HAM-71-3.81 (PID 77628) I-71 & Martin Luther King Interchange UpdateCincinnati Regional Business Committee MeetingFebruary 3, 2014 4:00pmQueen City Club
Roadmap For Today • I-71 & MLK Project Overview • Project Delivery Strategy
Uptown is home to The region’s only two Level 1 Trauma Centers Five ER’s Seven Hospitals • More than 20,000 jobs
Uptown is home to The University of Cincinnati • More than 40,000 students Cincinnati State Technical and Community College • More than 20,000 students
Uptown is home to Cincinnati Zoo and Botanical gardens • More than 1.4m visitors annually The US Environmental Protection Agency (EPA) • Second largest research facility in the US
A Truly Regional Project 20,000 Outside Hamilton County 60,000 Jobs in Uptown 5,700From Northern KY 82% Outside City Limits Source: Mark Policinski with OKI
MLK Blvd .
Project Benefits • Cut 3-4 minutes off of EMS response • University Hospital • Children’s Hospital • Promote economic development • 5,900-7,300 additional permanent jobs • $325m in private investment UC Economics Center Study, May 2012
It starts with Advocacy
Advocacy Inspires Leadership
a powerful goal July 2014
Innovative Strategy • Two Step, Low Bid Design Build • Step 1: Short List • Step 2: Invitation to Bid • New Project Development Process (PDP) • Allows Right of Way Phase to overlap NEPA • Managed risk creates opportunity • Unique schedule for each parcel
Partnership Historic agreement between OKI and Cincinnati to take a SIB loan is paramount
Brute Force • HAM-71 & MLK is a top priority for all staff • Review times are condensed • Passive reviewers become active decision makers
Old PDP 14 Steps 5 years New PDP 5 Steps
Traditional Project 5 years Design Environmental Right of Way Construction 5 Years HAM-71 & MLK Design Environmental Right of Way Construction 14 months