Spine Status. R. Bates Glasgow University, Anatoli Holodenko IHEP. Spines by type. Over sites have 83% of required good spines, after making mechanicals, and pre-quals. Spines at each module site. Spines shipped since last year.
E N D
Spine Status R. Bates Glasgow University, Anatoli Holodenko IHEP ID week, CERN
Spines by type • Over sites have 83% of required good spines, after making mechanicals, and pre-quals. ID week, CERN
Spines at each module site ID week, CERN
Spines shipped since last year • Fall in November due to delay in spines reaching CERN shipping problem • 6 months with > 180spines ID week, CERN
Cumulative totals delivery ID week, CERN
Delivery from IHEP to CERN • IHEP making inners from new order, 70 delivered • 60 Middles from original order still to come ID week, CERN
New contract • All new contracts were signed last December • Extra TPG • All material has been delivered in November • Payment from CERN very late • ISTC • Delay see next slide • Contract with IHEP to machine parts and assembly spines • Paid and money at IHEP ID week, CERN
ISTC contact • Covered extra shipping costs and new ceramics for extra order • Signed on time BUT • Contract LOST between CERN and ISTC during Christmas holiday • New copy sent, invoiced raised and CERN paying • Delay due to payment taking time • ISTC won’t/can’t work without payment taking place • Markus Nordberg has pushed CERN finance to speed up the process. • In the meantime • Can’t use DHL as custom papers demand shipping takes place via ISTC. • Spines been sent by hand (thanks to Sasha Cheplakov for help) over 100 this year so far. • Some of the extra material purchased from Glasgow account • Payment will be made tomorrow • Assume at least 1 week delay to get spines from IHEP to CERN • Will be a little tight if delay is longer than 2 weeks. ID week, CERN