EMMA Commissioning Milestones 5 July 2010

EMMA Commissioning Milestones 5 July 2010. Hardware Installation Milestones. 4 sector installation - complete Target dates Full ring installation and testing – 30 July Diagnostic beamline phase 1 – 30 July

Download Presentation

EMMA Commissioning Milestones 5 July 2010

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EMMA Commissioning Milestones 5 July 2010

  2. Hardware Installation Milestones • 4 sector installation - complete Target dates • Full ring installation and testing – 30 July • Diagnostic beamline phase 1 – 30 July • RF installation and testing by – 31 Aug (Commissioning with ITEC from 18 Aug …..) • Diagnostic beamline phase 2 – 30 Sep • Would need to open the ALICE equipment wall before to get the long diagnostic beamline modules into the area 2 day shutdown towards the end of Aug Assumptions • Access to accelerator on weekdays • all July, • Most of August • 50 – 50 in September and October • ALICE long shutdown starts on 18th October • Need to fold into plan EMMA ring quadrupole survey – Jul or early Aug • 5 day shutdown

  3. Commissioning Milestones http://projects.astec.ac.uk/EMMAManual/index.php/EMMA_ring_setup_work_package • 2.1 Four-sector commissioning - July • 2.2 Inject a beam and establish a stable orbit - August • 2.3 Circulation of a beam for more than 10 turns - August • 2.4 Capture a beam in an rf bucket - September • 2.5 Serpentine acceleration and write a letter (PRL) - September • 2.6 Output of accelerator physics experiments and publication of some results • 2.7 Extraction of a beam - October

  4. Shift Request • July injection line and 4 sector • 12 shifts • 12 - 15 July: shift 3 (Mon, Tue, Wed, Thu) • 19 - 22 July: shift 3 • 26 - 29 July: shift 3 • August EMMA ring commissioning without RF • 14-18 shifts. Prefer shift 3+ of Mon, Tue, Wed, Thu • September – October 18 • 22 - 26 shifts. Prefer shift 3+ of Mon, Tue, Wed, Thu