1 / 17

Plan of EMMA commissioning 1 shifts in Run #3

Plan of EMMA commissioning 1 shifts in Run #3. Shinji Machida o n behalf of the beam commissioning team ASTeC /STFC/RAL 29 July 2010. Beam time. Run #1: 20-23 June 2010 Run #2: 12-15 July 2010 Run #3: 27-29 July 2010 Run #4: 4-6 August 2010 (full ring)

aimee
Download Presentation

Plan of EMMA commissioning 1 shifts in Run #3

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Plan of EMMA commissioning1 shifts in Run #3 Shinji Machida on behalf of the beam commissioning team ASTeC/STFC/RAL 29 July 2010

  2. Beam time • Run #1: 20-23 June 2010 • Run #2: 12-15 July 2010 • Run #3: 27-29 July 2010 • Run #4: 4-6 August 2010 (full ring) • Run #5: 12-15 August 2010 full ring • (Run #6: 18-24 August 2010) • Run #7: 30 August – 2 September 2010 rf available • Run #8: 7-10 September • Run #9: 15-18 September • Run #10: 24-26 September • Run #11: 2-3 October • Run #12: 10-13 October

  3. Plan backward • At the end of Run #5 (15 August), • A full lattice which accepts a fixed momentum beam from 10.5+a to 20.5-b [MeV/c]. • Know time of flight in that momentum range. • At the end of Run #4 (6 August), • Know a way to injection a beam for some equivalent momentum range. • Measure cell tune vs relative momentum. • At the end of Run #3 (29 July), • Understand injection orbit for fixed momentum.

  4. Four main lattice parameters (1) • We do not know calibration factor of strength and position of QD and QF. • With fixed QD/QF ratio, strength of QD and QF is equivalent to beam momentum. • Cell tune is sensitive to strength of QD and QF, but insensitive to position.

  5. Four main lattice parameters (2) • With fixed QD/QF ratio (as designed) • Injection a beam. • Minimize betatron oscillations with septum and kickers. • Measure cell tune. • (Measure time of flight.)

  6. Four main lattice parameters (3) • Change strength of QD and QF keeping QD/QF fixed • Injection a beam. • Minimize betatron oscillations with septum and kickers. • Measure cell tune. • (Measure time of flight.)

  7. Four main lattice parameters (4) • Previous procedures give • Cell tune vs “relative” momentum. • Time of flight vs “relative” momentum. • Notice we never know absolute measure of x-axis (momentum). • This is not because we use “equivalent” momentum beam. • This is because we do not know calibration factor of strength and position of QD and QF.

  8. Four main lattice parameters (5) • Determine absolute momentum by looking at cell tune experimentally. • With the fixed range of momentum, change position of QD and QF to obtain desired time of flight curve. • If we do not have a good solution, back to the beginning and try another QD/QF ratio.

  9. From previous measurements (1)kicker • Measured kicker-1 strength agrees with design. • Polarity is correct (kick outside.) • No information on kicker-2. • Assume calibration is correct (same as kicker-1). • Check polarity by BPM1 in S03.

  10. From previous measurements (2)septum • Measured (x, x’) at the exit of septum varies. However, this may be because (x, x’) at the entrance is not the same. • Do the measurement vs strength again with the same initial (x, x’), namely the centre of two quadrupoles. • No re-cabling is required up to here.

  11. Task in Run #3 (1)Initial BPM cabling • Use analog cable for BPM measurements. • BPM04-X&Y in IL (2 cable2) for injection orbit • BPM01, 02 in E01 (4 cables) for (x, x’) after septum • BPM01-X in E03 (1 cable) for kicker-2 calibration

  12. Task in Run #3 (2)with Initial BPM cabling • Orbit measurement at Q17 and Q18. • Vary Q18 current and measure H&V at BPM04. • Q18 is off. Vary Q17 current and measure H&V at BPM04. • (x, x’) measurement at septum exit. • QD/QF is off. Measure (x, x’) with BPM-01,02 in E01. • Vary septum strength and rotation to make design value (at least closer).

  13. Task in Run #3 (2b)with Initial BPM cabling • (x, x’) measurement at septum exit. Simple geometrical estimate gives • +18 mrad per 1 degree rotation • -10 mm per 1 degree rotation • D(angle) = DB/B

  14. Task in Run #3 (3)with Initial BPM cabling • Kicker 2 polarity and calibration. • QD/QF is on. Vary kicker 2 and measure BPM-01 in E03. • Then, change the cable connection during a shift.

  15. Task in Run #3 (4)Initial setting of magnets • QD/QF: 260/220 A, based on Ben’s measurement. • It is not 50% more as Scott recommended, but we will try to increase it further. • K1/K2: -34.5/-40.7 mT, 45 mT corresponds to 6.6 V(?) • Septum: based on the repeated measurement.

  16. Task in Run #3 (5)Understand injection • BPM re-cabling: BPM1 in S03, S04, S05, S06, S07, S08, S09. Sxx is Yuri’s naming at May 2009 commissioning meeting. • Use kicker 1 and 2 only to minimize betatron oscillations.

  17. Task in Run #3 (6)Measure cell tune and tof • With minimized betatron oscillations, measure time of flight. • With small betatron oscillations, measure cell tune.

More Related