An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The New Library for Trinity – an exercise in Space and Time? Trevor Peare, Keeper (Systems) New Library Project Officer Trinity College Library

  2. James Ussher 1581 - 1656 First day of creation: Sunday 23 October 4004 BC

  3. A New Library for Trinity A little background ...

  4. A New Library for Trinity Year Students 1960 2,833 Berkeley '67 1970 4,428 Lecky '78 1980 6,623 1990 9,267 Hamilton '92 2000 14,750 Ussher '01

  5. A New Library for Trinity Year Volumes 1960 1.4 M 1970 1.9 M Santry I ('74) 1980 2.5 M Santry II ('86) 1990 3.2 M Santry III ('91) 2000 4.0M Santry IV ('98)

  6. A New Library for Trinity To provide: 700+ additional readers' places 350,000 additional open access volumes Integrated ICT of course!

  7. A New Library for Trinity • 1996 'Idea' developed • 1997 Library visits Architectural Brief • 1998 Architects appointed • 1999 Work on site starts

  8. A New Library for Trinity Issues identified during visits:  Separation of books and readers  Flexibility v. Environment  Finishes for surfaces important  IT wiring throughout  Staff areas

  9. A New Library for Trinity • The Brief: • 650 - 700 additional reader places • 350,000+ additional volumes on open access • Integration of IT and traditional use • Single point of focus for services • Linking of three library buildings

  10. The Site

  11. A New Library for Trinity Reality sets in! Map Library to be included Conservation Laboratory out/in Budget restraints

  12. Map Library

  13. The Gateway Profile 3

  14. A New Library for Trinity Progress Report Handover date - ? October 2001 Partial occupation by December Berkeley Refurbishment 2002 All done Autumn 2002 ?

  15. 15 August 2001

  16. A New Library for Trinity Berkeley Refurbishment Significant work Remodeling entrance area Iveagh Hall and Basement transformed Lecky Library reorganised

  17. Berkeley Entrance area

  18. Iveagh Hall

  19. A New Library for Trinity What will the user experience? Good study environment Integration of Printed and Electronic material Easier access for HEA visitors

  20. A New Library for Trinity Watch it happen at: www.tcd.ie/Library/LIRC/

  21. A New Library for Trinity Acknowledgments Anne Walsh Robin Adams for supplying the numbers!

  22. A New Library for Trinity More information from: tpeare@tcd.ie Trevor Peare, Keeper (Systems) New Library Project Officer Trinity College Library

  23. A New Library for Trinity More information from: tpeare@tcd.ie Trevor Peare, Keeper (Systems) New Library Project Officer Trinity College Library

  24. A New Library for Trinity More information from: tpeare@tcd.ie Trevor Peare, Keeper (Systems) New Library Project Officer Trinity College Library

  25. A New Library for Trinity More information from: tpeare@tcd.ie Trevor Peare, Keeper (Systems) New Library Project Officer Trinity College Library

More Related