1 / 14

QPS: "What was learned from HWC"

QPS: "What was learned from HWC". MOPS training lesson 6 R. Denz AT-MEI. Outline. Present state of the QPS system and planned evolution of the system Problems observed during hardware commissioning HC specific problems Non HC related problems QPS system faults

abeni
Download Presentation

QPS: "What was learned from HWC"

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. QPS: "What was learned from HWC" MOPS training lesson 6 R. Denz AT-MEI

  2. Outline • Present state of the QPS system and planned evolution of the system • Problems observed during hardware commissioning • HC specific problems • Non HC related problems • QPS system faults • QPS faults caused by other systems • QPS controls • Interventions into LHC • Regular maintenance • Interventions in case of non-conform behaviour • QPS piquet • Conclusions QPS web: https://at-mel-pm.web.cern.ch/at-mel-pm/ QPS logbook: http://elogbook.cern.ch/eLogbook/eLogbook.jsp?lgbk=340

  3. State of QPS • Present state of the QPS system • Having survived HC, QPS is now basically ready for operation • Transition phase between commissioning and operation • Some issues left over from HC, e.g. circuits not fully commissioned, wrong configurations etc. • Firmware upgrades for some type of controllers • Issues to be closed by the end of the month • Short term evolution • Installation of Remote Reset Units • Rack supervision, power cycle of “lost” systems without access • Upgrade to 7 TeV operation • Following the outcome of HC commissioning and the expected amount of training quenches required to reach 7 TeV the QPS protection system needs to be upgraded for better detection of symmetric quenches • ECR to be issued soon – some more testing required (this week)

  4. QPS – HC specific problems • Polarities, layouts, cabling, settings, filters, algorithms etc • Basically all sorted out but proper documentation still to be done • Normally not to be expected to affect LHC exploitation • A few problems still to be fixed • Circuits not yet fully commissioned • Current limit for MCBXH/V powering • Spares management • Updates may be required in case of • Obsolete components, systems, tools (e.g. compilers) • Change of requirements by beam physics (e.g. 600 A circuits) • Increasing luminosity of the LHC – radiation effects

  5. QPS system faults - introduction • QPS and EE systems comprise • 6200 quench heater power supplies (100 % needed for pilot beam) • 6400 quench detection systems (97.5% needed for pilot beam) • 32 13 kA energy extraction systems (100 % needed for pilot beam) • 202 600 A energy extraction systems (80 % needed for pilot beam) • 2200 fieldbus couplers (99 % needed for pilot beam) • System reliability • Most of the systems have already reached the bottom of the famous bathtub curve • Still some teething problems • Transition phase from commissioning to exploitation

  6. QPS system faults I • Quench heater circuits • To be checked after every trigger / discharge • Powering must be stopped in case of doubt as repeated firing of damaged heaters may affect magnet integrity • Quench heater power supplies • Slow discharge  ST_POWER_PERM (QPS power permit) removed if below 810 V  typically main switch is broken  repair in situ possible • Power supply does not re-charge correctly after a trigger  no QPS power permit  power supply must be replaced

  7. QPS system faults II • Detection systems in general • All systems are fully redundant • Loss of communication normally does not affect protection • Detectors are to a very large extent “fail safe”, i.e. faults will activate the interlocks • Main magnet protection systems • MB, MQ protection systems normally very stable • Somewhat higher fault rate in the not so dry part of the machine (sector 3-4) • IPQ, IPD and IT protection systems • No particular faults after HC revealed • 600 A circuit protection • Drifts of detection systems (magnets only)  RESET prior to run • New controller firmware generates regular automatic software resets (only if |I| < 5 A) • Most sensitive systems with respect to noise (EMC)

  8. QPS faults related to or caused by other systems • AC powering: power cuts • Several problems observed with UPS system (10 minutes autonomy guaranteed in case of mains loss) • The weak point seems to be the link between the UPS and the client • Power cuts affecting QPS will in any case activate the interlocks and the energy extraction systems • The quench heaters are not fired in case of a total loss of power  unprotected magnet during discharge of the circuit • Re-start of QPS after a power cut may require expert intervention • AC powering: over-voltages other than spikes • One serious event observed in RE88 (alcove)  damage to equipment • Cooling and ventilation • Loss of cooling water  13 kA EE systems only • Humidity in sector 3-4

  9. QPS control system I • QPS users and their access rights • Monitor: can observe only • Operator: can access all commands required for LHC operation • Expert: can access all commands – supposed to know what she or he is doing but human error is never excluded • Access to QPS controls only via technical network TN • i.e. terminal server, CCC console, trusted machine on TN • two LOGIN required from home (still possible) • Basic applications • QPS supervision (PVSS based) • QPS expert console • PM viewer • TIMBER (logging data)

  10. QPS control system II • Critical commands and actions • RESET • Software reset of a QPS controller and the associated protection systems • Does not fire heaters, interrupts transmission of PM data, may trip powered 600 A circuits • Macro for sending a RESET command prior to start of ramp • TEST MODE • Generates an artificial quench signal • Required for test purposes only – not needed for operation • Operation of Remote Reset Units (not yet installed) • So far only attached to 600 A systems (other systems in preparation) • Accidental activation will stop powering of corresponding circuits

  11. QPS control system III • Communications problems – various reasons • QPS controller: only a few circuits related to that controller affected • Power cuts: a group of controllers also of different type is affected • Fieldbus infrastructure (repeaters, cabling etc.) many circuits affected • Gateways (frontend computers): all circuits linked to one or two fieldbus segment affected • RESET of QPS gateways • Only if OK from EIC and QPS expert

  12. Interventions into LHC I • General remarks • All QPS and EE equipment is installed inside controlled zones (exception IT protection .L5 I USC55) • Clearance by RP required • Some QPS spare parts, e.g. quench heater power supplies already stored in LHC • MAD only required for material transport and bicycles (access to tunnel and point 7) • Bicycles and trailers soon to be parked in LHC • Regular maintenance • Exchange of broken systems not affecting LHC operation • System updates • According to LHC schedule • R&D ongoing to minimise interventions into the LHC

  13. Interventions into LHC II • Interventions in case of non-conform behaviour affecting LHC operation • Exchange of equipment, re-start, reset etc. • Only by QPS experts or explicitly authorised staff • Interventions to be coordinated with LHC operation • Piquet services • General AT-MEI piquet for ELQA, current leads, QPS and EE issues • Team currently being setup: 1st line 162266 2nd line 163162 (not yet operational) • Training of the team to be started soon • Specialist support on best effort

  14. Conclusions • QPS and EE systems are built to protect LHC superconducting circuits – second priority is to protect the beam • Triggers of the system are normally not related to faults • Most of QPS and EE systems required to inject pilot beam – all are required for nominal beam • QPS and EE systems are to a very large extent “fail safe” • Faults will prohibit LHC operation but should not cause any further damage • LHC operation just started • Challenging time for all concerned systems, QPS and EE systems are no exception

More Related