1.09k likes | 1.43k Views
** PMP® Training: https://www.edureka.co/pmp ** <br>This Edureka PPT on PMP® Exam Questions and Answers will discuss the top 50 questions which can be asked in your PMP Certification Exam 2018 along with the proper explanation. After going through this PPT, you will have a better insight of which type of questions you must focus on and how to filter out the correct option from the lot.
E N D
PMP QnA PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Project Management Professional® (PMP) Certification Globally acknowledged professional certification program in Project Management PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Project Management Professional® (PMP) Certification Legalizes a professional’s education and experience in Project Management Globally acknowledged professional certification program in Project Management PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Project Management Professional® (PMP) Certification PMP certified project managers command 25% more salaries than their peers Legalizes a professional’s education and experience in Project Management Globally acknowledged professional certification program in Project Management PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Project Management Professional® (PMP) Certification PMP Certificate is very prestigious and is considered to be the golden standard of Project Management PMP certified project managers command 25% more salaries than their peers Legalizes a professional’s education and experience in Project Management Globally acknowledged professional certification program in Project Management PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Job Opportunities PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PM Role wise Salaries 0 35k 70k 105k 140k Director of PM/PMO Portfolio Manager Program Manager Project Management Consultant Project Manager III Project Manager II Project Manager I Project Management Specialist PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
Questions & Answers Copyright © 2018, edureka and/or its affiliates. All rights reserved.
PMP Questions & Answers Q. Define Project Scope. It is the design of experiments that is used to complete the project work. It is the combination of the cost and the schedule which is required to complete the project work. It is the description of the required work that is necessary to complete the project. It is the description of the required work and resources that are needed to complete the project. PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. Define Project Scope. It is the design of experiments that is used to complete the project work. It is the combination of the cost and the schedule which is required to complete the project work. It is the description of the required work that is necessary to complete the project. It is the description of the required work and resources that are needed to complete the project. PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. What is a Program? A very large and complex project A collection of projects which have common resources A collection of sub-projects having a common goal A collection of subprojects having a common customer PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. What is a Program? A very large and complex project A collection of projects which have common resources A collection of sub-projects having a common goal A collection of subprojects having a common customer PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. Which of the following comprises the Project Life Cycle? Phases Milestones Estimates Activities PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. Which of the following comprises the Project Life Cycle? Phases Milestones Estimates Activities PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Being the project manager of the ABC Project , you have allowed subsequent project phase to begin even before the predecessor phase completes. Which of the following relates to this scenario? Q. Crashing Fast tracking Risk management Tandem scheduling PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Being the project manager of the ABC Project , you have allowed subsequent project phase to begin even before the predecessor phase completes. Which of the following relates to this scenario? Q. Crashing Fast tracking Risk management Tandem scheduling PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. The person or group providing the resources and support for the project, program or portfolio and is also responsible for enabling success is called the: Project Manager Senior Management Sponsor Client PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. The person or group providing the resources and support for the project, program or portfolio and is also responsible for enabling success is called the: Project Manager Senior Management Sponsor Client PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. Which of the following cannot be the part of Group creativity techniques: Vendor Bid Analysis Brainstorming Affinity Diagram Nominal Group Technique PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. Which of the following cannot be the part of Group creativity techniques: Vendor Bid Analysis Brainstorming Affinity Diagram Nominal Group Technique PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Being the project manager of a thermal power plant project you need to manage the construction of an administrative unit building. Which of the following technique will you use to quickly estimate and decide the use of historic estimate and expert judgement. Q. Analogous Estimating Parametric Estimating Historical Estimating Expert Judgement PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Being the project manager of a thermal power plant project you need to manage the construction of an administrative unit building. Which of the following technique will you use to quickly estimate and decide the use of historic estimate and expert judgement. Q. Analogous Estimating Parametric Estimating Historical Estimating Expert Judgement PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. What is the acceptable range used for determining the realistic activity cost estimates? Level of Accuracy Units of Measure Level of Precision Cost Management Plan PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. What is the acceptable range used for determining the realistic activity cost estimates? Level of Accuracy Units of Measure Level of Precision Cost Management Plan PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. What is the SPI of a Software development Project where EV = $6,000, PV = $5,000, AC = $4,000? 0.73 1.2 0.8 1 PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. What is the SPI of a Software development Project where EV = $6,000, PV = $5,000, AC = $4,000? 