APM Terminals POTI. Gateway to The Caucasus and Central Asia. APMT Poti today – General data. ● Water area – 65.34 ha; ● Length of approach channel – 1.6 km; ● Length of breakwater – 1.8 km; ● Operating area – 30.0 ha; ● Total Capacity – 10 million ton;
E N D
APMT Poti today – General data ●Water area – 65.34 ha; ● Length of approach channel – 1.6 km; ●Length of breakwater – 1.8 km; ● Operating area – 30.0 ha; ● Total Capacity – 10 million ton; ● Total length of berth’s – 2.9 km; ● Total length of railway - 17.0 km; ● Direct access to hinterland ways; ● 100 hectare of development area; ● General and Break bulk Cargoes; ● Conventional and Project Cargoes; ● Liquid Cargoes; ● RO-RO and FERRY Terminals; ● Container Terminals; ● Multi-Purpose Terminal;
Oil terminal ● Berth’s 1 and 2; ● Length – 383 m; ● Depth – 12.5 m; ● Storage Capacity – 110 000 tons; ● Light Oil; ● Chemicals; ● Gasoline; ● Diesel and etc;
Ro-Ro & Ferry terminal ● Ro-Ro & and Ferry terminal; ● Length – 183 m; ● Depth – 12.5 m; ● Storage Capacity – 6 500 sq. m; ● Poti – Illiychevsk , Kerch (Ferry Line); ● Poti – Kavkaz (Ferry Line); ● Poti – Varna (Ferry Line); ● Poti – Bourgas (RO-RO Line); ● Poti – Novorossiysk (RO-RO Line);
Container & Multipurpose terminal ● Berth 14; ● Length – 253 m; ● Depth – 8.4 m; ● Storage area – 13 200 sq. m; ● Berth 7; ● Length – 221 m; ● Depth – 8.2 m; ● Storage area – 16 300 sq. m;
Shipping Lines – Container traffic 2010 2009 2008 2010 2009 2008 2010 2009 2008 2010 2009 2008 2010 2009 2008 2010 2009 2008
Objectives & Goals ● Rehabilitation of existing port infrastructure and developing new territories for expansion; ● Improvement of handling technologies in order to provide better services; ● Develop value added services;