1 / 17

Greg Wagoner Manager, Power Supply Wabash Valley Power Association June 6, 2006

Methane Recovery Workshop. Greg Wagoner Manager, Power Supply Wabash Valley Power Association June 6, 2006. “Working with the Electric Utility”. Discussion Points. Overview of Wabash Valley and Programs Interconnection Process & Agreements Power Purchase Agreements Recommendations

Ava
Download Presentation

Greg Wagoner Manager, Power Supply Wabash Valley Power Association June 6, 2006

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Methane Recovery Workshop Greg Wagoner Manager, Power Supply Wabash Valley Power Association June 6, 2006

  2. “Working with the Electric Utility”

  3. Discussion Points • Overview of Wabash Valley and Programs • Interconnection Process & Agreements • Power Purchase Agreements • Recommendations • Questions

  4. Wabash Valley Program • Distributed Generation Policy • Behind the Meter Generation • 10 MW or less • Support • Digester, Wind, Solar, Landfill, etc.

  5. Landfill Power Plants • WVPA owns seven landfill gas generating facilities throughout Indiana • Total of 22 MW

  6. Additional Resources • Adding two landfill sites – 6.4 MW • Commercial within 12 to 18 months • Final stages of entering into PPA for 8.4 MW wind power • Commercial Q4 2006 or Q1 2007

  7. Interconnection Process • Identify local configuration • Local capabilities • Feasibility studies • Interconnection Agreement • Local distribution/transmission provider • Safety, metering, liability, etc.

  8. 69 KV Transmission Line • CASE #3 • M1 • M2 • 6.9 kv / 12kv Sub • Gen • M1 • M2 • CKT. #1 (Load) • CASE #2 • CKT. #2 (Load) • Gen • CKT. #3 (Load) • M1 • M2 • Load • CASE #1 • Gen

  9. Power Purchase Agreement • Establishes Terms & Conditions • Wabash Valley Power • Rates, Contract Term, etc. • Net Billing “not” Net Metering • Utility buys 100% of output • Retail Displacement • Local Facilities • Back-up

  10. Recommendations • Hire an “experienced” developer/contractor • Contact local utility early in process • Understand the issues • Risks • Production capabilities • Prioritize your goals • Lower electricity costs • Environmental objectives • Reliability

  11. Questions?

More Related