100 likes | 354 Views
LEASEHOLD IMPROVEMENT GROUP. 19 TH MAY 2011. Contents. Funding Contractor Procurement Programme of Works Pre-works Surveys Notice of Estimates Estimated Bills. Funding. MRA funding approx £12m pa. Before AC inspection provisional allocation £153.8m for catch up works.
E N D
LEASEHOLD IMPROVEMENT GROUP 19TH MAY 2011
Contents • Funding • Contractor Procurement • Programme of Works • Pre-works Surveys • Notice of Estimates • Estimated Bills
Funding • MRA funding approx £12m pa. • Before AC inspection provisional allocation £153.8m for catch up works. • Current allocation £94.5m with £25.5m confirmed. • All exclusive of leasehold contributions but affects the volume of rechargeable work.
Implications of Reduced Funding • Asset Investment Plan developed with MWIG and approved by Board Feb 2010. • Programme to be reviewed. • Fewer dwellings to be improved in early years. • Lewisham Council will have to find additional funding to complete the programme. • Need to start immediately to spend this year.
Contractor Procurement • EU Procurement Process. • Leaseholder Involvement. • Breyer appointed for South area. • Kier withdrew from North area. • S20 Notices issued proposing MITIE for North area.
Programme of Works Initial areas from Asset Investment Plan: • North – Sub-area N01 – SE8 5 and SE16 2 • South – sub-area S01 – SE26 4
Programme of Works Areas selected to commence works: • North N01 – Evelyn Estate • South S02 – Lower Sydenham street properties – e.g. Burghill Road and Bishopsthorpe Rd moving towards Peak Hill.
Pre-Works Surveys • Stage 1 - scoping & electrical surveys – rented dwellings only. • Stage 2 – detailed internal survey of rented dwellings and joint external survey by surveyor and contractor. • Stage 3 – kitchen designer and OT – rented dwellings only.
S20 Notices of Estimates • Stage 1 (Intention) and stage 2 (Proposals) already issued to all leaseholders. • Stage 3 (Estimates) to be issued to affected leaseholders following stage 2 surveys. • Notices of Estimates to be issued at least 30 days before works commence to each block.
Estimated Bills • Estimated bills to be issued approx 6 weeks after works start to each block. • Bills will be for 90% of estimated cost. • Leaseholders will be asked to pay by instalments over 2 or 3 years.