PREPARED BY: Balbo Y. Mahunja Project coordinator KIHUMBE YOUTH CENTRE FEBRUARY 2009 REPORT
REPORT CONTENTS • Introduction • Class rooms • Teachers office • Waiting shelter • Furniture and fittings • New students report • Sincere Gratitude
INTRODUCTION • GLOBAL CARE support for renovation of KIHUMBE YOUTH CENTRE for the second phase which cost 69,476 USD has been fully accomplished, pending 9,700 USD left pending for kitchen making.
2 CLASS ROOMS • The project focused on the construction of two class rooms with the capacity of accommodating 45 students each
TEACHERS OFFICE • 2. The project also involved construction of a teachers offices building which contained 4 rooms with 2 toilets
WAITING SHELTER • The shelter which was built at the middle of all the existing buildings intended to serve as the waiting chamber for visitors and students during the break hours
FURNITURE AND FITTINGS • Both classrooms have been fully furnished with desks to accommodate 45 students each. The desks will allow students to remain very comfortable during their study hours
FURNITURE AND FITTINGS • Teachers offices are well furnished with tables and have wall draws which equip staff with a conducive atmosphere for work preparation and other academic assignments
OTHER STUDENTS Male 101 Female 91 TOTAL 192 NEW STUDENTS JAN. 2009 • KIHUMBE ORPHANS • Male 37 • Female 48 • TOTAL 85
SINCERE GRATITUDE • To Knorr Bremse Company Ltd • To Global care team • To Julia and family • Christopher • All indirect related personnel For your commitments, devotion and heartfelt support to make all things happen as planned May all the blessing shower upon your life forever!