E N D
1. Federal Aid 101 Presented by Dan Erickson
And Colleen VanWagner
3. Federal Aid Funds This is a REIMBURSABLE Program
- the work has to be completed before the
Federal dollars are available.
This is not a grant!
4. Process Overview STIP Approval
Project Kickoff Meeting
Local Public Agency (LPA) Project Development
LPA Right-of-Way Acquisition
LPA Plan Preparation
Authorization of Federal Funds
LPA Letting, Contract Award & Approval
LPA Construction, Engineering, and Supervision
LPA Contract Administration
5. FEDERAL FUNDS National Highway System (NHS)
Surface Transportation Program (STP)
Bridge Programs (BR, BH, BROS)
Enhancement Funds (TEA)
Highway Safety Improvement Program (HSIP)
Safe Routes to School (SRTS)
Rail-Highway Crossings (RRS)
Scenic Byways (SB)
Transportation, Community and System Preservation (TCSP)
Interstate Maintenance Discretionary (IMD)
Comprehensive Highway Safety (CHSP)
Emergency Relief (ER)
Non Motorized Transportation (NMTP)
American Recovery and Reinvestment Act (ARRA)
High Priority Projects (HPP) 5
6. Calendars Calendar Year is January 1 to December 31
State Fiscal Year is July 1 to June 30
Federal Fiscal Year is October 1 to September 30
TIP/STIP follows State Fiscal Year.
7. Met Council Roles and Responsibilities Per state statute, Council is designated MPO with advisory committee (TAB)
Council is lead in transportation planning process with TAB input and recommendations
TAB is lead in federal MPO funding programming with Council concurrence
9. TAB Responsibilities Regional process to select and monitor transportation projects funded in part with federal funds
Regional Transportation Improvement Program (TIP) and Amendments including public involvement
Advise on Transportation Policy Plan and planning process
10. Metro transportation programming Transportation Improvement Program (TIP)
TIP amendments
Regional solicitation distributing federal funds
11. Regional Solicitation Distributed ~ $160 million with each of last two biennial cycles:
Surface Transportation Program (STP)
Congestion Mitigation Air Quality (CMAQ)
Transportation Enhancement (TE)
12. Project Criteria Consistency with regional policy
Safety
Cost effectiveness
Readiness
Usage
Air quality improvement
System connectivity
13. Sunset Date Policy Adopted Oct. 2004, Revised April 2005
Expected to meet “program year”
Sunset date March 31 following program year; effective projects beginning 2007/2008
Sunset extension process still exists
No inflationary cost adjustment
Cost index decreases, project cost cap will be lowered.
14. Criteria for Meeting Sunset Date Environmental Document approved
R/W cert. approved or condemnation initiated
Dist. State Aid Engineer approval of plan
Engineer’s Estimate
Special Provisions
Utility Relocation Certificate
Permit Applications submitted
Letting Date to be set within 90 days
15. Sunset Date Extension Requests See handout for submittal information
Agency must illustrate “significant” progress has been made on the project.
Sunset date criteria can be met within 1 yr.
Projects are only eligible for one extension request.
16. Scope Change Required When:
Termini Change
Major Element Removal/additions
New location
Process:
Submit letter (documenting change, reasons, etc)
Starts at Funding and Programming
May result in reduction of Federal Funding
NOTE: A Scope Change could also require a Formal STIP Amendment
17. TIP/STIP Amendment See handout
Formal amendments take about 3 months to get through all committees
Administrative amendments take about 2 weeks
21. Items Needed for Authorization Approved Environmental Document
Approved Right-of-way Certificate (#1 or 1A)
Engineers Estimate
Approved Plan
Permits
22. Additional Timeline to Award Authorization – 2 weeks
Advertisement – 1 month
Award – 2 weeks (just accounting for DBE clearance, Board or Council Mtgs may add more time)
Totaling about 2 months from when authorization is requested.
23. Types of Local Projects -Trunk Hwy Impact Projects Mn/DOT Bridge Design
Mn/DOT Metro Plan Review
CO Plan Review – Interstate
FHWA Full Oversight
Layout Review – Level 2&3 Metro, Level I CO
Municipal Agreement
Mn/DOT Construction oversight
24. Metro State Aid Websitewww.dot.state.mn.us/metro/stateaid/home.html State Aid/Project Development Manual
State Aid Rules
Minnesota Bikeway Guidelines
DCP Process/Checklist
PM Writer
Salt website – www.dot.state.mn.us/stateaid