1 / 42

Chapter 12 Risk Topics and Real Options in Capital Budgeting and Cash Flow Estimation

Chapter 12 Risk Topics and Real Options in Capital Budgeting and Cash Flow Estimation. Cash Flows as Random Variables. “Risk” in every day usage: the probability that something bad will happen “Risk” in financial theory: Associated with random variables and their probability distributions.

affrica
Download Presentation

Chapter 12 Risk Topics and Real Options in Capital Budgeting and Cash Flow Estimation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 12 Risk Topics and Real Options in Capital Budgeting and Cash Flow Estimation

  2. Cash Flows as Random Variables • “Risk” in every day usage: the probability that something bad will happen • “Risk” in financial theory: Associated with random variables and their probability distributions

  3. Cash Flows as Random Variables • Risk – the chance that a random variable will take on a value significantly different from the expected value • In capital budgeting the future period's cash flow estimate is a random variable

  4. Figure 12-1 The Probability Distribution of a Future Cash Flow as a Random Variable

  5. Cash Flows as Random Variables • The NPV and IRR are random variables with their own probability distributions • Actual value may be different than the mean • The amount the actual value is different from expected is related to the variance or standard deviation

  6. Figure 12-2 Risk in Estimated Cash Flows

  7. The Importance of Risk in Capital Budgeting • Until now we have viewed cash flows as point estimates – a single number rather than a range of possibilities • Actual cash flows are estimates, a wrong decision could be made using point estimates for NPV and IRR • The riskiness of a project's cash flows must be considered

  8. Figure 12-3 Project NPVs Reflecting Risky Cash Flows

  9. The Importance of Risk in Capital Budgeting • Risk Aversion • Changing the Nature of a Company • A company is a portfolio of projects • Ignoring risk when undertaking new projects can change the firm’s overall risk characteristics

  10. Scenario/Sensitivity Analysis • Select a worst, most likely, and best case for each cash flow • Recalculate the project's NPV (or IRR) under several scenarios • Gives an intuitive sense of the variability of NPV • Also called sensitivity analysis

  11. Concept Connection Example 12-1 Scenario Analysis

  12. Concept Connection Example 12-1 Scenario Analysis

  13. Decision Tree Analysis • Decision Tree: A graphic representation of a project in which certain events have multiple outcomes • Decision Tree Analysis – Develops a probability distribution of NPV given the probabilities of certain events within the project

  14. Computer (Monte Carlo) Simulation • Assume separate probability distribution for each cash flow • Computer draws observation from each and calculates NPV • Sort outcomes into histogram of probability distribution of NPV (next slide) • Drawbacks • Probability distributions are difficult to estimate • Cash flows tend to be correlated • Interpretation of results is subjective

  15. Figure 12-4 Results of Monte Carlo Simulation for NPV

  16. Figure 12-5 A Simple Decision Tree

  17. Concept Connection Example 12-2 Decision Tree Analysis The Wing Foot Shoe Company is considering a new running shoe. A market study indicates a 60% probability that demand will be good and a 40% chance that it will be poor. C0 is $5M. Cash inflows are estimated at $3M per year for three years at full manufacturing capacity if demand is good, but just $1.5M per year if it’s poor. Wing Foot’s cost of capital is 10%. Develop a rough probability distribution for NPV.

  18. Concept Connection Example 12-2 Decision Tree Analysis A decision tree diagram and NPVs along each path are: NPV 0 1 2 3 $2.461M $3M $3M $3M P = .6 ($5M) $-1.270M P = .4 $1.5M $1.5M $1.5M The expected NPV is: The decision tree explicitly calls out the fact that a big loss is quite possible, although the expected NPV is positive.

  19. Figure 12-6 A More Complex Decision Tree

  20. Concept Connection Example 12-3 More Complex Decision Trees Wing Foot now feels there are two possibilities along the upper branch. If first year demand is good, there’s a 30% chance it will be excellent in the second and third years, and a $1 million factory expansion will generate cash inflows of $5 million in years 2 and 3. That means net cash inflows will be $4 million in year 2 and $5 million in year 3. A decision tree for the project with this additional possibility is on the next slide

  21. Concept Connection Example 12-3 More Complex Decision Trees The NPV for the new upper path is

  22. Concept Connection Example 12-3 More Complex Decision Trees

  23. Concept Connection Example 12-3 More Complex Decision Trees

  24. Concept Connection Example 12-3 More Complex Decision Trees The project’s probability distribution expected return are as follows.

