1 / 6

TOT3 Archer Interconnection Project

TOT3 Archer Interconnection Project. (Formerly TOT3 300 MW Upgrade Project) Results And Status David Gustad, TSGT August 19, 2010. Project Description. A new substation (called Arrow Substation) tapping the LRS-Story 345 kV line adjacent to Archer Substation

Faraday
Download Presentation

TOT3 Archer Interconnection Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TOT3 Archer Interconnection Project (Formerly TOT3 300 MW Upgrade Project) Results And Status David Gustad, TSGT August 19, 2010

  2. Project Description • A new substation (called Arrow Substation) tapping the LRS-Story 345 kV line adjacent to Archer Substation • A 345/230 kV transformer at Arrow Substation with a minimum rating of 600 MVA • A short (less than 2 miles) 230kV Arrow – Archer transmission line • A 10-mile 230 kV Arrow – Cheyenne transmission line • Upgrade terminal equipment on the LRS – Ault 345 kV line to raise the rating above 2000 A • Upgrade terminal equipment on the LRS – Arrow 345 kV line to raise the rating above 2000 A

  3. Background • Formerly TOT3 300 MW Upgrade Project • Formerly Sponsored by Basin • Sponsorship Changed to TSGT • Based on Alternative C from Wyoming Joint Queue Study (WJQS) • Basin Performed Phase I Study and Comprehensive Progress Report • Phase II Project Review Group (PRG) Kickoff November 21, 2008

  4. Results • New Non-Simultaneous TOT3 Rating of 1844 MW Achieved • Limit-Defining Cell: • CPP at 243 MW • Pawnee Area Generation at 280 MW • LRS at 1140 MW • DC Ties Set East-West (Importing) at 300 MW • No Dynamic Stability Concerns • No Interactions with TOT4A or 4B • No Impact on TOT7 Transfer Capability

  5. Timeline • Final Draft Completed and Submitted to PRG July 22nd • Sent Final Report to PRG August 17th • Next PRG Meeting Monday, August 23rd • Request Approval of Archer Interconnection Phase II Study Report • Start Discussions on TOT3/TOT7 Operating Interactions • Send Report to PCC with PRG Approval, for 30-day PCC Member Review • Request Phase III Status • ISD 4Q 2013

  6. Comments?

More Related