Re-Introduction • Design a styrene plant on HYSYS, a computer simulator • Capacity: 2 billion lbs/year • $0.70/lb • 14% of US production • New chemical process • Ethane instead of Ethylene
Design Process • Research • Base Case • Detailed Equipment Design • Reactors • Separations • Other equipment • Economic Optimization • Finalized Design
Struggle • Separations • Not in patents • Heuristics • No kinetic data • Cannot determine a rate law • Assumed conversion and selectivity
Changes since December • Kinetics • Working base case • Optimization beginning • Catalyst regeneration plan • More detailed schedule • Plant Details • 50-60 acres • Texas/Louisiana