades (FAC Approved temp. range 70°-75°) • Lighting upgrades (Interior/Exterior/Lighting controls) • Hot water system upgrades • Irrigation controls • Window film addition

  16. Current and UpcomingConstruction Projects Financial Benefit of Energy Retrofit Program

  17. Current and UpcomingConstruction Projects Los Coyotes Property - Measure E 2008 • Re-design current dirt lot to have 80 parking stalls with new lighting and drainage. (Awaiting City feedback) • Re-slurry and re-stripe existing asphalt parking lot. (Done) • Replace elevator controls to bring them up to new current standards. (In process) • Installation of new automated front door. (In process) • Building perimeter landscape upgrade. (In process)

  18. Current and UpcomingConstruction Projects Upcoming Projects • LAC • Carson Street Median Fence Replacement (Construction completion July 2009) • Pool boiler upgrade (In process) • Replace current antiquated heating system with energy efficient boilers. • Bldg. F - Conversions of rooms F104 and F106 to new classroom space. (Awaiting structural calculations) • Expansion of Building I (In Design Phase) • Bookstore to be relocated here • Bldg. E – Interior painting, carpet/tile replacement, and restroom upgrades • Bldg. K – Roof extension over kiln area • CDC - Roof, carpet, and playground equipment replacement • PCC • Bldg. MM (FPP) • Exterior renovation (In Process – utilizing scheduled maintenance funds) • Paint, windows, replacement of all exterior doors • Restroom ADA upgrade (In Process) • Bldg. JJ – Add new landscaping around perimeter • Add additional parking at corner of PCH and Walnut

  19. Planned Phasing of Future Projects • 2009-10 • Parking Structure – groundbreaking Spring 2010 • South Quad Complex complete - Fall 2009 • Tech 1 at PCC complete – Fall 2009 • Building O occupancy scheduled • Foundation – July 2009 • ERD, Warehouse, BMT and IITS – January 2010 • Begin infrastructure construction – Fall 2009 • Master landscaping implementation will follow this project • Submit FPP for M/N Project at LAC and MM Project at PCC and submit IPP for P Building at LAC and MM Project at PCC – July 1, 2009 • Install portables for swing space at PCC – Fall 2009

  20. Planned Phasing of Future Projects • 2009-10 (continued) • Submit plans to DSA for Building A renovation – August 2009 • Submit plans to DSA for Building I (Bookstore) renovation – September 2009 • Submit plans to DSA for Building R (Gym) renovations – Fall 2009 • Begin retrofit of Z Building – Fall 2009 • Begin construction of Buildings DD and EE at PCC • Anticipating December 2009 start • Schematic design begins for Outdoor PE Labs at LAC – Spring 2010 • Anticipating swing space move for Building A at LAC – June 2010 • Marquees complete – Spring 2010

  21. Planned Phasing of Future Projects • 2010-11 • Begin Building R (Gym) HVAC and ADA upgrades – Summer 2010 • Anticipating Spring 2011 completion • Begin construction of Building I (Bookstore) and move to portable swing space – Summer 2010 • Retrofit completion of Building Z – Summer 2010 • Submit plans to DSA for Outdoor PE Labs – Fall 2010 • Begin construction of Building A at LAC – Fall 2010 • Begin Schematic Design for Buildings C and F at LAC • Submit plans to DSA no later than Summer 2011

  22. Planned Phasing of Future Projects • 2011-12 • Infrastructure project complete at LAC – Summer 2011 • Submit plans to DSA for Math/Technology Building at LAC – Summer 2011 • Begin construction of Buildings AA, BB and CC at PCC – Summer 2011 • Construction completion of Buildings DD and EE at PCC – Summer 2011 • Begin construction of Outdoor PE Labs at LAC – Summer 2011 • Anticipating Spring 2012 completion • Anticipated construction completion of Building I (Bookstore) at LAC – Fall 2011 • Anticipated construction completion of Parking Structure at LAC – Fall 2011

  23. Planned Phasing of Future Projects • 2012-13 • Move Buildings C and F programs into Swing Space (M/N Building) and begin construction – Summer 2012 • Anticipated Construction completion of Building A at LAC – Summer 2012 • Submit plans to DSA for M/N Building at LAC and Building MM (Phase 1) at PCC – Summer 2012 • Begin Schematic Design for Building P at LAC and Building MM (Phase 2) at PCC – Summer 2012 • Submit to DSA – Spring 2013 • Begin construction of Math/Technology Building at LAC – Winter 2013

  24. Planned Phasing of Future Projects • 2012-13 (continued) • Begin Schematic Design for Building D and E renovations – Fall 2013 • Anticipated Construction completion of Buildings AA, BB and CC at PCC – Spring 2013 • Submit plans to DSA for Building GG at PCC – Summer 2012

  25. Planned Phasing of Future Projects • 2013-14 • Begin construction on Building GG at PCC – Summer 2013 • Anticipated Construction completion of Buildings C and F at LAC – Fall 2013 • Begin construction of Buildings M/N at LAC and MM (Phase 1) at PCC – Fall 2013 • Submit plans to DSA for Buildings D and E renovations at LAC – Fall 2013 • Schematic design for Performing Arts Building (G&H) and Building R at LAC – Spring 2014

  26. Planned Phasing of Future Projects • 2014-15 • Anticipated Construction completion of Math/Technology Building at LAC – Summer 2014 • Begin construction on Buildings D and E at LAC – Fall 2014 • Submit plans to DSA for Performing Arts Building and Building R (Gym) at LAC – Spring 2015 • Anticipate construction start – Spring 2016 • Anticipated construction completion of Buildings M/N at LAC and MM at PCC – late Spring 2015 • Begin construction on Buildings P at LAC and MM (Phase 2) at PCC – Spring 2015

  27. QUESTIONS& ANSWERS EDUCATE ENGAGE EMPOWER