Project Life Cycle. Minimum time to complete. 6 Months. Preliminary Engineering Environmental Clearance Permitting. Design Detailed Design (18 mo) Land Acquisition (3 mo) Railroad Rights of Way (1 mo) Utility Relocation (3 mo) Local Agreements with Counties
E N D
Project Life Cycle Minimum time to complete 6 Months • Preliminary Engineering • Environmental Clearance • Permitting • Design • Detailed Design (18 mo) • Land Acquisition (3 mo) • Railroad Rights of Way (1 mo) • Utility Relocation (3 mo) • Local Agreements with Counties • & Municipalities (1 mo) 24 Months Time 2 Months • Public Comment (15 days) • Federal Authorization (1-3 wks) • Advertise for Bid (3 wks) Shovel Ready (minimum time 32 months) 8 Months Construction • Priority to Projects expected to be completed within 3 years (2/17/12) • 50% Obligated within 120 days (8/17/09) • From H.R. 1-92 • Remaining 50% Obligated within 1 Year (2/17/10)