1 / 11

Commercial Awareness for Project Managers

Commercial Awareness for Project Managers. Types of Contract Managing the Client/Contractor Interface Managing Instructions, Variations and Claims Payment Contract Completion. Contractor’s risk. Client’s risk. Types of Contract. Fixed Price Time and Materials Cost-Reimbursable

Gabriel
Download Presentation

Commercial Awareness for Project Managers

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Commercial AwarenessforProject Managers Types of Contract Managing the Client/Contractor Interface Managing Instructions, Variations and Claims Payment Contract Completion

  2. Contractor’s risk Client’s risk Types of Contract • Fixed Price • Time and Materials • Cost-Reimbursable • And various hybrids….

  3. Managing the client/contractor interface • Roles and responsibilities • Review meetings • Document control

  4. Roles and Responsibilities • Named in the contract • Administration and management delegated • Empowered to make decisions ‘Project manager’ Probably one on each side

  5. Strategy review between directors Progress reviews between managers Technical review between engineers Review Meetings • Often at Director Level • Scheduled within the contract • Potentially three types, or levels

  6. Someone wants a change The work is carried out They bring it to the Document Controller The variation is communicated Document Control To control all communications between the two parties Objective: An authorised decision is made

  7. Raised by the client; usually minor, within the terms of the contract Raised by the client; usually cause a change to the terms of the contract Raised by the contractor; asking for more money for having to make changes to the contract Managing instructions, variations and claims • instructions • variations • claims

  8. Managing instructions and variations • Must be issued in writing • By an appropriate authority • Contractor must acknowledge receipt • The cost of additional work must be agreed Should NOT be actioned by the contractor if: • Issued orally • By the incorrect authority within the client • By the contractor without authority

  9. Managing claims Contractor encounters a problem Contractor identifies cost implication Verbal warning to client project mgr. Contractor presents written details of claim Client considers Client disagrees with claim Client approves claim; issues variation Client/Contractor negotiation Contractor receives payment Contractor receives partial settlement

  10. Payment • Against pre-determined milestones • Against valuations of the work achieved to-date The Project Manager will authorise or provide evidence

  11. Contract Completion • Practical completion • Sectional completion • Defects and making good • Final account First Final Completion Certificate Retention Fund Unresolved Issues Snagging List Defects liability period

More Related