0.73 1.2 0.8 1 PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. Cost baseline is the output of which of the following? Plan Cost Management Estimate Costs Determine Budget Control costs PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. Cost baseline is the output of which of the following? Plan Cost Management Estimate Costs Determine Budget Control costs PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. Suppose you are the project manager on a thermal power plant project. How will you manage your team members, if there is a difference in opinion over the design of turbine? Organize meetings to resolve misunderstanding and agree on a common solution Defer the decision to procure turbine components as much as possible Copy the design of turbine from a similar past project Procure the turbine parts from the nearest located vendor PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. Suppose you are the project manager on a thermal power plant project. How will you manage your team members, if there is a difference in opinion over the design of turbine? Organize meetings to resolve misunderstanding and agree on a common solution Defer the decision to procure turbine components as much as possible Copy the design of turbine from a similar past project Procure the turbine parts from the nearest located vendor PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers You find that an activity in your project is very risky. How will you estimate the duration for this activity when your team member has given the optimistic, most likely and pessimistic duration for the activity? Q. Using variance analysis Using Sensitivity analysis Using PERT formula Using Performance Reports PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers You find that an activity in your project is very risky. How will you estimate the duration for this activity when your team member has given the optimistic, most likely and pessimistic duration for the activity? Q. Using variance analysis Using Sensitivity analysis Using PERT formula Using Performance Reports PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. Which among the following is not valid according to McGreger's Theory X? Employees seek to be directed Employees avoid work Employees are self-centered Employees are self-motivated PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. Which among the following is not valid according to McGreger's Theory X? Employees seek to be directed Employees avoid work Employees are self-centered Employees are self-motivated PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers You are the project manager on a software development project. Your CPI drops to 0.93 when one of your key developers suddenly falls ill. To make up for your effected work, you have decided to outsource it to a vendor. What will be the most appropriate contract type in this case: Q. Retainage FPEPA Cost Reimbursable contract Letter of Intent PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers You are the project manager on a software development project. Your CPI drops to 0.93 when one of your key developers suddenly falls ill. To make up for your effected work, you have decided to outsource it to a vendor. What will be the most appropriate contract type in this case: Q. Retainage FPEPA Cost Reimbursable contract Letter of Intent PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. Who among the following said, “People will be interested in their safety needs only after their physiological needs have been fulfilled.”: Maslow Ouchi McGregor Herzberg PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. Who among the following said, “People will be interested in their safety needs only after their physiological needs have been fulfilled.”: Maslow Ouchi McGregor Herzberg PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. WBS is an excellent and most effective tool that is used for tracking of: Project Resources Project Schedule Project Scope Project Risks PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. WBS is an excellent and most effective tool that is used for tracking of: Project Resources Project Schedule Project Scope Project Risks PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. The best project organization structure for a small but highly technical project will be: Matrix Organization Functional Organization Mixed Organization Projectized Organization PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. The best project organization structure for a small but highly technical project will be: Matrix Organization Functional Organization Mixed Organization Projectized Organization PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Being a project manager is you need to manage a project where there will be a number of persons working together. If you want to enhance the ability of the team to work together and perform as a team which one of the following things you need to do to maximize the ability of the team? Q. Work breakdown structure Staffing Plan Cohabitation Colocation PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Being a project manager is you need to manage a project where there will be a number of persons working together. If you want to enhance the ability of the team to work together and perform as a team which one of the following things you need to do to maximize the ability of the team? Q. Work breakdown structure Staffing Plan Cohabitation Colocation PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. What is the role of the change control board? Assessing the impact of the change on Project objectives Defining requirements for the customer Doing performance appraisal for team members involved in implementing changes Encouraging team members to raise more change requests PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. What is the role of the change control board? Assessing the impact of the change on Project objectives Defining requirements for the customer Doing performance appraisal for team members involved in implementing changes Encouraging team members to raise more change requests PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. Being the project manager on a STP project, you decide to respond to an identified risk by contracting out work. Which of the following will lead to the minimum risk of buyer? CPFF FFP CPPC T&M PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. Being the project manager on a STP project, you decide to respond to an identified risk by contracting out work. Which of the following will lead to the minimum risk of buyer? CPFF FFP CPPC T&M PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. For which process the stakeholder’s engagement assessment matrix is prepared as a part? Identify Stakeholders Manage Stakeholder Engagement Control Stakeholder Engagement Plan Stakeholder management PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp
PMP Questions & Answers Q. For which process the stakeholder’s engagement assessment matrix is prepared as a part? Identify Stakeholders Manage Stakeholder Engagement Control Stakeholder Engagement Plan Stakeholder management PMP® CERTIFICATION EXAM TRAINING www.edureka.co/pmp