340 likes | 1k Views
Tennessee Tombigbee Waterway Development Opportunities Conference. FY 2008/2009/2010 O&M PROGRAM. * Includes $5.7M for Mooring Cells and Lock Closures * Includes $1.8M for Water Control Manuals * Includes $550K for Water Control Manuals * American Recovery and Reinvestment Act (ARRA)
E N D
Tennessee Tombigbee Waterway Development Opportunities Conference
FY 2008/2009/2010 O&M PROGRAM *Includes $5.7M for Mooring Cells and Lock Closures *Includes $1.8M for Water Control Manuals *Includes $550K for Water Control Manuals *American Recovery and Reinvestment Act (ARRA) **Received an additional $4 Million Supplemental Funding for Dredging
TENN-TOM O&M FUNDING FOR FY02 – FY09(President’s Budget + Appropriations)
American Recovery and Reinvestment Act (ARRA) O&M Funding by Business Program $48.6M $5M $105.5M $59.1M $9.5M
Mobile Harbor Turning Basin • Type of Work: New • Depth: 45 Feet • Quantity: 2.6Mcy • Type of Material: Sand, Silt and Clay • Disposal Area (D/A): Upland/Ocean • Distance to D/A: 35 miles (Ocean) • Type of Equipment: Bucket/Pipeline • Contract Awarded: 8 Jul 09 • Contractor: Great Lakes D &D Co. • Start Work: Around late Aug 09 • Completion: Projected in March 2010 Project Costs CG Federal $6M CG Non-Federal $2M ARRA Federal $16M ARRA Non-Federal $5M Total $29M
ARRA • Key Focus Areas: • Job Preservation and Creation • Infrastructure Investment • Energy Efficiency • Projects • Backlog Maintenance/Buy Down Risk • Energy Efficiency • Focus on quick execution/job creation • Cooperation of users during outages
TTWW DREDGING PROGRAM FY2007 Work • Inland Dredge KELLY L • 10 July – 21 August 2007 (43 days) • 4 Most Critical Locations • Approximately 10,000 linear feet of bars, 191,000 cubic yards of material removed • Several locations werenot dredged due to funding limitations FY2008 Work • No Project Contract due to funding limitations • Issued Task Order to Shared 16”/24” Dredge Contract with Coastal Project • Dredged 2 Locations • Approximately 6,500 linear feet of bars, 130,000 cubic yards of material removed • Increased Survey Efforts to Monitor Channel Conditions • “Hot Spots” Removed with R.W.DAVIS
TTWW 2009 DREDGING PROGRAM Supplemental Funding • Received $4 million • ENCO Dredge “EDWARD G” (subcontract to Mike Hooks, Inc.) • Approximately 9 bars – 225,000 cy ARRA Funding • Received $8 million • $4.2M Committed for 2009 (balance carry over to FY10) • Inland dredge “INGENUITY” • Approximately 8 bars – 350,000 cy
DREDGE MATERIAL REMOVAL WORK • Regain critical disposal capacity • Agreements for removal of materials • Beneficial use of materials • Barge to Louisiana & Gulf Coast • Truck to local markets • Approximately 200,000 cubic yards removed
O&M CONTRACT • TTW’s O&M Contract expired September 30, 2008. • Maintenance work performed under BWT’s O&M contract from October 1, 2008 through April 8, 2009. • New TTW O&M contract awarded April 7, 2009.
LOCK CLOSURES • Selden Lock: September 9 – October 8, 2009 • Coffeeville Lock: September 11 – October 1, 2009 • Bankhead Lock: September 14 – October 4, 2009 NOTE: Next Scheduled Lock Closures on the Tennessee-Tombigbee Waterway (2011) are Wilkins Lock, Bevill Lock and Heflin Lock.
Remove a portion of the island and dredge to elevation 116.0 Remove dogleg and 100 feet of existing spur dike Dredge the upper approach to elevation 110.0
Construct a system of nine submerged bendway weirs Relocate the Snagboat Montgomery
AQUATIC PLANT MANAGEMENT • O&M Contract • Treated To Date – 778 acres • Projected Through End of FY – 775 acres • ARRA - Helicopter Contract (Projected Through End of FY) • Floating Plant Treatment – 1400 acres • Submersed Plant Treatment – 1000 acres
Tennessee-Tombigbee WaterwayCanal Section Levee Certification 20 August 2009
Certification • PAL > Analyses > Report > FEMA • 2 yr. max. • Monroe, Itawamba, Tishomingo counties • 31 August deadline to sign request or decline to seek accreditation
Certification Requirements • 44 CFR 65.10 and complementary USACE and FEMA regs • Required report Submittals • Engineering Analyses • Operations and Maintenance Plans • As-Builts • Stamped by Engineer • USACE requirements more comprehensive and exhaustive
Issue Authority – Public Law 79-525, 79th Congress, 2d Session, enacted July 24, 1946. Two-way barge traffic, no provisions in the authorization for flood control protection . . .
Issue Certification – no analyses exist that refute or demonstrate flood control performance; required analyses are extensive. Hydraulics, geotechnical, vegetation compliance, O&M . . .
Issue Vegetation – currently heavily wooded, can not certify unless vegetation and roots removed. Would also require increased annual O&M to sustain levee requirements. . .
Issue Wildlife Mitigation – Wooded areas on levee are part of Tenn-Tom mitigation lands. Clearing would likely require acquisition of replacement lands. . .