1 / 11

Project Managers Report

Detailed update on project milestones, dashboard analysis, critical path items, and office/operational space status. Includes insights on cooling demonstration, job card system, and timeline adjustments. Report highlights risk assessment, schedule, and facilities updates. Interactive elements and detailed specifications are discussed.

vbetty
Download Presentation

Project Managers Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Managers Report CM41 - RAL Roy Preece 10th February 2014

  2. Content • Where are we / Where are we going • Milestones • Dashboard • Installation work • Job card system • Cooling Demonstration • Specification • Office / Operational Space

  3. Critical and Near Critical path items • Orange – <15 days total slack • Yellow - >15 days < 30 days total slack • Step IV Data Taking period starting 11th August 2015 • Hard end date of 1st June 2016 • RF looks to be off of the Critical path but only has 0.5 days total slack so will be treated as on the critical path. • PRY, Magnet and Cavity Installation complete 1st Feb 2017 • Construction complete, including RF without B-Field 24th March 2017 • Commissioning complete, including RF with B-Field 2nd May 2017 To CompletionCritical and Near 3

  4. Milestone ID numbers 1 – 8 are the original milestones tracked in the dashboard. • Milestone ID number 9 – 21 are new and are now tracked I the dashboard. • Reporting on the dashboard and in future Review meetings will be against these baseline milestones. • The period for data taking will be subject to grant requests (UK FY16/17 onward), the final milestone, 21, may be revised after discussion. To CompletionMilestones 4

  5. Work on the PRY base installation took effort away from the water system installation and so is now forecast to be a little later than the baseline. • The rack for SS was a little later than expected and the effort was diverted to other work. • https://micewww.pp.rl.ac.uk/dashboard/V5_020215_MICE_Dashboard.pdf To CompletionDashboard 5

  6. On a monthly basis a progress and forecast report is passed to the STFC Project Risk Committee. • High level view of the projects across the STFC • For a long time the project has been Red on the Risk Register. • Cost and Schedule • Following the recent MPB and RLSR confidence in the project is growing • The latest PRC meeting, after the recent reviews, has down graded the project risk from Red to Amber. • This is a huge endorsement to the project following the recent work in re-scoping the project to completion and the PRC having confidence in our attaining the cost and schedule profile laid out. Project Risk 6

  7. Detailed schedule of installation is being build • Interaction between many teams of mechanical and electrical • During the PRY plate installation long working days will be in action • Heavy equipment being installed • We must be safe in the hall and so general walk about will not be allowed • A job card system has been introduced • Any work for the hall must be put through the job card system, either mechanical or electrical • An online program is being used at the moment with a small group to test the system • Will be rolled out to a wider team soon • Available in any browser • IOS app Hall work 7

  8. Specification for the Cooling demonstration • Capture the requirements for each sub system • Skeleton has been produced and sections will be fleshed out • Three sections • Management • Technical • Physics • It will not be a single documents but a place to link to subject areas already in existence Cooling Demonstration Specification 8

  9. Asbestos work is being carried out soon • Moved much of the spares and equipment • Will need to share with a group from TD • Small experiments • Refurbishment complete June Working Space Moving out of this area Current R9 experimental area ~200m2 Additional Experimental area ~170m2 9

  10. We are now in the Atlas building • Visitor network and EduRoam available • Swipe access is needed to get in and out • Contact Rose and she will get your visitor pass activated, if not already done • Some desks have monitors and keyboards to use, more will be purchased. • Seating plan for regular visitors has been made • If you would like to request a persistent desk space for you institute please ask me and I will allocate a space. • A POD is being purchased and will be installed in the open plan area. • Secure space for MICE NET to be accessed • Remote MICE Control Room • Many status monitors will be installed • A second POD will be purchased for MICE to use as a meeting room Office Space 10

  11. Questions

More Related