1 / 33

What you need to know about handling major school works 5 th July 2013

What you need to know about handling major school works 5 th July 2013. Topics for Discussion. Who are we? People Buying Process Lessons learnt. Design. Construction. Built Environment Services. Facilities Management. Building Consultancy. Community & Leisure. Energy. Investment.

ahalverson
Download Presentation

What you need to know about handling major school works 5 th July 2013

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. What you need to know about handling major school works 5th July 2013

  2. Topics for Discussion Who are we? People Buying Process Lessons learnt

  3. Design Construction Built Environment Services Facilities Management Building Consultancy Community & Leisure Energy Investment

  4. Established 2006 Focus on North East and Education Best practice services Maintaining buildings for approx 40,000 children Spent over £300m with North East businesses Who are we?

  5. Size Complexity Value Disruption – Business Continuity & Health & Safety risks What is a major project?

  6. PEOPLE

  7. Who’s who?- The client team Key Authority Visioning

  8. Who’s who? – Client representative • ‘Special one’ – deliver on demand • Time

  9. ‘Intelligent Client’ – level of technical knowledge and expertise How much technical knowledge does the Client Representative need? External Support Who’s who? – Client representative

  10. Who’s who?- External

  11. Who’s who - External LANDSCAPE ARCHITECT ACOUSTIC ENGINEER OTHER SPECIALISTS HIGHWAYS ENGINEER

  12. Who to work with? - Selection • Identify a short list • Key Points: • References • Bid Documents • Interviews • Evaluation • Feedback

  13. BUYING

  14. What to Consider . . . What do you want to achieve as a result of the project . . . ? Consider Long Term, Mid Term & Short Term goals What is your Vision in terms of education. . .? not just the physical requirements What is your school’s pedagogy, ethos . . . ? Should be enhanced/reflected in the built solution Challenge initial pre-conceived ideas . . . Additional space/new build isn’t always required Consider alternative options: remodel/refurb Programme and Construction Is phasing of work required/possible, avoid decant Translating Visions into Plans Developing the Brief A clear Vision translates into A clear Brief . . . Not what you physically want to do but what you want to achieve . . .

  15. Translating Visions into Plans

  16. Procurement route

  17. Choose carefully! No construction project is the same OJEU - £4,348,350 works £113,057 services CDM – 30 days or 500 man hours Risk Procurement route

  18. Typical risks Programme slippage Funding Accuracy of cost plan Design changes\clashes Accuracy of client information Delay in sign off Site conditions Changes in legislation Delay to planning Inflation Availability of materials Market conditions RISK

  19. Procurement route – Traditional Key Main Legal Relationship Communications

  20. Advantages Disadvantages Procurement route – Traditional

  21. Procurement route – D&B Key Main Legal Relationship Communications

  22. Advantages Disadvantages Procurement route – D&B

  23. Process

  24. RIBA –Stages of work

  25. Stage A • Establish Team • Vision in Place • Stage B • Appoint Design Team • Feasibility • Surveys

  26. Stage C • Outline Design • Initial Cost Plan • CDM • Risk, Risk, Risk

  27. Do you understand how much it will cost to run your building? Capital v Whole Life Cost Aftercare

  28. Aftercare

  29. Identify operational costs and when they occur Utilities Planned maintenance Replacement Repair Sub contracts Training Aftercare

  30. Snags, Defects Liability & Latent Defects Snags couple of months from hand over Defects liability – 12 months from hand over Latent Defects – Up to 12 years from hand over Aftercare

  31. Attitude Single point responsibility Decant Work to one programme Furniture Fittings & Equipment Lessons Learnt Emirates Stadium Wembley Stadium

  32. Summary Find your ‘Special One’ and support them Pick the right team & procurement route Put time into vision & design brief Understand aftercare

  33. Questions? Aura Level 4, West Tower Baltic Place, South Shore Road Gateshead NE8 3AE www.auranortheast.com

More Related