Integrated Systems Market Trials

Integrated Systems Market Trials. June 26, 2015. Call Etiquette. Mute your phones Do not put the call on hold (even if you are on mute) No roll will be taken – please include company name when signing into Web-Ex so that your attendance will be noted Please be courteous of everyone’s time

yolandai
Download Presentation

Integrated Systems Market Trials

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Integrated Systems Market Trials June 26, 2015

  2. Call Etiquette • Muteyour phones • Do not put the call on hold (even if you are on mute) • No roll will be taken – please include company name when signing into Web-Ex so that your attendance will be noted • Please be courteous of everyone’s time • Identify yourself and company when speaking

  3. Agenda • Weekly Activity Review • Deployment Testing Update • Training Opportunities • Reminders • Look Ahead at Next Week’s Schedule • Questions

  4. Weekly Activity Review

  5. Day-Ahead Market Update • Results Posted by 4:00 pm CST • IS Commitments Out of DAMKT • General Questions About Results Bryan Clark

  6. IS DAMKT Total Gen MW (6/19) Bryan Clark

  7. Day-Ahead RUC Update • DA RUC cases completed by 20:00 OD -1 for each Operating Day • No Emergency Conditions • No Breached Constraints • DA RUC Market Commitments for IS occurred on all days Raleigh Mohr

  8. Day-Ahead RUC vs DAMKT (6/15) Raleigh Mohr

  9. Day-Ahead RUC Commitments (6/15) Raleigh Mohr

  10. Day-Ahead RUC vs DAMKT (6/16) Raleigh Mohr

  11. Day-Ahead RUC Commitments (6/16) Raleigh Mohr

  12. Day-Ahead RUC vs DAMKT (6/17) Raleigh Mohr

  13. Day-Ahead RUC Commitments (6/17) Raleigh Mohr

  14. Day-Ahead RUC vs DAMKT (6/18) Raleigh Mohr

  15. Day-Ahead RUC Commitments (6/18) Raleigh Mohr

  16. Day-Ahead RUC vs DAMKT (6/19) Raleigh Mohr

  17. Day-Ahead RUC Commitments (6/19) Raleigh Mohr

  18. RTBM Analysis (6/15 – 6/19) • Good RTBM participation • LMPs and MCPs continue to be high. • Cause: Discrepancy in CMODES on resources selected for Regulation due to the test environment • LMPs and MCPs for the current week have significantly improved and closer reflect production prices Gentry Crowson

  19. Gentry Crowson

  20. Settlements (6/14 – 6/21) • Meter Submittals – Reviewed OD 6/14 and 6/19 meter submittal and overall looked pretty good. Had one big issue on 6/14 and some sign issues on 6/19. • BSS Submittals – Continue to look great! • Everything is up-to-date and posted on schedule • Posted Invoice 6/25 – Had 19 Operating Days – 7 Initials, 7 Finals, and 5 Resettlements. Please review! David Daniels

  21. Settlements – Daily Calibration • Calibration is DAILY calibration and represents the whole Operating Day. • 6/11 – 6/13: Calibration was very good! • 6/14 : One bad submittal for one interval. • 6/17 – 6/21: Have some generators submitting as load. Injection: Import/Generation (-) or Withdrawal: Export/Load (+) David Daniels

  22. Settlements – Meter Submittal • Down to about eight meter locations not submitting • Approximately 130 MDSL’s. This varies as new commercial models are implemented (MDSL’s added/terminated) • Please continue to verify all meters ready to be submitted and data is accurate. Please verify reports and access to reports. David Daniels

  23. Deployment Test UpdateChris Baldwin

  24. Deployment Test Results (6/1 – 6/26) • Time frame 6/1/2015 – 6/26/2015 Is being extended • Duration:  There will be two deployment tests a day Monday through Thursday. • Due to resource constraints we were not able to test as many resources as we had hoped • We have been able to successfully complete 2 deployment tests for 19 resources • We have been able to successfully complete 3 deployment test for 12 resources working towards meeting those resources Regulation Qualification Requirements

  25. Deployment Test Schedule (6/29 – 7/2)

  26. Training Opportunities

  27. Reliability Unit Commitment (RUC) Training Computer-Based Training • Reliability Unit Commitment Process • Self-paced (21 Minutes) Training Materials • RUC Education Session Presentation • RUC Education Session FAQ Request in LMS

  28. Reliability Unit Commitment (RUC) Training Virtual Instructor-Led Course Commitment Decisions: How Reliability Unit Commitment Works • Scenarios to understand RUC processes and commitment decisions • 2 VILT sessions offered • September 22 (2-4 pm) • November 4 (2-4 pm) Register in LMS

  29. Market Monitoring Data Depository Overview Registration Now Open! July 8: 10:00 a.m. – 11:30 a.m. Central Time • Identify purpose of Market Monitoring Data Depository (MMDD) • Identify MMDD data modules • List key data components of five data modules • Identify frequency of data submittal • Navigate in MMDD to complete data submittal

  30. Marketplace SymposiumOpportunity, Relationships, Value October 7 - 8 at SPP Corporate Campus in Little Rock • Offer 8-10 sessions per day on current and relevant Integrated Marketplace topics • Include combination of Customer Trainers and Subject Matter Experts delivering sessions • Host an on-site, after-hours event Day One • Registration now open! • $100 fee for non-members

  31. RemindersMichael Hodges

  32. CROW – Outage Scheduler • CROW is the system used for outage coordination • Submit known outages for both generator and transmission outages in CROW • All resources should now be setup in CROW (if a unit is not listed please let SPP know via RMS) • The link to CROW is: https://crow.itespp.org/crow/Outages/outage_req_index.aspx

  33. Scheduling: Submitting Tags • IS MPs will need to submit tags in MTE for the entire IS Integrated Market Trials Testing period • MPs will submit tags each week starting the week of May 11 through the week of July 17 • IS MPs will need to submit their tags each week on Tuesday and Wednesday between 1:00 – 3:00 CPT for the next day’s DA Process • IS MPs can submit tags for up to 7 days in the future • Submit tags with source/sinks that have been registered • The link to the ITE e-Tag is https://demo.spp.oati.com/

  34. Scheduling: TSR Approvals Transmission Service Requests (TSR) are submitted through the SPP OASIS (Open Access Same-Time Information System) so eligible transmission customers can request transmission service. • Long Term TSRs will need to be entered into SPP’s MTE environment prior to submitting tags. • If the customer chooses to test short term point-to-point TSR or Market Import Service (MIS); • They can enter those TSRs between 8:00 and 10:00 (CST) on Tuesdays and Wednesdays to be approved and ready for test tagging in the afternoon on those days. • The URL to submit your TSRs is https://demo.oasis.oati.com/

  35. Look-AheadMichael Hodges

  36. Look-Ahead… • Friday (6/26): Enter data today for Saturday and Sunday • Thursday (7/2): IS Market Trials Meeting (1:30 – 3:00 CST) • Friday (7/3): SPP Closed in Observance of Fourth of July Holiday

  37. IS Market Trials Calendar • Environment Maintenance/Patches • CWG Calendar (spp.org) – communication of minor/moderate changes • CWG Exploder – communication of large and emergency changes (sign-up for on spp.org) • Normal Maintenance Window – Friday Mornings

  38. Important Dates • IS Market Trials in MTE: May 18 – July 17 (MPs Submit Data in MTE) • Deployment and Regulation Qualification Testing: June 1 – June 26 • Last Settlement Statements Posted: Friday, July 24th • Go-Live/Cutover: October 1

  39. Questions