SHIPBUILDING AND SHIP PROCUREMENTFOR THE SPANISH NAVY BRIEFING FOR: SCHOOL OF POLICY STUDIES QUEEN'S UNIVERSITY NOVEMBER 2009
SHIPBUILDING PROGRAM ENTERING THE FINAL STAGE OF ONE OF THE MOST AMBITIOUS SHIPBUILDING PROGRAM OF THE SPANISH NAVY HISTORY NOVEMBER 2009
THE SHIPBUILDING MODEL THE SHIPBUILDING STRATEGY IS AT THE CORE OF OUR CAPABILITY TO DESIGN, BUILD, SUPPORT AND EVOLVE, THROUGH THE LIFE CYCLE, THE FLEET NOVEMBER 2009
THE SHIPBUILDING MODEL • THE PILLARS • A LONG-TERM SHIPBUILDING STRATEGY • RULES OF ENGAGEMENT • THE CHALLENGES • THE DELIVER RESULTS NOVEMBER 2009
THE SHIPBUILDING MODEL THE PILLARS NOVEMBER 2009
THE PILLARS OF THE MODEL THEORY OF NICHES NAVANTIA SOLE SOURCE SHIPYARD FABA COMBAT SYSTEMS THE INDUSTRIAL MODEL THE NAVY A PROACTIVE ROLE THE BEST TECHNOLOGICAL PARTNER WE CAN AFFORD NOVEMBER 2009
WHY SOLE SOURCE SHIPYARD? • WE CAN'T AFFORD COMPETITION • LIMITED NUMBER OF CONTRACTS, MANY DIFFERENT TYPES OF SHIPS AND SMALL NUMBER OF SHIPS BY CLASS ( SOME PROTOTYPES) MAKES UNREALISTIC DIFFERENT SHIPYARDS IN COMPETITION • NAVANTIA IS OUR SOLE SOURCE SHIPYARD AND A STRATEGIC ASSET FOR THE NAVY SOLE SOURCE SHIPYARD NOVEMBER 2009
ENGINEERING & PRODUCTIONCRITICAL MASS FERROL FERROL SHIPYARD ROTA CARTAGENA ENGINES SAN FERNANDO PUERTO REAL ALFLOT HQ FABA NOVEMBER 2009
THE ROLE OF THE NAVY • CLEAR DEFINITION OF OP REQS • MAINTAIN THE TECHNICAL SPECS CODE • CONTROL THE SHIPBUILDING PROCESS • COMPETENCY IN THE : • DESIGN • BUILDING • RISK ASSESSMENT • COST ESTIMATE & NEGOTIATION • SYSTEM ENGINEERING • SHIPYARD BUSINESS • DRIVER OF TECHNOLOGY IMPROVEMENTS THE NAVY IN CONTROL OF THE ENTIRE BUILDING PROCESS NOVEMBER 2009
THE SHIPBUILDING MODEL A LONG-TERM SHIPBUILDING STRATEGY NOVEMBER 2009
A LONG-TERM SHIPBUILDING STRATEGY OWN DESIGN PHASE AUSTRALIAN LHDs FUTURE FRIGATE LHD AAW DESTROYER F310 PDA F-100 LPD OWN CONSTRUCTION IMPORTED DESIGN PHASE F-100 LEVEL OF NATIONAL DESIGN S-80 FFG Corvettes DEG S-70 S-60 S-70 XX XXI CENTURY 70’s decade 80’s decade 90’s decade NOVEMBER 2009
THE SHIPBUILDING MODEL THE CHALLENGES NOVEMBER 2009
THE CHALLENGES SOLE SOURCE SHIPYARD THEORY OF NICHES CONTAIN COST IN A SOLE SOURCE SCENARIO CONTINUOUS&COMPETITIVE LONG TERM IMPROVEMENT KEEP KNOW-HOW WITHIN THE NAVY THE BEST TECHNOLOGICAL PARTNER WE CAN AFFORD THE NAVY IN CONTROL OF THE ACQUISITION PROCESS RELEASABILITY ISSUES COMMERCIAL Vs MIL SPCS NOVEMBER 2009
THE MODEL RULES OF ENGAGEMENT NOVEMBER 2009
“RULES OF ENGAGEMENT” • RESTRAIN CHANGES DURING CONSTRUCTION • EMPLOY SAME SYSTEM ENGINEERING AND MANAGEMENT PROCEDURES ACROSS THE PROGRAM • DO NOT START CONSTRUCTION UNTIL DESIGN IS MATURE • SATISFY PERFORMANCE AND SCHEDULE AT ACCEPTABLE RISK AND AFFORDABLE COST • ALLOW FUTURE GROWTH FOR EMERGING OPERATIONAL REQUIREMENTS NOVEMBER 2009
THE SHIPBUILDING MODEL THE DELIVER RESULTS NOVEMBER 2009
F-100 FRIGATE • CONCEPT: FRIGATE FOR AAW SUPERIORITY. A FULL AEGIS IN A 6000 TONS SHIP • ACQUISITION STRATEGY: • NAVANTIA PRIME CONTRACTOR • NATIVE DESIGN FOR THE PLATFORM • AEGIS FMS & NATIONAL DESIGN FOR COMBAT SYSTEM • USN SUPPORT KEY FOR INTEGRATION AND CSSQT NOVEMBER 2009
S-80 A SUBMARINE OF THE NEXT GENERATIOM THE COMBINATION OF AN AIP SYSTEM AND STRIKE CAPABILITY MAKES THE S-80 A SUBMARINE OF THE NEXT GENERATION NOVEMBER 2009
SUBMARINE S-80 • CONCEPT: CONVENTIONAL SUBMARINE COMBINING AIR INDEPENDENT PROPULSION AND STRIKE (TACTOM) • ACQUISITION STRATEGY: • NATIVE DESIGN • PRIME CONTRACTOR NAVANTIA • LOCKHEED MARTIN TECHNOLOGICAL PARTNER FOR THE COMBAT SYSTEM • UTC TECHNOLOGICAL PARTNER FOR POWER CELLS • USN KEY FOR ESTABLISHING THE SUBSAFE PROGRAM AND TACTOM INTEGRATION NOVEMBER 2009
S-80 PROGRAM NOVEMBER 2009
S-80 PROGRAM NOVEMBER 2009
LHD • CONCEPT : A FORCE PROJECTION UNIT THAT COMBINES AMPHIBIOUS, HELO & VSTOL CAPABILITIES • ACQUISITION STRATEGY: • NAVANTIA PRIME CONTRACTOR • NATIVE DEVELOPMENT OF COMBAT SYSTEM AND SENSORS • USN SUPPORT KEY FOR FLIGHT CERTIFICATION AND JSF INTEGRATION NOVEMBER 2009
PROJECTION CAPABILITY NOVEMBER 2009
PROJECTION CAPABILITY NOVEMBER 2009
BAC • CONCEPT : A FORCE SUPPORT UNIT • ACQUISITION STRATEGY: • NAVANTIA PRIME CONTRACTOR • NATIVE DEVELOPMENT OF COMBAT SYSTEM AND SENSORS NOVEMBER 2009
CONCLUSIONS THE SHIPBUILDING MODEL IS OPTIMIZED TO OUR CONSTRAINS AND NEEDS AND HAS PROVEN VERY SUCCESSFUL IN FULFILLING THE MAIN OBJECTIVE OF BUILDING A BALANCED AND MODERN FLEET NOVEMBER 2009