  25. Real Options • An option is the right or ability to take a certain course of action • A real option is a course of action that usually • Improves financial results under certain conditions • Exists in a real, physical business sense • Frequently occurs in capital budgeting • Generally increases a project's expected NPV

  26. The Abandonment Option • A poorly performing project can sometimes be abandoned • Usually by redeploying project resources to another use • Avoids continuing losses along a decision tree path • It usually takes planning early in a project’s life to preserve an abandonment option

  27. Valuing Real Options • Real Options usually • have definite costs early in projects • Create additional income along only one path • The chance of more income increases NPV • An option’s value is at least the increase in NPV less the option’s cost • But the real option may be worth more if it also reduces project risk (e.g. abandonment )

  28. Valuing Real Options • The Risk Effect is Tricky – • Not all real options have a risk effect • To lower risk an option has to reduce a potential loss not make a success better • A case by case analysis is necessary • An Approach Through Rate of Return • If lower risk is associated with a lower rate of return in NPV calculations, the result is higher NPV

  29. Designing Real Options into Projects • Abandonment option • Usually increase NPV and lower risk • Contract obligations can make abandonment tough • Expansion options • Often require little or no early commitment • Should be planned in whenever possible • Investment timing options • Permit delaying investment until more certain about surrounding issues • Flexibility options • Preserve ability to respond to changing business conditions

  30. Incorporating Risk Into Capital Budgeting • For NPV • k is used as the discount rate • A higher k leads to lower NPV reducing the chance of project acceptance • For IRR • Compare IRR to k • A higher k leads to a lower chance that IRR>k reducing probability of project acceptance The cost of capital (k) plays a key role in both NPV and IRR.

  31. Incorporating Risk Into Capital Budgeting • Riskier Projects Should Be Less Acceptable • Using a higher, risk-adjusted rates for risky projects lowers their chance of acceptance • The Starting Point for Risk-Adjusted Rates is the firm’s current risk level reflected in its cost of capital

  32. Incorporating Risk Into Capital Budgeting • Relating Interest Rates to Risk • Interest rates are comprised of a base rate plus a risk premium • Investors demand a higher risk premiums  higher interest rates if they are to bear more risk • In capital budgeting the company is the investor

  33. Incorporating Risk Into Capital Budgeting • Choosing the Risk-Adjusted Rate for Various Projects • An arbitrary, subjective process • Three categories of increasing risk • Replacements – low risk, use cost of capital • Expansion projects - slightly more risky than the current level • New ventures – generally involve a lot more risk

  34. Estimating Risk-Adjusted Rates Using CAPM • The project as a diversification • If viewed as a collection of projects, a new venture diversifies the firm • A new venture also diversifies the stockholders’ investment portfolios

  35. Estimating the Risk-Adjusted Rate Through Beta • The Security Market Line (SML) can be used to determine a risk-adjusted rate for a new venture • SML: kx = kRF + (kM - kRF) bX • bX = beta = the measure of a company's systematic risk • If a project is viewed as a business in a particular field, use a beta common to that field to estimate a risk-adjusted rate for project analysis

  36. Estimating Risk-Adjusted Rates Using CAPM • The project as a diversification • Diversifiable and non-diversifiable risk for projects • Projects have two levels of diversifiable risk • Some risk diversified away within the firm's portfolio of projects • Some risk diversified away by the shareholders' investment portfolios • The remaining risk is systematic risk

  37. Figure 12-7 Components of Project Risk

  38. Concept Connection Example 12-6 Risk-Adjusted Rates - SML • Orion Inc. makes radio communications equipment. • beta = 1.1 cost of capital = 8% • Considering a venture into risky military radios. • Military radio market is dominated by • MilradInc. - 60% market share, beta = 1.4 • AntexRadio Corp. - 20% market share, beta = 2.0 • Both make only military radios. • kM = 10% , kRF = 5%. • C0 = $10M, Ci= $3M n = 5 years • Should Orion undertake the project?

  39. Concept Connection Example 12-6 Risk-Adjusted Rates - SML Calculate the risk-adjusted rate for the project: k = 5% + (10% - 5%)2.0 = 15.0% Then calculate the project's NPV using the 15% risk-adjusted rate: NPV = -$10.0M + $3M[PVFA15,5] = -$10M + $3M[3.3522] = $0.1M NPV at Orion’s own 8% cost of capital is $2.0M clearly indicating acceptance. Adjusted for risk, however, the project is marginal . This is a crucial insight! Since the NPV is barely positive, the project is marginal at best.

  40. Problems with the Theoretical Approach • It is often difficult to find a pure play firm from which to obtain an appropriate beta • If a pure play division is found within a corporation, estimate the beta of that division using the accounting beta method • Systematic risk may not be only important risk • If total risk is important, an even higher risk-adjusted rate would be appropriate

  41. Certainty Equivalents (CE) • For every cash flow management develops a lower risk free (certain) figure that is as attractive as the forecast risky figure. • Then calculate a risk adjusted NPV or IRR with those cash flows • Alternatively choose a CE factor (0< 1) for each cash flow and multiply. • CE factors generally decline as they proceed further into the future

  42. A Final Comment on Risk in Capital Budgeting • Virtually every firm of any size uses capital budgeting techniques • But few explicitly include risk • Business managers do recognize risk but they do it through subjective judgments

More Related