National Environmental Policy Act:. NEPA. Required for all major Federal actions Analyze potential impacts to the human and natural environment and investigate reasonable alternatives Analyses documented in Individual Environmental Reports (IER)
E N D
National Environmental Policy Act: NEPA • Required for all major Federal actions • Analyze potential impacts to the human and natural environment and investigate reasonable alternatives • Analyses documented in Individual Environmental Reports (IER) • Public Involvement is KEY! We want to hear from you! • Goal: more informed decision making through public involvement
IER 11 Tier 1 Decision Record signed March 14, 2008for Borgne 1 and Pontchartrain 2 Where we’ve been Pontchartrain 2 Borgne 1
Two Tier 2 IERs IER 11 Tier 2 Borgne: Alignment and design alternatives within “Borgne 1”Public Release of Draft IER 11 Tier 2 – August 20, 2008 IER 11 Tier 2 Pontchartrain: Alignment and design alternatives within “Pontchartrain 2” (alternatives currently being developed) IER 11 Tier 2: Where we’re going
Alternative Alignments # Gate Designated Natural and Scenic River (portion of Bayou Bienvenue) IER 11 Tier 2 BorgneAlternative Alignments Overview Michoud Canal Michoud Slip 5 4 3 2 1 Bayou Bienvenue Control Structure
Concern of vessels and barges in the Inner Harbor Navigation Canal and the Gulf Intracoastal Waterway during storm events. Concern of the operation of the gates during and after construction, as well as rapid response to open gates after storm has passed through area. Gate size openings and alignments need to safely accommodate barge and navigation traffic. -- Current modeled velocities with a 150 ft wide gate on the GIWW would be approximately 0.6 ft/s which is not expected to have negative impacts to navigation. Snapshot of Public Comments
Construction cost approximately $828 million creating approximately 350 jobs at construction peak. Temporary and permanent impacts from construction activities to property owners around the Michoud Canal. Navigational access and barge traffic along the GIWW would remain functional during construction. On-site construction management would be coordinated closely with the Coast Guard and GIWW navigators to minimize operational impacts. The GIWW sector gate is designed to open and close within 30 minutes to accommodate LOS of barge traffic. Barge gate once constructed could be used as a navigation bypass during maintenance of sector gate. Beneficial impacts to local economy from use of local materials and human resources. Contracting goal of approximately 40 percent local small business, with local economic impact estimated at approximately $186M. 100 year protection and participation in the National Flood Insurance Program encourage the recovery and redevelopment of the New Orleans Metropolitan area. Socioeconomic Impacts
Opportunities for Public Input Monthly Public Meetings throughout New Orleans Metro Area • Make sure to sign in tonight to get on our meeting notification mailing list Comments can be submitted at any time at Individual Environmental Reports (IER) 30-day Public Review www.nolaenvironmental.gov Questions and comments regarding Hurricane Protection Projects should be addressed to: Gib Owen PM-RS P.O. Box 60267 New Orleans, LA 70160-0267 Telephone: 504-862-1337 E-mail: mvnenvironmental@usace.army.mil