1 / 8

Solar Eclipse August 2017 LADWP Impact & Preliminary Plan

Solar Eclipse August 2017 LADWP Impact & Preliminary Plan. ~5500MW peak load (high assumption) ~5530MW Thermal Gen ( Incl ~800MW quick start/fast ramp capable) ~2030MW Hydro Gen (Most units quick start/fast ramp capable) 440MW Wind Gen ~1240MW Solar Gen

adamdaniel
Download Presentation

Solar Eclipse August 2017 LADWP Impact & Preliminary Plan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Solar Eclipse August 2017LADWP Impact & Preliminary Plan

  2. ~5500MW peak load (high assumption) ~5530MW Thermal Gen (Incl ~800MW quick start/fast ramp capable) ~2030MW Hydro Gen (Most units quick start/fast ramp capable) 440MW Wind Gen ~1240MW Solar Gen (incl ~230MW behind the meter estimate)

  3. ~ 1240MW Total Solar Gen (%obscuration & times from https://eclipse2017.nasa.gov/eclipse-maps) • ~230MW Behind the Meter in LA area (estimate) • ~60% obscuration • 0905-1144hrs, 1021hrs max • ~15MW Apple Valley area • ~65% obscuration • 0906-1147hrs, 1022hrs max • ~490MW Mojave/Tehachapi area • ~65% obscuration • 0905-1145hrs, 1021hrs max • ~500MW Las Vegas area • ~70% obscuration • 0909-1153hrs, 1027hrs max

  4. LADWP is still in process of determining • Expected Solar gen drop • Max magnitude • Ramp rate down and up

  5. LADWP Total Solar Trend Late August 2016 • about double the Solar Gen this August

  6. LADWP Load Trend, same day as above

  7. We expect to use same operating principles used during cloudy days. • Carry additional reserves for expected gen drop • Have sufficient ramp capability to keep up with both • Solar Gen drop ramp down • Rising Load curve

  8. LADWP will minimize outages/de-rates on fast ramping generation resources. Note: If insufficient fast moving gen online/available to keep up with ramp of simultaneous solar drop & load increase, LA may choose to pre-emptively curtail Solar gen to expected output during max obscuration.

More Related