An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Laredo Bridge System Budget Presentation FY 2009-2010

  2. Budget Highlights FY 08-09 • $6 million shortfall of revenues, 13% • Reduced operating budget - $6 million • Meet 15% required fund balance, $1.7 million FY 09-10 • Revenues and expenditures are similar to FY08-09 • Deleted $6m from proposed budget • Deleted 11 positions, unfunded 17 positions • Meet 15% required fund balance of $1.8 million • No rate increase proposed

  3. REVENUECOMPARISONS

  4. Estimated Revenue FY08-09 $46,564,504 $40,511,119 -$6,053,485 -13 % Budget FY08-09 Estimated FY08-09

  5. Proposed Revenue FY09-10 $40,511,119 $40,510,627 -$492 +.00 % Estimated FY08-09 Proposed FY09-10

  6. 5 Year Revenue Comparison $45,576,258 $39,101,761 $40,511,119 $40,510,627 $33,069,032 $38,051,562 +19.8% +18.2% - 13 % +0% - 2.7 % Proposed Estimated FY 04-05 FY 06-07 FY 09-10 FY 08-09 FY 05-06 FY 07-08 $1.00Increase Comm. & .40¢ Increase AVI toll rate Decrease in Non-Comm & Commercial 50¢ Increase Non-Com & Increase Com. Traffic Decrease in Pedestrian & Non-Comm. Decrease in Non-Comm & Commercial

  7. TRAFFIC COMPARISONS

  8. Yearly Commercial Traffic 1,699,732 1,662,549 1,608,566 1,384,975 1,384,975 - 2% -37,183 -3.2% -14 % -53,983 -223,591 FY 08-09 Estimated F`Y 09-10 Proposed FY 05-06 FY 06-07 FY 07-08

  9. Border City Commercial Traffic ComparisonAs of May 31, 2009 33,428 - 24.3% 53,888 132,023 193,265 916,553 - 18.6% - 18.4% 274,611 - 15.2% - 13.9% 23,887 - 11.4% + .28% Del Rio Eagle Pass Laredo McAllen Brownsville El Paso Pharr

  10. Yearly Non-Commercial Traffic 6,075,453 5,718,799 5,539,281 -355,654 5,018,589 5,018,589 -179,518 - 6% -520,692 - 3.1% - 9.4% FY 07-08 FY 08-09 Estimated FY 05-06 FY 06-07 FY09-10 Proposed

  11. BorderCity Non-Commercial Traffic Comparison As of May 31, 2009 2,395,190 -14.8% 2,617,840 3,407,780 3,024,607 -13.6% 996,636 -9.4% -9.4% 1,799,328 1,074,171 -7.48% -5.1% -3.7% Del Rio Pharr El Paso Brownsville Laredo McAllen Eagle Pass

  12. Yearly Pedestrian Traffic 4,362,476 200,953 4,157,440 4,157,440 +4.8 4,161,523 4,137,543 +23,980 -205,036 + .60% - 4.7% FY 08-09 Estimated FY 09-10 Proposed FY 07-08 FY 05-06 FY 06-07

  13. Border City Pedestrian Traffic Comparison As of May 31, 2009 40,323 1,248,915 10.8% -7.1% 451,960 3,430,866 2,814,147 -4.6% -4.7% -5.2% 1,070,673 -.31% El Paso McAllen Brownsville Laredo Eagle Pass Del Rio

  14. Santa Ursula Connector

  15. World Trade BridgeInspection Station Expansion Project

  16. Thank You. Mario Maldonado Bridge Manager