280 likes | 575 Views
Purposes of Competitive Bidding. Prevent FavoritismSecure Goods or Services at the Lowest Prices Encourage Free CompetitionProtect Taxpayer (Public) Money. Process. Does the bid law apply?Request bidsAllow time for preparation and filingOpen and total bidsAward contract to lowest responsible bidderPerformance of the contract.
E N D
1. Competitive Bid Law General Competitive Bidding
Public Works Bidding
2. Purposes of Competitive Bidding Prevent Favoritism
Secure Goods or Services at the Lowest Prices
Encourage Free Competition
Protect Taxpayer (Public) Money
3. Process Does the bid law apply?
Request bids
Allow time for preparation and filing
Open and total bids
Award contract to lowest responsible bidder
Performance of the contract
4. Alabama Code Provisions Competitive Bid Law
41-16-50 through 41-16-63
Public Works Bid Law
Section 39-1-1 through 39-1-2
Section 39-2-1 through 39-2-14
5. General Competitive Bid Law
6. When Does the Law Apply? Contracts for $7,500 or more
Goods or labor
Purchase or lease (inc. lease/purchase)
Used or new equipment
Special rule for heavy-duty equipment (§41-16-52)
7. Bid Law Does NOT Apply To: Contracts Between Public Agencies
Sales of Public Property
State Bids
Emergency Purchases
8. What Entities Are Covered? Municipalities
School Boards
Utility Boards
Public Library Boards
Most Public Agencies
But: There are exceptions
Check the statute!!!
9. What Contracts? Questions to ask:
Is there an exception? (§41-16-51)
Is contract for $7,500 or more?
Look at total expenditures required by the contract!!!
10. Process Does the bid law apply?
YES
Request bids
11. Advertising Requirements Newspaper notice is not required!
Post notice on bulletin board
Mail notice to those who have filed a written request for notice of the solicitation of this type bid (removed after 3 no-bids)
Other notice as board determines
Length of advertising must be reasonable for the project
12. Division of Contracts Forbidden No division of a purchase just to avoid bidding requirements
May legitimately divide a contract if project justifies it and purpose is not to avoid bid law
13. Joint Purchasing Ordinance (or Resolution as the case may be) by each entity
Contents:
Items or services to be purchased
Manner of advertising and awarding of contracts
Method of splitting the costs of the contract
Other matters determined by the entities
May designate a joint purchasing agent
14. Process Does the bid law apply?
YES
Request bids
Allow time for preparation and filing
Open and total bids
15. Time for Preparation Varies based on circumstances
Does bid require bidder to prepare?
Does bidder have to contact subcontractors?
Is this an emergency?
May need to allow bidders time to prepare a set of specifications
Must be reasonable
16. Bid Opening Bids must be sealed - no faxed bids
Opening must be public
Bids are tabulated & presented to council at next meeting
17. Bonding Requirements All contracts over $10,000 must have a bid bond
Board determines the amount of bond
Should protect the board against a change that would cause substantial loss
Must be executed before bid can be considered
Can submit irrevocable letter of credit instead
18. Who is the Low Bidder? Lowest unit price of an article
Warranty may only be considered for determining if bidder is responsible
May depend on specifications (alternative bids, etc.)
19. What is a Responsible Bidder? Have you had problems with this bidder in the past? (Documentation?)
Do you know of others who have had problems? (Documentation?)
Can they deliver promised products on time?
Has bidder qualified to do business in Alabama?
Does bid meet specifications?
20. Rejection of Bids Reason for rejecting low bid and accepting another must be stated on successful award & left open to public inspection
