MUCOOL ADVANCED M.T.F. & M.I.C.E. LAYOUTS. August 12-13, 2002 Edgar L. Black IIT. CURRENT EFFORTS FOR M.T.F. FINALIZE DETAILS OF FORCED COOLANT FLOW ABSORBER TO BE INSERTED INTO THE LAB G MAGNET. COORDINATE DESIGN OF THE CONVECTIVE TYPE ABSORBER FOR THE SAME LOCATION (KEK COLLABORATION).
E N D
MUCOOL ADVANCED M.T.F. & M.I.C.E. LAYOUTS August 12-13, 2002 Edgar L. Black IIT Edgar L. Black
CURRENT EFFORTS FOR M.T.F. • FINALIZE DETAILS OF FORCED COOLANT FLOW ABSORBER TO BE INSERTED INTO THE LAB G MAGNET. • COORDINATE DESIGN OF THE CONVECTIVE TYPE ABSORBER FOR THE SAME LOCATION (KEK COLLABORATION). • COMPLETE WINDOWS DESIGN WITH SHOP DRAWINGS FOR FABRICATION (TO BE SUBMITTED TO THE MISSISSIPPI COLLABORATION AT THE END OF THIS MEETING). • INITIATE THE INTERFACE RESOLUTION OF UP & DOWN SIDE VACUUM WINDOW DESIGN REQUIREMENTS, (INCLUDING IMMEDIATE AND FUTURE EXPERIMENT PROGRAMS) • START INSTRUMENTATION HARDWARE INTEGRATION DESIGN FOR THE IMMEDIATE TEST PLANS. Edgar L. Black
MAGNET, CRYOSTAT & ABSORBER LAYOUT Edgar L. Black
MTF ABSORBER FORCED FLOW Edgar L. Black
WINDOW/ ABSORBER SEAL DETAIL(SECTION OF THE MANIFOLD) Edgar L. Black
ABSORBER WINDOW DETAIL Edgar L. Black
WINDOW TEST PLATE Edgar L. Black
VACUUM VESSEL WINDOW Edgar L. Black
CURRENT EFFORTS FOR M.I.C.E. • NEED MORE STUDIES TO INTEGRATE NEW M.GREEN MAGNET DESIGN INTO THE SFOFO1 CONFIGURATION (CONFLICT WITH THE RF FEEDS). • INITIATED PLANT LAYOUT COORDINATION FOR THE INSTALLATION AT RAL (COMMUNICATION WITH IOURY) • NEED MORE INFORMATION ON THE PLANT FACILITIES Edgar L. Black
SFOFO/M.I.C.E. CONFIGURATION Edgar L. Black
M.I.C.E. SFOFO Edgar L. Black
LOCATION IN QUESTION PARTIAL VIEW OF THE R.A.L. FACILITY Edgar L. Black
LOCATION ENLARGED Edgar L. Black
FUTURE ACTIVITIES WITH TIME DURATIONS (HRS) 1- FABRICATION OF 21CM WINDOWS AND PRESSURE TEST PLATES. 480 3 OR 5 WINDOWS FOR EACH MATERIAL? 2 - RESOLVE VACUUM WINDOW ISSUES AND COMPLETE THE DESIGN FOR FABRICATION 80 3 -PERFORM PHOTOGRAMETRY MEASUREMENTS OF THE AS BUILT WINDOWS AT FERMILAB. 300 5 - SET UP FACILITY AT N.I.U. FOR WATER AND CRYO PRESSURE BURST TESTS AND TEST. 80 6 - PERFORM PHOTOGRAMETRY MEASUREMENTS DURING TEST AT N.I.U. 100 7 - FABRICATION OF MANIFOLD ASSEMBLY AND ACCEPTANCE TEST. 200 8 - COMPLETE INFRARED HEAT TRANSFER FLOW WITH THE 15 CM MANIFOLD ASSEMBLY. 60 9 - PROCURE (OR BORROW) VERTICAL CRYOSTAT FOR THE ABSORBERS FLOW TEST. 160 OR 60 10 - SETUP CRYO FLOW TEST SYSTEM (AT FERMILAB OR N.I.U.) AND PERFORM TESTS. 320 Edgar L. Black