An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Michelle Swisher • 11 years of service to the Borough of Mantoloking • Job titles included: • Chief financial Officer • Tax collector • Tax Search Officer • Michelle thank you for your service, you will be missed!

  2. MANTOLOKING UPDATE

  3. Michelle Saying “goodbye” to old Borough Hall!

  4. Sheet Pile • Progress • OEM continues to have weekly meetings • Estimates to have rock delivery at Lyman on or about week of Sept. 22nd

  5. Sheet Pile Caps are currently being installed

  6. Route 35 C2 – Lyman south 2000’: alternating traffic pattern A1, A2, & A3 – Downer south to Curtis Point: two lanes pushed to the west. Water company started to install new water main from Princeton to Albertson Monday. Downer Pump Station – work will focus on building the gazebo. Lyman Pump Station – work continues on stabilizing the ground and building of the underground portion of the pump station.

  7. Rt. 35 Those residents who have trees planted by the NJ DOT that have died are asked to leave them in place. The trees are insured and will need to be inspected in March. Once they are inspected the dead trees will be replaced with new ones. Please continue to call 732-230-7356 or email restore.nj35@dot.state.nj

  8. Mantoloking Bridge Construction Construction to start 2nd or 3rd week in October Estimated to be a 60 day work time Construction will go 200’ up the bridge This is a Federal funded project

  9. Garbage Pick Up Due to Rt.35 re-construction, Marpal has elected and the Borough has approved a 4:30 AM start time. This was done so that there not be an interruption in service. As the traffic pattern changes we may need to adjust times and days, and changes will be communicated to the public through the Borough web site and OEM Facebook page.