Can reject if price is excessive or quality is inferior
21. Process Does the bid law apply?
Yes
Request bids
Allow time for preparation and filing
Open and total bids
Award contract to lowest responsible bidder
22. Awarding Bid Local Preference
Other Preferences
Conflicts of Interest
Limit on Term of Service Contracts
Procedure for One or Fewer Bids
Resolution Necessary
23. Penalties Collusive Bids
Contract Void
Advance Disclosure of a Bid
Statute of Limitations
24. Process Does the bid law apply?
Request bids
Allow time for preparation and filing
Open and total bids
Award contract to lowest responsible bidder
Contract Performance
25. Contract Performance Retainage
Records Maintenance
Performance Bonds
Contracts Not Assignable Without Permission
26. Quantum Meruit No recovery on contract
Applies where board receives an unjust enrichment
Allows payment for work done or materials provided where mistake was small or inadvertent
27. Public Works Bidding 39-1-1 through 39-1-2
39-2-1 through 39-2-14
28. What is a Public Work Project? Construction, repair, renovation, or maintenance of public facilities
financed in whole or in part with public funds
with financing that is retired with public funds
Examples
Buildings, structures, sewers, waterworks, roads, bridges, docks, underpasses, and viaducts
29. Process Does the bid law apply?
Request bids
Allow time for preparation and filing
Open and total bids
Award contract to lowest responsible and responsive bidder
Contract Performance
30. Public Works Bidding DOES THE LAW APPLY?
31. When Does the Law Apply?
All public works projects involving an “awarding authority” for
Contracts for $50,000 or more
32. Exceptions Use of public employees
Contracts with other public agencies
Sales of property
Contracts for program management in support of public works that do not involve construction, etc.,
Use of Convict Labor
Projects under $50,000
33. Advertising Requirements Split advertising requirements
Under $500,000
Newspaper published in the municipality, or
Post on bulletin board
Send notice to all interested persons (may remove after 3 no bids)
Over $500,000
Three newspapers of general circulation throughout the state
34. Advertisement Must: Describe the improvement
State that plans and specs are on file in an office of the awarding authority
State procedures for obtaining plans and specs
State when and where bids will be received and opened
State whether prequalification is necessary and how to obtain prequalification information
35. Sole Source Bidding No sole source venders unless:
Documentation to State Building Commission
product or service is indispensable
no viable alternatives and
product or service is the only one that fulfills the function
Architect or engineer has recommended
All info is documented and available for inspection at time of advertising
36. Emergencies Must be declared in writing by the awarding authority
Must set forth the nature of the danger to the public health, safety or convenience
Can be let only to extent necessary to meet the emergency
Actions taken and reasons must be made public upon request
37. General Information Open bids at time and place specified
No splitting bids to avoid bidding requirements
Penalties:
Contracts in violation are void
Class C felony - Minimum - One year and a day, Max - 10 years
Fine up to $5,000 or double gain to defendant or loss to the victim
38. Bid Documents Must have adequate number on hand for prime contractors
May charge a deposit
39. Bid Guarantees With bid, bidder must:
File with bid a cashier’s check drawn on an Alabama bank, or
A bid bond executed by a surety company qualified in Alabama
Amount is not less than 5% of estimated project cost or bid
Capped at $10,000
This is the maximum guarantee required!
40. Prequalification Must be written, and
Published
Relate to the contract purpose
Relate to quality of product or service
Relate to responsibility and ability of the bidder
Permit reasonable competition
Publication may run with bid request, if it meets above requirements
41. Prequalification (cont.) Awarding authority has right to determine if contractor meets prequalification criteria
Any prequalified bidder is deemed responsible, unless revoked by:
Written notice
Hearing
Good faith showing by authority
Revocation within 10 days of notice
Awarding Authority retains right to judge responsibility of bidders
42. Return of Guarantees All but lowest three bidders must be returned immediately after bids are checked and tabulated
Lowest three are returned once contract bonds and the contract is executed
43. Contract Award Awarded to lowest responsible AND responsive bidder
Responsible bidder:
Competent, experience and financially able to perform contract
Responsive bidder:
Submits a bid that complies with terms and conditions of bid invitation
44. Notification of Award At earliest possible date, notify successful bidder in writing by:
telegram
confirmed fax
or letter
If winner refuses to sign contract or provide bond or insurance, award goes to second lowest bidder, then third.
45. If One or Fewer Bids: Advertise for and seek other competitive bids
negotiate for the work through the receipt of informal bids (provided that work is done for price lower than that bid)
46. If Negotiation is Used: Allow the Department of Examiners of Public Accounts to review:
The plans and specs, an itemized estimate of costs, and all informal bids, and
On completion of the project, the final costs, including any and all changes made to the original plans and specs
47. Award of Bid Successful bidder must (when required):
Enter into written contract on form included in the proposals, plans and specs
Give performance bond and payment bond
Provide evidence of insurance either within time set out in the bid or, if bid is silent, within 15 days of receiving the contract
Board may grant 5 extra days for return of contact
48. Bond Approval Within 20 days of receiving the contract and other materials from the bidder, the awarding authority must
approve the bonds
approve the evidence of insurance, and
execute the contract
Contractor may agree in writing to an extension of time
49. Proceed Order Within 15 days of the final execution of the contract, the board must issue a proceed order
Parties may agree, in writing, to an extension of time for the issuance of the proceed order
50. Guarantees If Contractor Fails to Act:
The board shall retain from the proposal guarantee the difference between the amount of the contract as awarded and the amount of the proposal of the next lowest bidder.
