Hospital Revitalization Grant Infrastructure Performance Review : Western Cape April-September 2010. Presentation to Select Committee on Appropriations 20 October 2010. Hospital Revitalization Grant Presentation Outline.

ailani
Download Presentation

Presentation to Select Committee on Appropriations

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Hospital Revitalization Grant Infrastructure Performance Review : Western Cape April-September 2010 Presentation to Select Committee on Appropriations 20 October 2010

  2. Hospital Revitalization GrantPresentation Outline • Programme Overview • Budget spending for first two quarters • Expected Budget Performance for year • Inter-departmental Reporting and Co-ordination • Performance of Contractors & Consultants • Project Monitoring and Co-ordination • Capacity to implement HRP Grant programme

  3. Hospital Revitalization GrantProgramme Overview • 3 Projects completed (in retention, final account) • 7 Projects under construction • 3 Projects in planning

  4. Hospital Rationalization Grant: Budget spending for first two quarters 2010/11

  5. Hospital Revitalization GrantExpected Budget Performance for 2010/11

  6. Hospital Revitalization GrantInter-departmental Reporting and Co-ordination Projects • Site visits by DTPW project team at least once a month • Monthly project site meetings (DTPW, DoH, Contractor and Consultants) • Rational Programme Management (RPM) system for recording project Programme • Monthly progress meetings information and progress between DTPW, DoH and Treasury • Daily informal contact • Monitoring by Treasury with reports to National

  7. Hospital Revitalization GrantPerformance of Contractors and Consultants • Good contractor performances in general • Quality – strictly controlled • Adherence to programme – mostly on schedule - Khayelitsha and Mitchell’s Plain: early completion - Vredenburg Ph 2A: slight delay expected - Worcester Ph 4: lagging - JV seems to be problematic • Consultants generally competent • Input / guidance required from DTPW professionals varies across disciplines and projects

  8. Hospital Revitalization GrantProject Monitoring and Co-ordination • Co-ordination between Principal Agent (or Project Manager on larger projects) and internal Project Co-ordinator • DoH Project Manager • Clerk of Works provides daily on site quality control and co-ordination with DoH Project Manager and Principal Agent

  9. Hospital Revitalization GrantProgramme Implementation Capacity • Sufficient capacity for HRP Programme • Large number of capital projects places professional staff under high work load stress. • Micro-structure being finalised - IDIP assessment of capacity requirements - HR Plan Developed to increase built sector professional staff • Architectural –Fully staffed • Quantity Surveying – fully staffed • Electrical Engineering – two vacant posts • Mechanical Engineering – two vacant posts • Civil & Structural – two vacant posts • Number of built sector professionals have been appointed additional to the establishment in order to attend to the internal capacity