1. January PMR
Pam Emch
Algorithm Implementation Process Lead
1/21/04
3. Useful Algorithm Information on E-Rooms Top-Level Algorithm Processes & Responsibilities
Data Product Algorithm Management (DPAM) Plan - (SE&I, Emch)
https://collab1.trw.com/eRoom/NPOESS/SystemEngineeringIntegration/0_2a3c3
Algorithm Roles & Responsibilities Matrix – (SE, Hughes)
https://collab1.trw.com/eRoom/NPOESS/SystemEngineering/0_c570
Cal/Val
Sensor-Specific Cal/Val Plans - (ST&E, Lottman)
https://collab1.trw.com/eRoom/NPOESS/SystemTestEvaluation/0_24489
Science Algorithm Verification - Plans
NPP EDR Science Algorithm Verification Plan (Overview) – (SE, Hughes)
https://collab1.trw.com/eRoom/NPOESS/SystemEngineering/0_b705
NPP EDR Latency Verification Plan – (SE, Shannon)
https://collab1.trw.com/eRoom/NPOESS/SystemEngineering/0_c58b
Sensor Characterization Tasks data package – (SE, Hughes)
https://collab1.trw.com/eRoom/NPOESS/SystemEngineering/ 0_b705
4. Useful Algorithm Information on E-Rooms, Cont’d Science Algorithm Verification – Algorithm Specific Test Plan, Test Data Description and Test Results
VIIRS [CrIS, etc] Algorithm Testing and Verification Status Reports – (SE, Shoucri)
https://collab1.trw.com/eRoom/NPOESS/SystemEngineering/0_12a62
Specific to each Algorithm: Science Algorithm Test Plan, test data set descriptions, tests conducted, results, AIs, drops to IDPS. Regularly updated.
Specific to each sensor: Algorithm Testing Report provides overview per sensor, including test data sets. Updated by pointers specific to each algorithm at each drop to IDPS.
Post-Drop Algorithm Follow-up Tasks Tracker – (SE, Chu)
https://collab1.trw.com/eRoom/NPOESS/SystemEngineering/0_12a62
NPP EDR Latency Status Report – (SE, Shannon)
https://collab1.trw.com/eRoom/NPOESS/SystemEngineering/0_1b2b1
Science Algorithm Configuration Control and Management
Algorithm RB/CCB (ARB/ACCB) Membership, Description, Guidelines – (SE&I, Emch)
https://collab1.st.northropgrumman.com/eRoom/NPOESS/SystemEngineeringIntegration/0_8be3
ARB/ACCB CM: Agendas, Presentations, ECRs, Minutes – (CM, Dufur)
https://collab1.st.northropgrumman.com/eRoom/NPOESS/ConfigurationManagement/0_cbd3
Algorithm Docs: SCM Control – (CM – Samala)
https://collab1.trw.com/eRoom/NPOESS/SystemEngineering/0_12a62
5. Useful Algorithm Information on E-Rooms, Cont’d Summary Algorithm Status Charts
Monthly PMR Algorithm Status Summary – (SE&I, Emch)
Covers all NPP algorithms on one page
Addresses both schedule and performance at a top level
Updated monthly based on weekly, bi-weekly, and monthly statuses
https://collab1.st.northropgrumman.com/eRoom/NPOESS/ProgramOffice/0_1b51c
Monthly Algorithm Status Roadmap (Prelaunch) – (SE, Hughes)
Covers all NPP algorithms
Updated on a regular basis based on inputs from IDPS, SE
Contains much detail on each algorithm and its progress in the notes feature
https://collab1.st.northropgrumman.com/eRoom/NPOESS/SystemEngineering/0_b705
Bi-weekly GS and IDPS Algorithm Status Summary – (IDPS, Barth & SE, Chu)
Charts are joint IDPS/SE effort
Covers algorithms “dropped” from SE to IDPS to date
Includes details on sci to Ops migration status
Includes assessment of future algorithm task effort/resources required
https://collab1.st.northropgrumman.com/eRoom/NPOESS/SystemEngineering/0_365c8
6. SE IPT chairs VIIRS (weekly) and CrIS/ATMS (bi-weekly) Algorithm Performance meetings
Discuss both hardware and software topics of importance to algorithm and product performance
Detailed technical discussions
Wide attendance
POCs: Phil Moffa for CrIS, ATMS, CMIS; Debra Olejniczak for VIIRS
P/L & SE IPTs organize weekly OMPS technical telecons
Similar scope to above VIIRS, CrIS/ATMS meetings
POCs: Raymond Crew & Maria Caponi
7.
Regular Operational Algorithm Team (OAT) meetings are held
The OATs are advisors to the IPO
SSPR team utilizes OATs for recommendations, “peer” reviews, and possible assistance on ongoing algorithm tasks
All OATs meet nominally every 6 months at a joint “NOAT” meeting
Discuss both hardware and software topics of importance to algorithm and product performance
Detailed technical discussions
Wide attendance includes OATs, IPO, SSPR team, multiple IPTs
OATs meetings are one of the best ways to flow external science community comments and recommendations to SSPR team
POCs: Jim Duda, IPO & Pam Emch, NGST
8. Algorithm Splinter at PMRs
Every month; nominally 2 hrs. long
Excellent opportunity for cross-IPT discussions at a management level
NGST/RC PMR attendees are normally IPT leads, not necessarily technical task executors
POC: Emch
Algorithm Session at SEI F2F meetings
Approx. every 2 months; length determined by topics
Attendees are primarily SEI, both technical and management
Good opportunity to have mid-level technical discussions regarding SEI tasks & issues
Possible to discuss cross-IPT topics based on attendees
Very detailed discussions may require separate focus meetings
POC: Emch
9. Algorithm Session at IDPS F2F meetings
Every 6 weeks; length determined by topics
Attendees are primarily IDPS, both technical and management
Emch to provide top-level alg status (PMR status); remaining portion of session led by SE
Good opportunity to have mid-level technical discussions regarding joint IDPS/SE tasks & issues with access to the broader IDPS team
Should segue to include ST&E and O&S
Very detailed discussions may require separate focus meetings
POC: TBD within SE IPT