1 / 8

Network Diagram and Critical Path

Avimanyu Datta. Network Diagram and Critical Path. Activity Duration and Preceding Activities. Some Key Definitions. ET: Estimated Duration TE: Earliest Expected Completion Time TE = Max [ TE (Previous Process) ] + ET (Current Processes)

airell
Download Presentation

Network Diagram and Critical Path

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Avimanyu Datta Network Diagram and Critical Path

  2. Activity Duration and Preceding Activities

  3. Some Key Definitions • ET: Estimated Duration • TE: Earliest Expected Completion Time TE = Max [TE (Previous Process) ]+ ET (Current Processes) • TL: Latest Expected Completion Time: Time in which an activity can be completed without delaying the project TL =Min[ TL (Later Process ) – ET (Later Process)] • SLACK = TL-TE. Zero Slack = Zero Flexibility.

  4. Network Diagram with ET D ET=4 A ET=1 H ET=6 E ET=5 B ET=2 J ET=3 F ET=4 C ET=3 I ET=2 G ET=6

  5. Network Diagram with ET and TE We take the TE from Process E rather than Process D. Because TE(E)> TE (D) START From HERE TE= 5 We take the TE from Process H rather than Process I or F. Because TE (H) >TE(I)> TE (F) D ET=4 TE= 1 TE = 13 A ET=1 H ET=6 TE = 7 E ET=5 TE = 2 TE= 16 B ET=2 J ET=3 TE= 6 F ET=4 TE = 3 C ET=3 TE = 11 TE = 9 I ET=2 G ET=6

  6. Network Diagram with ET and TE * We take TL from Process E rather that Process F because TL-ET for E is lover that that of F TE= 5 D ET=4 TE= 1 TL= 7 TE = 13 A ET=1 H ET=6 TL = 3 TE = 7 TL = 13 E ET=5 TE = 2 TE= 16 TL = 7 B ET=2 J ET=3 TL = 2* TE= 6 TL = 16 F ET=4 TE = 3 TL = 13 START From HERE C ET=3 TE = 11 TL = 5 TE = 9 I ET=2 G ET=6 TL = 13 TL=11

  7. Critical Process and Critical Path Path comprising of Process where Slack ( TL-TE) = 0 TE= 5 D ET=4 TE= 1 TL= 7 TE = 13 A ET=1 H ET=6 TL = 3 TE = 7 TL = 13 E ET=5 TE = 2 TE= 16 TL = 7 B ET=2 J ET=3 TL = 2 TE= 6 TL = 16 F ET=4 TE = 3 TL = 13 CRITICAL PATH I S B E H J C ET=3 TE = 11 TL = 5 TE = 9 I ET=2 G ET=6 TL = 13 TL=11

  8. Critical Path: Questions to Ponder upon • What is the importance of Critical Path? • How will you distribute your resources when you know the critical path? • What happens if process within a critical path is delayed?

More Related