If only one bid, the full guarantee may be retained as liquidated damages
51. Guarantees If the board fails to execute the contract and issue a proceed order, contractor may withdraw the bid without forfeiture of the guarantees
52. Mistakes If low bidder discovers a mistake, bidder may, without penalty:
Give written notice to the board within 3 days of the bid opening, and
Provide clear and convincing evidence of mistake due to calculation, or clerical error, inadvertent omission, or typo
53. Mistakes (cont.) Board must permit withdrawal without forfeiture
Board must decide within 10 days of receiving the evidence, or at the next regular meeting
Mistake of law, judgment or opinion is NOT a valid ground to withdraw bid
54. Mistakes (cont.) If bidder withdraws due to mistake, the bidder is prohibited from:
Performing any work on the project, either as a subcontractor or other capacity
Bidding on the same project if it is re-advertised for bids
55. Bidder’s Requirements Before beginning work, the bidder must:
Execute a performance bond equal to 100% of the contract price
Execute a second bond of at least 50% of the contract price, promising to pay all subcontractors and for payment of attorneys fees to enforce the bond
56. General Provisions After Award No contract may be assigned without written consent of the awarding authority and no assignment may be made to an unsuccessful bidder who was not responsible or responsive.
57. Partial Payments Unless otherwise provided in the specs, the board must begin making partial payments:
at the end of each calendar month, or
as soon thereafter as practicable
Material and work covered by partial payments becomes the property of the board.
58. Partial Payments (cont.) Authority may retain from partial payments:
No more than 5 % of the estimated work done, and the value of materials stored on site, or suitable stored and insured off-site
Once 50% of the job is completed, no further retainage shall be withheld
Retainage held until job is finished and accepted
59. Retainage Money belonging to the contractor which has been retained by the awarding authority conditioned on final completion and acceptance of all work in connection with a project or projects by the contractor
60. Nonresident Contractors To obtain retainage, a nonresident contractor must satisfy the board that all taxes due and payable to the state and all political subdivisions have been paid.
61. Escrow Account or Security May be used in lieu of retainage
Board has the right to decide which is used
Escrow account has conditions
Contractor may deposit securities and withdraw retainage, subject to conditions
62. Completion of Contract Upon completion and acceptance of work, but not until 10 days after the advertisement of the completion as required, the contractor must give the board:
An executed and certified voucher for payment;
A release, if required, of all claims and liens against the board, other than contractor liens;
Proof of advertisement
63. Completion of Contract (cont.) Board shall, before execution of final contracts and bonds:
Certify that contract complies with bidding requirements
Certificate constitutes a presumption that the bid law was followed. Can only be overcome by clear and convincing evidence that certificate is false and that the contractor knew it was false
64. Advertising Completion Contracts of $50,000 or more - contractor must give notice of contract completion:
Advertise in a newspaper in general circulation published within the city where work has been done. For 4 successive weeks
No final settlement until 30 days following completion of notice
Proof of publication is by affidavit of publisher and a printed copy of notice.
65. Advertising Completion (cont.) If no newspaper, post at courthouse for 30 days
Proved by probate judge, sheriff, and contractor
Public works contracts below $50,000 – Board advertises:
Once in a newspaper of general circulation in the county and
Posts final completion on bulletin board for one week
Authority requires contractor to certify under oath that all bills have been paid
66. False Certification Willful or fraudulent issuance of certification is a felony
Punishment:
Fine between $5,000 and $50,000, or
Jury may sentence violators to prison for one to three years
67. Enforcement To recover paid public funds, action may be brought by:
Attorney General
Any interested citizen
Must be clear and convincing evidence of a knowing violation before the execution of the contract
Statute of limitations is three years of contract settlement
68. Enforcement (cont.) To enjoin the contract, action may be brought by
Attorney General
Any interested citizen
An unsuccessful bidder
Bidder who wins may recover reasonable bid preparation costs
Statute of limitations is 45 days of contract award
69. Quantum Meruit No quantum meruit for work done or materials furnished pursuant to a contract in violation of the public works bid law