An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Week of July 14-20, 2013 OperationsJuly 3, 2013 DCS Event Reliability Committee August 15, 2013 John Norden Director, Operations

  2. Preparations for the Week of the 14th thru 20th • All transmission work and generation outages and reductions that could be postponed or cancelled were completed prior to heat wave • ISO New England Operations Staff had preparatory meetings with the following entities prior to and during the heat wave: • NYISO, HQ, NBSO, IESO, PJM and MISO Reliability Coordinators • Master Local Control Centers • Gas Pipeline Operators • Implemented M/LCC #2 at 1045 on Monday, 7/15/13 • Forecasted tight operating reserves throughout the week

  3. Preparations for the Week, cont. • Weather deviations from forecast impacted load forecast accuracy. This was particularly the case on Thursday when the temperatures dropped significantly along the coast due to an afternoon sea breeze • Actual average temperatures were lower than forecast by an average of 1.1°F during peak hours throughout the week. • Boston temperatures on Thursday during peak hours were lower than forecast by an average of 3.4°F with a dew point below forecast by an average of 1.4°F • Friday saw the closest correlation between the weather and load forecast with very high temperatures and dew points throughout New England

  4. Capacity Deficiency Event Summary (*) = Actions of OP#4 that were not implemented in Maine due to transmission constraints Operating Procedure #4 “Action During a Capacity Deficiency” (OP-4) implemented on July 19 due to generator reductions and transmission constraints.

  5. Capacity Deficiency Event Summary, cont. • On Friday forecasted an operating reserve deficiencyof 449 MW based on the load forecast of 27,850 • Peak hour generator reductions and outages totaled 4,611 MW • Peak hour (Hour Ending 17) imports were as follows:

  6. Capacity Deficiency Event Summary, cont. • Forecasted temperature in Hartford and Boston was 99°F. • Sixth consecutive day with temperatures climbing above 90 degrees in New England • Actual temperatures in Boston were as forecasted. Temperature in Hartford was slightly lower. • Expected schedule of net deliveries for the peak hour were 1,718 MW. The actual scheduled net deliveries were 2,677 MW

  7. Capacity Deficiency Event Summary, cont. • Just prior to noon, operating reserves became deficient • OP#4 Action 1 was declared at 12:00 allowing for the depletion of 30 minute reserves and notification to all resources to be prepared to provide capacity up to Capacity Supply Obligation • At 13:00, Action 2 was declared (excluding Maine) dispatched all Real Time Demand Resources (193 MW) • At 14:20, Action 3 of OP#4 was declared requesting Market Participants to conserve energy • At 15:00, Action 5 of OP#4 was declared in order to maintain ten minute operating reserves. 200 MW of Participant Emergency Energy Transactions were purchased in Hour Ending 16.

  8. System Load vs. Forecast on July 19

  9. System Load – Week of July 15 through July 19

  10. Daily Peak Load – Week of July 14

  11. Total Energy Consumed in July since 2001

  12. Summary of Demand Response Dispatch 193 MW Dispatched at 13:05 (performance measurement starts at 13:35) Demand Response dispatch cancelled at 20:35

  13. Demand Response Performance

  14. Generation by fuel type at peak

  15. Observations • Transmission Constraints from North to South locked in Northern Generation from getting to load centers • In past years, transfers from New Brunswick to New England have been low due to Point Lepreau outage and this is no longer the case • 6th hot day in a row (>90° F) • Generator reductions due to ambient air temperature and environmental issues • No transmission system facility failures • Adequate reactive resources to maintain transmission system voltages • System Operators at the ISO, LCCs, External Areas, Generating Designated Entities and Demand Designated Entities performed well and in a collaborative and coordinated fashion to maintain reliability of the system

  16. July 3rd DCS Event Highlights • Forest fires in James Bay area of Quebec in vicinity of 735 kV transmission right-of-way • Multiple transmission line trips coupled with losses of generation, load and exports • Four transmission lines tripped • Approximately 2,900 MW of Quebec generation rejected by NPCC Type 1 SPS • Approximately 3,500 MW of Quebec load tripped • Approximately 3,370 MW of exports to NYISO, ISO-NE, NBSO, and IESO tripped or ran back • New England lost approximately 1,750 MW of imports from HQ • New England recovered from the source loss in under 11 minutes • No SOL or IROL violations in New England • Reviewed contingency response of on-line and off-line resources

  17. Highlights (Continued) • Eastern Interconnection was able to sustain the loss of HQ Imports • System load was decreasing • Imports from HQ tripped over the course of several minutes • Length of disturbance allowed governor response and some level of AGC to mitigate the impact on Eastern Interconnection • Frequency decreased to a minimum value of 59.91 • TransÉnergie is working with NERC/NPCC to perform an event analysis

  18. New England Overview At 16:35 New England experienced a source loss of approximately 1,750 MW over 2 - 3 minutes Support via Simultaneous Activation of Reserve (SAR) was limited to initial loss of 1,500 MW due to imports lost in Ontario, New York, and New Brunswick Operating Reserves were distributed across many units due to the size of the largest source contingency and the operating response rates of available resources

  19. Exports from Hydro Quebec • Beginning around 16:35, Hydro Quebec exports across various interconnection ties either tripped or were reduced over the course of approximately 3.5 minutes • NYISO imports were reduced by 790 MW • Chateauguay-Massena 7040 was reduced from 1,400 MW to 700 MW • Cedars was reduced from 190 MW to 100 MW • ISO-NE imports were reduced by 1,750 MW • One Pole of Phase 2 tripped, then approximately 1.5 minutes later the second Pole tripped, total loss 1,547 MW • Highgate reduced from 216MW to 0 MW • IESO imports were reduced by 500 MW • Outaouais reduced from 1,020 MW to 500 MW • NBSO imports were reduced by 380 MW • Madawaska reduced from 280 MW to 0 MW • Eel River reduced 80 MW

  20. Event Overview – Initial Conditions * Hourly forecast for Hour Ending 17 System Conditions at the time of the contingency:

  21. Initiating Event

  22. Satellite View of Fires Source:http://cdn.physorg.com/newman/gfx/news/hires/2013/forestfiresn.jpg Approximate Transmission Path

  23. Timeline

  24. Recovery Actions • Desired Dispatch Points (DDP) were sent to 57 Generators via Electronic Dispatch to increase output for a total of 1,495 MW • 19 startups for a total of 952 MW • 38 online units for a total of 543 MW • At 16:41, due to the loss of Highgate, a second emergency dispatch was sent to 96 Generators via Electronic Dispatch to increase output for a total of 1,962 MW. • 47 startups for a total of 1,542 MW • 49 online units for a total of 420 MW • ACE was restored to its pre-contingent value at 16:46 • Additional resources were called due to expected resource cuts from neighbors due to other losses from HQ

  25. ACE Recovery

  26. Interconnection Frequency

  27. Generator Response • Summary of generator response to second emergency dispatch • Of the 47 start ups: • 1,542 MW dispatched • 1,484 MW produced • 58 MW deficiency • 6 failed to start within 10 minutes • Of the 49 online units: • 420 MW dispatched • 77 MW produced • 342 MW deficiency

  28. Summary • Loss of 1,750 MW • Recovery in under 11 minutes • No SOL or IROL violations • HQ event undergoing event analysis • Reviewing the generator non-response with the impacted Designated Entities